Summary of 810422 Meeting W/Util & Boeing Re Load Sequencer for Offsite Power
ML20003J109
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 05/04/1981
From: Kane W
Office of Nuclear Reactor Regulation
To:
Office of Nuclear Reactor Regulation
References
NUDOCS 8105080456
Download: ML20003J109 (5)


Text

_

P o

/

'o UNITED STATES g

NUCLEAR REGULATORY COMMISSION n

<E WASHINGTON, D. C. 20566 l

lilAY 41981 1

Docket No. 50-395 APPLICANT:

South Carolina Electric & Gas Company FACILITY:

Virgil C. Sumer Nuclear Station, Unit No.1

SUBJECT:

SUMMARY

OF APRIL 22, 1981 E ETING REGARDING LOAD SEQUENCER FOR OFFSITE POWER 1.

General l

Representatives of the staff met on April 22,19/ii with representatives i

of the applicant and its consultant to discuss the staff requirement for a sneak circuit analysis of the load sequencer. A list of those I

persons who 1ttended the meeting is included in the enclosure.

2.

Purpose i

The purpose of the meeting was to discuss the staff's requirements for a sneak curcuit analysis. and the manner in which it could be rescived by the applicant.

3.

Dtscussion I

The discussion related to open issue 1.6.9 as identified in the staff's Safety Evaluapion Report (SER) for the facility i.e. NUREG-0717.

In the SER we noted that we would require (1) a design decription, (2) a reliability analysis, and (3) a sneak circuit analysis for the load sequencer. Since that time the applicant has completed items 1 and 2 but has not initiated work on item 3.

The staff reiterated its position in the SER stating that the sneak circuit analysis had the potential for identifying problem areas that could not be identified by a reliability analysis or periodic testing, thereby providing additional assurance of the overall reliability of the sequencer design.

l l

The applicant's consultant provided a written discription of the scope of I

the sneak circuit analysis and a sample of the format for the final report.

I We concluded that this appeared to be complete enough and that if similar information was submitted by the applicant it would be in sufficient detail for the staff's evaluation. However, we noted that any recomendation from the supplier of the sneak circuit analysis would have to be reviewed j

by the applicant and the load sequencer vendor before any changes were made.

l Decisions on each recommendation would have to be documented and justified We noted that neither the sneak circuit analysis nor any changes need be made prior to the operation of the facility.

In addition, we stated that, l

l b

s105080456

i, i

i i ;

in order to close out this open issue, we would need the applicant to document j

(1) its commitment to perform the analysis (2) a description of the analysis, (3) the format for the final report and (4) the schedule.

Q WiIfe ane, Project M3 nager Licensing Branch No.1 Division of Licer. sing l

Enclosure:

As stated l

cc: See next page i

\\

l

w I

Mr. T. C. Nichols, Jr.

Vice President & Group Executive Nuclear Operations South Carolina Electric & Gas Company P. O. Box 764 Columbia, South Carolina 29218 cc: Mr. Henry Cyrus Senior Vice.Presidcnt South Carolina Public Service Authority 223 North Live Oak Drive Moncks Corner, South Carolina 29461 J. B. Knotts, Jr., Esq.

Debevoise & Liberman 1200 17th Street, N. W.

Washington, D. C.

20036 Mr. Mark B. Whitaker, Jr.

Group Manager - Nuclear Engineering & Licensing South Carolina Electric & Gas Company P. O. Box 764 Columbia, South Carolina 29218 Mr. Brett Allen Bursey Route 1, Box 93C Little Mountain, South Carolina 29076 Resident Inspector / Summer NPS c/o U. S. NRC Route'1, Box 64 Jenkinsville, South Carolina 29065

t i

April 22, 1981 i

. LIST OF ATTENDZES.

i i

NRC Staff.

SCE&G i

W. Kane C. Price F. Rosa A. Wachter A. Ungaro-N. Clark l

0. Chopra I

Boeing I

R. Poirier i

i f

t t

I' i

4 4

l l

i i

}

4 i_,

. _..,.... _ _ _ _ - _... _ _.. _ - _ _.. _. _ _ _. - _., _ _ _,, _ _ _. - _...... _ _ _ _ - - _ _ _ _... - - ~.. - _ _.

v o

MEETINGSUMMdRYDISTR_IBUTION Docket File G. Lear fiRC POR V. Noonan gy 4g Local PDRm,l S. Pawlicki TIC /NSIC/ Tera V. Benaroya N. Hughes Z. Rosztoczy LD#1 Reading W. Haass H. Denton 7

D. Muller 1/ e R. Ballard E. Case

<5 \\

D. Eisenhut W. Regan O' b(. % I).,

, f f

'l D. Ross

/

R. Purple

/

B. J. Youngblood

[

P. Check A. Schwencer 2

l'Mi' 0 71981>. T8 Chief, Power Systems Branch F. Miraglia

0. Parr (s

J. Miller u*

F. Rosa G. Lainas g

W. Butler R. Vollmer N

W. Kreger J. P. Knight

<tr R. Houston R. Bosnak Chief, Radiological Assessment Branch F. Schauer L. Rubenstein R. E. Jackson T. Speis Project Manager W. Kane W. Johnston Attorney, OELD

.. Stolz M. Rushbrook S. Hanauer 01E (3)

W. Gamnill ACRS (16)

T. Murley R. Tedesco F. Schroeder D. Skovholt M. Ernst NRC

Participants:

R. Baer C. Berlinger W. Kane K. Kniel F. Rosa G. Knighton A. Ungaro A. Thadani

0. Chopra D. Tondi J, Kramer D. Vassallo P. Collins D. Ziemann bec: Applicant & Service List

v u u

-