ML20003G044

From kanterella
Jump to navigation Jump to search
Informs That Scheduled Date for Reinforcing Masonry Block Walls Will Be 810313.Delay Due to Late Start in Beginning Work & Obtaining Required Matls.Work on Class I Walls in Turbine Bldg Completed
ML20003G044
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 02/09/1981
From: Swart F
PUBLIC SERVICE CO. OF COLORADO
To: Seyfrit K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
IEB-80-11, P-81048, NUDOCS 8104280123
Download: ML20003G044 (1)


Text

,

~ ~~]

puhuc service company or conende 12015 East 46th Avenue, Suite 440; Denver, CO 80239

\\)

l t

)

To ADM/DMB:

February 9, 1981 NSIC Fort St. Vrain

?!

ADM/TIDC Unit No. 1 N.

y ADM/RSB gf P-81048 e

A

^

t s,,pg 2 41981w b2 Mr. Karl V.

Seyfrit g

'f}

Director Region IV Nuclear Regulatory Commission o) d

,g W

611 Ryan Plaza Drive Suite 1000 Arlington, Texas 76012

Subject:

IE-80-11, Masonry Block Walls

Reference:

P-80381, dated October 28, 1980

Dear Mr. Seyfrit:

In the reference letter, PSC committed to a completion date of February 1, 1981 for the work of reinforcing those walls which require additional strength to withstand a seismic event.

The scheduled completion date to reinforce the walls is now March 13, 1981.

The reason for the delay is due to a late start in beginning the work and in delays of obtaining the required materials.

To date, all work on Class I walls that required reinforcing in the turbine building has been completed.

Work is now scheduled to begin on reinforcing the required Class I masonry block walls in the reactor building.

Overall, the project is estimated to be 60%

complete.

Very truly yours, 3

4 lt~k Frederic E.

Swart Nuclear Project Manager FES/ RAG /pa 8104280 M Q

s