ML20005F525

From kanterella
Jump to navigation Jump to search
Notification of 900104 Significant Licensee Meeting 89-207 in Plymouth,Ma to Discuss Licensee self-assessment of Power Ascension Program
ML20005F525
Person / Time
Site: Pilgrim
Issue date: 12/26/1989
From: Blough A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
NUDOCS 9001160359
Download: ML20005F525 (2)


Text

,

o. -.

=

NC is um U.S. NUCLEAR REGULATORY COMMISSIDH No.89-207 REGION I NOTICE OF SIGNIFICANT LICENSEE MEETING Licensee:

Boston Edison Company Facility:

Pilgrim Nuclear Power Station Docket No.:

50-293 Time and Date:

9:00 a.m., January 4, 1989 Location:

Boston Edison Company (BEco) Ch11tonv111e Training Center, Classroom 6A/B, Old Sandwich Road, Plymouth, Massachusetts

Purpose:

NRC Restart Assessment Panel Meeting /BECo Presentation on Their Final Self-Assessment of Their Power Ascension Program NRC Attendees:

W. Russell, Regional Administrator W. Kane, Director, Division of Reactor Projects (DRP)

J. Durr, Chief. Engineering Branch, Division of Reactor Safety (DRS)

R. Bellamy, Chief, Facilities Radiological Safety and Safeguards Branch, Division of Radiation Safety and Safeguards (DRSS)

J. Johnson, Chief, Projects Branch No. 3 DRP A. Blough, Chief, Reactor Projects Section 3A, DRP J. Macdonald, Senior Resident Inspector A. Cerne, Resident Inspector C. Carpenter, Resident Inspector B. Boger, Assistant Director for Region I Reactors, Office of Nuclear Reactor Regulation (NRR)

D. Wessman, Director, Project Directorate I-3, NRR D. Mcdonald, Project Manager, NRR T. Hiltz, Reactor Engineer, DRP Licensee Attendees: S. Sweeney, Chairman and Chief Executive Officer R. Bird, Senior Vice President, Nuclear K. Highfill, Vice President, Nuclear Operations and Station Director G. Davis, Vice President,. Nuclear Administration E. Wagner, Vice President, Nuclear Engineering R. Ledgett, Director, Special Projects R. Anderson, Plant Manager R. Swanson, Regulatory Affairs Department Manager R. Varley, Emergency Preparedness Department Manager F. Famulari, Quality Assurance Department Manager D. Long, Plant Support Department Manager D. Eng, Planning and Outage Manager E. Robinson, Nuclear Information Division Manager.

R. Fairbank, Nuclear Engineering Department Manager OFFICIAL RECORD COPY LIC MTG NOTICE 89-207 - 0001.0.0 12/20/89 d(g 9001160359 891226 PDR ADOCK 05000293 p

PNV

.e o

2 DEC 26 geg Note: Attendance by NRC personnel at this meeting should be made known by 4:00 p.m, December 29, 1989 via telephone call to A. Randy Blough, Region I, at FTS 8-346-5146 or (215) 337-5146.

l ORIGINAL SIGNED BY Prepared by:

A. Randy Blough, Chief, RPS 3A Distribution:

J. M. Taylor, Executive Director for Operations H. Thompson, Deputy Executive Director for Materials safety, Safeguards and Operations Support B. Grimes, Director, Division of Reactor Inspection and Safeguards, NRR J. Lieberman, Director, Office of Enforcement T. Murley, Director, Office of Nuclear Reactor Regulation F. Miraglia, Associate Director for Inspection and Technical Assessment, NRR S, Varga, Director, Division of Reactor Projects - I/II, NRR B. Boger, Assistant Director for Region I Reactors, NRR D. Wessman, Director, Project Directorate I-3, NRR O. Mcdonald, Project Manager, PD I-3, NRR J. Dyer, Regional Coordinator, EDO Public Document Room (PDR) local Public Document Room (LPDR)

Commonwealth of Massachusetts (2)

NRC Resident Inspector W. Griffin, Plymouth Board of Selectmem Honorable William B. Golden, Massachusetts State Senator bec:

Regional Administrator Deputy Regional Administrator Division Directors Branch Chiefs Section Chiefs Public Affairs Officer (2 copies)

J. McGrath, RI M. Miller, RI K. Smith, RI D. Holody, RI Region I Receptionist DRMA Files DRP Files Bulletin Board M. J. DiDonato, DRP D. Rathbun, OCA RI:DRP Blough/meo 12/20/69 0FFICIAL RECORD COPY LIC MTG NOTICE.89-207 - 0002.0.0 12/20/89