Status Rept for PDR-81/01 Re Lubrication of Thrust Bearings on Turbocharger.Engine Availability Could Be Affected If Defect Found by Transamerica Delaval Not Corrected
ML20003B635
Person / Time
Site: Grand Gulf  Entergy icon.png
Issue date: 01/29/1981
From: Mcgaughy J
MISSISSIPPI POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
10CFR-050.55E, 10CFR-50.55E, AECM-81-50, NUDOCS 8102250072
Download: ML20003B635 (3)


Text

.

6 MISSISSIPPI POWER & LIGHT COMPANY

=i Helping B uild .blississippi ,

andmWasanE P. O. B0X 16 4 O. J A C K S O N. MISSISSIPPI 39205 V

JAMES P. McGAUGHY. JR January 29, 1981

.ss.sror v,ca msmr '

~, ( ( , . _' ,4 -

1/ s. e L' ,_

Office of Inspection & Enforcement /\ ' / , l' U. S. Nuclear Regulatory Commission / ,

Region II /Y[4a [ ffV 101 Marietta Street, N . '4.

Suite 3100  ;

[hy

_--)

P ,[f3o 'o I3; Atlanta, Georgia 30303 L 4 u.s, " IOS/ A -

?$ & tou $,

Attention: Mr. J. P. O'Reilly, Director [,s /0

Dear Mr. O'Reilly:

yky\(8/ 'y, j ig SUBJEC*: Grand Gulf Nuclear Station Units 1 and 2 Docket Nos. 50-416/417 File 0260/15525/15526 PRD-81/01, Status Report, Trans-america DeLaval Turbocharger Lubrication AECM-81/50 On January 2, 1981, Mississippi Power & Light Ccmpany notified Mr. P. K. VanDoorn, of your office, of a Potentially Reportable De-ficiency (PRD) at the Grand Gulf Nuclear Station (GGNS) construc-tion site. The deficiency concerns lubrication of the thrust bear-ings on Turbochargers manufactured by the Elliott Co=pany for De-Laval DSRV engines. Transamerica DeLaval notified the NRC of a 10CFR Part 21 condition concerning the above on December 16, 1980.

Transamerica DeLaval has designed a system modification cor-recting the above problem. However, we will require more time to review the adequacy of their modification and formulate proper corrective actions, as well as determine reportability under 10CFR 50.55(e) and 10CFR21. '4e expect to forward to you our final report on this matter by June 2, 1981. Our status report is attached.

Yours truly, M

p J. P. McGaughy, Jr.

CW:st Attachment cc: See page 2 k q

's n r.f ? R [.h L C O G ,

810225no_,g Member Middle South Utilities System

MISSISS1PPI POWER & LIGHT COMPANY Mr. J. P. O'Reilly AECM-81/50 NRC Page 2 cc: Mr. N. L. Stampley Mr. R. 3. McGehee Mr. T. B. Conner Mr. Victor Stello, Director Div. of Inspection & Enforcement U. S. Nuclear Regulatory Commission

'w'as hing t on , D . C . 20555 Mr. G. 3. Taylor South Miss. Electric Power Association P. O. Box 1589 Hattiesburg, MS 39401

e Attachment to AECM-81/50 Page 1 of 1 a

STATUS REPORT FOR PRD-81/01 I. Description of Deficienev Transamerica DeLaval notified the NRC on December 16, 1980, of a 10CFR Part 21 condition, which identified a potential problem with lubrication of the thrust bearings of the turbochargers which ceuld result in engine non-availability. The engines identified with GGNS are SN70433/36 DSRV.

These turbochargers are manufactured by Elliott Company of Jeannette, PA. They are installed on the engines by Transimer-ica DeLaval and lubricated in accordance with Elliott Company's recommendations.

The potential defect exists in the lubricating oil system that supplies oil to the turbocharger bearings. The design of this system permits lubricating oil to flow to the bearings only when the engine is running and prevents oil flow to the bear-ings when the engine is in the standby mode. The oil seal of the turbocharger is a labyrinth type seal and is only effective when the turbocharger is running. Because of the possibility of seal leakage when the turbocharger is at rest (engine Standby mode) the turbocharger L. O. system is bypassed at this time.

Engine availability could be affected if the defect noted by DeLaval is not corrected. If the engines are not available, then the standby generators would not be able to supply power

' in the event of the loss of offsite power. As such, the ability to safely shut.down the plant and =aintain it in a safe, shut--

down condition would be impaired following a loss of offsite power.

4 II. ' Proposed Resolution.

MP&L has implemented the following program through the Architect /

Engineer / Constructor:

1. Evaluate Transamerica DeLaval's proposed modification for application at GGNS.
2. Investigate corrective actions required in light of (1.)

above.to correct the deficiency and to preclude recurrence.

3. -Investigate further the possible impacts on safety and de-

-termine reportability under 10CFR50.55(e) and 10CFR21.

III. Status of Proposed Resolution / Reason for Delav in Final Report Initial investigations are still under way by Architect / Engineer.

IV. Projected Final' Report Submittal Date We project submission of our-Final Report by June 2, 1981.