Metropolitan Edison Company Post (Mfice Box 480 g

Middletown, Pennsylvania 17057 717 9444041 Writer's Direct Dial Number February 6,1981 LlL 015 Office of Nuclear Reactor Regulation Attn:

R. W. Reid, Chief Operating Reactors Branch No. 4 U. S. Nuclear Regulatory Commission Washington, D.C.

20555

Dear Sir:

Three Mile Island Nuclear Station, Unit 1 (TMI-1)

Operating License No. DPR-50 Docket No. 50-289 Containment Purging and Venting Our letter of May 9, 1980 (TLL 229) responding to your letter of January 28, 1980, committed to modify the purge valves to limit their travel to no more than 30 - 50 open. We committed to complete this modification by January 1981, pending delays in receiving kit parts.

Delays have occurred in receiving kit parts and modifying the valves. Therefore, we have revised our completion date to July 15, 1981. Until complete installation of the modifications, Met-Ed will limit purging to 90 hours0.00104 days <br />0.025 hours <br />1.488095e-4 weeks <br />3.4245e-5 months <br /> per year during normal operations.

It is our intention that upon completion of the above stated modifications the purge limit will not apply.

Sincerely,

. H ki 1 i

l Director, TMI-l l

l HDH:DGM:lma cc:

B. J. Snyder B. H. Grier L. Barrett j

l D. DiIanni H. Silver l

1 l

l l

vetrocatan Ec son company s a vemeer of : e General puene ut.i t:es sys:em f/671 M 79 f

'