Interim Deficiency Rept Re Soil Characteristics Error in Facility Design,Initially Reported on 800715.Design Analysis Work to Be Completed by 811231
ML20003H339
Person / Time
Site: Clinton Constellation icon.png
Issue date: 04/24/1981
From: Koch L
ILLINOIS POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, 1605-L, U-0230, U-230, NUDOCS 8105050612
Download: ML20003H339 (1)


Text

.

1605-L U-0230 ILLINDIS POWER COMPANY f'. "' L14-81(04-24)-L

[:.. _. s:0 SOUTH 27TH STREET, DECATUR ILLINO!S 62525 April 24, 1981

'qli-I m y',Y R Q

'O di NY.ef/b, 6

.c e u's.

n By.0 y

Mr. James G. Keppler 8 "i" Director, Region III C

f Office of Inspection and Enforcement "v

U.S. Nuclear Regulatory Cocmission 799 Passevelt Road Glen Ellyn, Illinois 60137

Dear Mr. Keppler:

Clinton Power Station Unit 1 Docket No. 50-461 Construction Permit CPPR-137 The purpose of this letter is to update my letter of July 15, 1980, to you concerning the S&L soil characteristics error in the Clinton Power Station design.

The design analysis work is proceeding and is anticipated to be completed by the end of December, 1981.

The determination of whether this error is report-able per 10 CFR 50.55(e) will not be possible until all design analyses have been completed.

If you have any further questions concerning this matter, please do not hesitate to bring them to my attention.

Sincerely l J 4 i

L. J. Koch Vice President di cc: