...A.
ILLINDIS POWER 00MPANY j,]y l gg (93_ggy_g 3 500 south 27TH STREET, DECATUR. tLLINOfS 62525 May 20, 1981 tr p
'V/
Mr. Darrell G. Eisenhut, Director i
'i Division of Licensing Office of Nuclear Reactor Regulation Ej_ L'g 2 G Kt _g3_
u.s. g y ma 7/
United __ State s, Nuclear 4egul-atvCommis s. ton e
Washington, D.
C.
20555 p
&_ /0
/
d'
Dear Mr. Eisenhut:
s/
,~
Clinton Power Station Units 1 & 2 Docket Nos. 50-461 and 50-462
Subject:
Implementation of NUREG-0313, Rev. 1,
" Technical Report on Material Selection and Processing Guidelines for BWR Coolant Pressure Boundary Piping (Generic Task A-42)"
Reference:
D. G. Eisenhut's Letter of February 26, 1981, Same Subj ect.
The Clinton Power Station design and construction practices meet the applicable requirements of NUREG-0313, Rev. 1, for Class 1, 2, and 3 ASME pressure boundary piping, safe ends, and fitting material (including weld metal).
These requirements were antici-pated and extensive measures were taken to assure compliance with NUP.EG-0313.
If we can be of further assistance, please do not hesitate to contact us.
Sincerely, G. E. Uuller Supervisor-Licensing Nuclear Station Engineering CCH:ks cc:
C. I. Grimes, NRC Clinton Project Manager H. H. Livermore, NRC Resident Inspector 300/
.s l
/I 8105270153
.