Memorandum Affirming That ASLB 800912 Memorandum & Order Did Not Prejudice Issue of Whether Effects of Expanding Spent Fuel Pool Per Se Necessitate Preparation of EIS
ML20003F950
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 04/22/1981
From: Grossman H, Paris O, Shon F
Atomic Safety and Licensing Board Panel
To:
References
ISSUANCES-OLA, LBP-81-9, NUDOCS 8104240373
Download: ML20003F950 (7)


Text

_

LBP-81-9 UNITED STATES OF AMERICA s

NUCLEAR REGULATORY C0ffi!SSION 4

ATOMIC SAFETY AND LICENSING BOARD 6-I* I Before Administrative Judges:

g og$[#

et s, Herbert Grossman, Chairman

\\

' hice Dr. Oscar H. Paris, Member Frederick J. Shon, Member

\\

7' Y

/

NAV[g488 gg

)

In the Matter of:

CONSUMER POWER COMPANY

)

Docket No. 50-155 OLA

)

(Spent Fuel Pool Expansion)

(Big Rock Point Nuclear Plant) )

~ ~-

)

April 22, 1981

'i./

~

fll4 0;

(

k.d /Sg f)j MEMORANDUM 4

O Z

(Reassuring Staff Of Lack of Prejudgment C Environmental Assessment Suaaested By ALAB-

%g /

A i$

In its decision of March 31, 1981, ALAB-636, 13 NRC _,

Appeal Board reversed this Licensing Board's September 12, 1980 determination, LBP-80-25, 12 NRC 355, that 102(2)(C) of the National Environmental Policy Act (NEPA), 42 USC 4332(2)(C), requires the preparation of an environmental impact statement (EIS) covering the impacts of a proposed spent fuel pool expansion for a plant that had been licensed before NEPA M We had based our decision on the i

N

-1/ The EIS we had required would have been considerably more g

limited than a construction permit or operating license review since it would not have included as an environmental cost either

/p the cost of constructing the facility or the cost of operating the facility to the extent the operation would not be directly facilitated by the spent fuel pool expansion. LBP-80-25, suora, 12 NRC 365.

8104240 M C

grounds that the expansion was for the sole purpose of permitting an additional ten-year term of reactor operation that had never been environmentally reviewed because the facility had been licensed I

before the passage of L.8A and had never had an of its term of operation environmentally reviewed. The Appeal Board held that NEPA does not' require considering the environmental impacts resulting from a Federal action that merely permits continued reactor operation without any change in reactor operation.E We cannot, of course, quarrel with the Appeal Board's reversal of our holding.

l i

The Appeal Board also directed the Licensing Board to " rethink" (Op. 35) and " reconsider" (Op. 41) its purported further deter-minations that (1) the Staff would inevitably decline to prepare an EIS and (2) the f ailure to issue an EIS would be erroneous also because the impacts from the physical expansion of the spent fuel i

pool (disregarding the continued plant operation that the expansion might afford) themselves necessitate the preparation of an EIS. The Appeal Board discoursed at length about the " chilling effect" our

" unwise, if not improper" premature decision would have in

" inhibit [ing]" the Staff from doing its job of determining whether an EIS is necessary in an " honest and objective fashion," and would result in compromising the " integrity of the hearing process."

Op. 35-38.

2/ The Appeal Board disclaimed any reliance upon the prohibition against a retroactive application of NEPA for its decision.

Op. 33, fn. 32. Such reliance could have served to distinguish this situation from a license renewal application.

. - ~. _,

. -, _, _. _ _ _ _. _ _. _..,.. _ _ - _ - -,. = -...,,, _. _ _ _. _,. -

. This Board has no little difficulty in rethinking something that it had not thought in the first place and in reconsidering "an inappropriate prejudgment of the staff's position" (Op. 37) that is not evidenced in our decision. Simply stated, we never decided that the Staff was unalterably connitted to not preparing an EIS or that any effect of the proposed spent fuel pool expansion other than the continued plant operation it would afford necessitated the preparation of an EIS. We have carefully reexamined our Memorandum and Order, as well as the Appeal Board's decision, in order to locate the source of the confusion. On reflecticn, it appears to us to stem from our beginning assumption, apparently not shared by the Appeal b, that a sinale Federal action such as the proposed Board amendment of the license to permit a spent fuel pool expansion, requires and permits the preparation of but a single environmental document encompassing all of the impacts of that action: an environmental impact statement, if the action is major 'and has a significant effect upon the human environment; an environmental impact appraisal (EIA), accompanied by a negative declaration, if otherwise. 5102 of NEPA, 42 USC 4332, supra,; 10 CFR 51.5, 51.7.

We had never considered that a single major action having a number of environmental impacts would require or even permit the preparation of separate environmental reviewing documents covering separate

(

impacts, some which may be minor and some major, with an EIS (or EISs) covering the major impacts and an EIA (or EIAs) covering the minor ones. Hence, once we had determined that one of the effects of i

See ALAB-636, supra, Op. 34-35.

l

-. ~.. _. - _ _.

-i 4

the licensing action, viz. the continued operation of the facility over a lengthy term, necessitated the preparation of an EIS, we ordered that the docwent also cover all other environmental impacts of the licensing action, even though those impacts r,anding alone might not have required an EIS.

