Responds to NRC 810218 Request for Confirmation of Implementation Dates for Emergency Support Facilities. Facility Presently Under OL Review & Required Submittals Will Be Furnished Per Review Process
ML20003E625
Person / Time
Site: Clinton  Constellation icon.png
Issue date: 04/03/1981
From: Wuller G
ILLINOIS POWER CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
GL-81-10, L30-81(04-03)-6, L30-81(4-3)-6, U-0222, U-222, NUDOCS 8104070412
Download: ML20003E625 (1)


Text

-

U-0222 ILLINDIS POWER COMPANY  ;; g. g30.gt(04 03)-6 3 500 SOUTH 27TH STREET, DECATUR, ILLINOIS 62525 April 3, 1981 -

7'- s},

h Mr. Darrell G. Eisenhut, Director b(4

-M' \'\".,$'

v

' (c. r Division of Licensing H W ,

~T Office of Nuclear Reactor Regulation ,

W Y,- -S*

U. S. Nuclear Regulatory Commission  : ,

Washington, D. C. 20555 r. p y

Dear Mr. Eisenhut:

qg

Reference:

NRC Generic Letter 81-10, dated 2/18/81 - Post-TMI Requirements for the Emergency Operations Facility

, Clinton Power Station Units 1 & 2 Docket Nos. 50-461 and 50-462 Construction Permits Nos. CPPR-137 & CPPR-138 This is in reply to the referenced-letter which requested confirmation by Illinois Power Company regarding the implementa-tion dates for emergency support facilities as provided in Enclosure 1 to the referenced letter.

The Clinton Power Station operating license application is

! currently in the OL review process,and the OL for Unit 1 is scheduled for issuance after October 1, 1982. Therefore, all l required licensing submittals for emergency support facilities

, will be furnished in a time frame supporting the OL re'riew process.

! This position is consistent with the implementation requirements l for action plan item III.A.l.2.

Sincerely,

, G. E. Wtiler Supervisor - Licensing Nuclear Station Engineering GEW/em cc: C. I. Grimes, NRC Clinton Project Manager H.- H. Livermore, NRC Resident Inspector h0VS