TENNESSEE VALLEY AUTHORITY CH ATTANOOGA. TENNESSEE 374ot 400 Chestnut Street Tower II June 29, 1981 Director of Nuclear Reactor Regulation Attention:
Ms. E. Adensam, Chief Licensing Branch No. 4 Division of Licensing U.S. Nuclear Regulatory Commission Washington, DC 20555
Dear Ms.-Adensam:
'In the Matter of
)
Docket Nos. 50-327 Tennessee Valley Authority
)
50-328 My letter to H. R. Denton dated April 16, 1981 stated that the Sequoyah Nuclear Plant prompt notification system was expected to be installed and operational by July 1, 1981. We now expect to have about 80 percent of the sirens installed and operational by July 1, 1981 and to have the system fully operational by August 1, 1981.
If you have any questions, please get in touch with D. L. Lambert at FTS 857-2581.
Very truly yours, TENNESSEE VALLEY AUTHORITY L.'M. Mills, Man er Nuclear Regulation and Safety Sworn to ~ard sub ibed before me th s 19 ay o 1981 M? W NotgyPublic