It was this pari of our order (12 NRC 366) which was the apparent source of confusion.

We did not believe that the continued plant operation effect and other effects of the expansion could be viewed as separate Federal actions requiring the preparation of separate environmental doceents (e.g., 2 EISs, 2 EIAs, or an EIS and EIA).1I As we read 10 CFR 651.5 and 51.7, the action to be assessed was the amendment of the license to permit the spent fuel pool expansion. Thus, the environmental review would have considered all of the impacts resulting from tnat action and, in our view, those impacts included continuedplantoperation.El From the foregoing discussion, it is clear that the parties can be further reassured that our Memorandtsn and Order did not also postulate, as suggested by the Appeal Board (0p. 36, fn. 36), that an action that otherwise does not have a significant effect on the environment may be transformed into one that does by the absence of an environmental review of a different, prior action. The Appeal A

Ibid.

5 We concede that if eno were to begin with the assumption (as we did not) that the separate impacts of a single licensing action may require the preparation of separate environmental documents, one could easily misinterpret our decision as requiring an EIS to cover continued plant operation and at least one other EIS to cover all other impacts arising from the spent fuel pool expansion.

In fact, all that we determined was that the action facilitating continued plant operation required the preparation of an EIS.

. Board's suggestion was in the context of our having distinguished the instant proposed spent fuel pool expansion from other spent fuel pool expansions in which EISs were not required.6_/ We noted that in those cases there had been prior environmental reviews that need not be duplicated for the spent fuel pool expansion. However, as we thought was apparent in our opinion, those prior environmental reviews were prepared at the operating license stage and covered the impacts from the operation of the reactor that we recognized should not have to be duplicated in the spent fuel pool expansion proceeding.

Since none of the other impacts of the spent fuel pool expansions in those cases could have been covered in the environmental review at the operating license proceeding, the only portion of the review of the proposed spent fuel pool expansion that could have duplicated the prior environmental review was that regarding the~ continued plant operation. The impacts of the change in fuel pool itself have been deemed negligible in all cases we have discovered. We do not disagree with the findings in those cases: we thought we had carefully distinguished them from the case at bar.

6/

Comonwealth Edison Company (Zion Station, Units 1 and 2),

ESP-80-7, 11 NRC 245 (1980); Portland General Electric Comoany (Trojan Nuclear Plant), LbP-78-32, 8 NRC 413, 449-50 (1978),

aff'd, ALAB-531, 9 NRC 263 (1979), Duouesne Licht Comoany (Beaver Valley Power Station, Unit 1) LSP-78-16, 7 NRC 811, 816 (1978); Northern States Power Comoany (Prairie Island Nuclear Generating Plant, Units 1 and 2), LBP-77-51, 6 NRC 265, 268 (1977), aff'd, ALAB-455, 7 NRC 41 (1978), remanded on other grounds, sub. nom. State of Minnesota v. NRC, 602 F 2d 412 D.C.

Cir. 1979).

. In sum, we need not await the preparation of the Staff's environmental analysis as suggested by the Appeal Board (Op. 35, 41),

to affirm to the parties that our September 12, 1980 Memorandum and Order did not in any measure prejudge the issue of whether the effects of expanding the spent fuel pool, per _s_e, necessitate the e

preparation of an EIS.E If one purpose of the Appeal Board's discussion is to facilitate the Staff's making its analysis in "an honest and objective fashion," we have concluded that we would be better advised to clarify our position before the Staff makes its assessment. The Staff should be reassured, regardless of the outcome of Commission review, that it can proceed totally uninhibited by our September 12, 1980 Order, which was directed solely towards the question of whether the additional term of operation that the expansion would permit necessitated the preparation of an E ALAB-636 faulted us for purportedly prejudging the question of whether an EIS is necessitated by the impacts that might result from the spent fuel pool expansion, other than from continued plant operation. However, it decided the continued plant operation issue on the merits, apparently accepting our view that this issue could be considered ripe for determination as a matter of law, notwithstanding that the environmental 4

assessment ha'd not yet issued. See LBP-80-25, suora, 12 NRC 364, fn. 2.

We concede that a strict adherence to NRC procedures might have required our also delaying this question until after the Staff had spoken. But we were aware that operation of a nuclear plant for some years has heretofore always required an EIS, and we were reluctant to delay such a decision lest the delay result in a shutdown for lack of storage space.

o EIS,8 a matter on which the Appeal Board has now spoken.

Similarly, in view of the Appeal Board opinion, we take no position at this juncture on whether the other effects of the spent fuel pool expansion require the preparation of more than one environmental document.

IT IS SO ORDERED.

FOR THE ATOMIC SAFETY AND LICENSING BOARD

<. >Y M: -

Herbert Grossman, Chairman ADMINISTRATIVE JUDGE

$T\\

NY Dr. Oscar H. Paris, Member ADMINISTRATIVE JUDGF, Y

/

Frederick J. Sh AoMemDer ADMINISTRATIVEC D 1E Dated at Bethesda, Maryland this 22nd day of April 1981.

~

That we had requested the parties to assume only "arauendo" the Staff's prospective issuance of an EIA was recognized early in the Appeal Board's decision. Op. 4 It was apparently forgotten when we were later seen as promoting this assumption I

into "an inappropriate prejudgment of the staff's position."

Op. 37.