r O

1 BOSTON EDISON COMPANY D E N E m AL o FFIC E S B DO B ovLSTO N SYm EET BOSTON M ASS ACHUSETTS D2199 A. V. MO RIS S MANAGER NU CLEAR OPERAT10NS SUPPO RT DEPARTM ENT August 19, 1981 B ECo. Lt r.81-194 qo il I N g-4 s

Mr. Thomas A. Ippolito, Chief

. j, 4

g h6 Operating Reactors Branch #2

~

kg cl

7, [

Divison of Licensing

/

Office of Nuclear Reactor Regulation u,

U.S. Nuclear Regulatory Commission

//,

W

\\

Washington, D.C. 20555

'b/j7 (3

License No. DPR-35 Docket No. 50-293 REQUEST FOR AN EXTENSION CONCERNING INFORMATION REQUEST, UNRESOLVED SAFETY ISSUE A-44

Reference:

Infomation Request, NRC Letter of July 20, 1981 (BECo. Letter 1.81.198)

Dear Sir:

In the referenced letter, the Commission requested Boston Edison to answer the questionnaire attached to it within 120 days, or to supply a proposed completion date.

We have examined the questionnaire and would like to respond to it.

However, due to the work load imposed on us by the September,1981 Refueling Outage, we feel we could answer these questions in a more comprehensive manner by January 1, 1982.

We appreciate your consideration of this date. Should you have further questions regarding this matter, please contact us.

Very truly yours, N$

foO I

9 s

/!D 0109020310 810819 PDR ADOCK 05000293 F