O Ona First Nf tionni Plaza. Chicrgo, Ilknoc Commonwealth Edison Addrms Reply to: Post Office Box 767 Chicago, !!!inois 60690 June 5, 1981 Mr. Dennis M. Crutchfield, Chief Operating Reactor Branch 5 Division of Licensing U.
S. Nuclear Regulatory Commission Washington, D.C.
20555
Subject:
Dresden Unit 1 Schedule for Verification Test Concerning Adequacy of Station Electric Distribution System Voltages NRC Docket No. 50-10 Reference (a):
D.M. Crutchfield letter to J. S. Abel dated April 30, 1981.
Dear Mr. Crutchfiela:
Reference (a) provided the NRC Safety Eval'.ation concerning the adequacy of Dresden Unit i electric oistribution system voltages.
The aesign was found to be acceptable subject to the satisfactory completion of a confirmatory test similar to tests previously conducted at Zion and Quad Cities stations.
Commonwealth Edison will conauct this test prior to the startup of Unit 1, now scheduled for June 1986.
Please address any questions you may have in this mattar to this office.
l Very truly yours, M
Thomas J. Rausch Nuclear Licensing Administrator Boiling Waters Reactor cc:
Resident Inspector - Drescen
[ (: fr / T ij, ?,
/
g cf
/[.
k0 6 'O 2132N g
& ' ' s~.7, 198 1 r b l
.Qp, y
s x
,4
'A' j 81061G0 M6 P
.