Provides Schedule for Verification Test Re Adequacy of Station Electric Distribution Sys Voltages.Test Will Be Conducted Prior to June 1986 Startup
ML20004E947
Person / Time
Site: Dresden Constellation icon.png
Issue date: 06/05/1981
From: Rausch T
COMMONWEALTH EDISON CO.
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
NUDOCS 8106160225
Download: ML20004E947 (1)


Text

.. - -

O Ona First Nf tionni Plaza. Chicrgo, Ilknoc Commonwealth Edison Addrms Reply to: Post Office Box 767 Chicago, !!!inois 60690 June 5, 1981 Mr. Dennis M. Crutchfield, Chief Operating Reactor Branch 5 Division of Licensing U.

S. Nuclear Regulatory Commission Washington, D.C.

20555

Subject:

Dresden Unit 1 Schedule for Verification Test Concerning Adequacy of Station Electric Distribution System Voltages NRC Docket No. 50-10 Reference (a):

D.M. Crutchfield letter to J. S. Abel dated April 30, 1981.

Dear Mr. Crutchfiela:

Reference (a) provided the NRC Safety Eval'.ation concerning the adequacy of Dresden Unit i electric oistribution system voltages.

The aesign was found to be acceptable subject to the satisfactory completion of a confirmatory test similar to tests previously conducted at Zion and Quad Cities stations.

Commonwealth Edison will conauct this test prior to the startup of Unit 1, now scheduled for June 1986.

Please address any questions you may have in this mattar to this office.

l Very truly yours, M

Thomas J. Rausch Nuclear Licensing Administrator Boiling Waters Reactor cc:

Resident Inspector - Drescen