Notifies That Formal Reload Application Is Not Required for Cycle 6.Util Will Submit Tech Specs Changes Necessary to Enable Review of cycle.End-of-cycle Test Program Will Include on-line Monitoring & post-irradiation Exams
ML20003A317
Person / Time
Site: Quad Cities Constellation icon.png
Issue date: 01/23/1981
From: Abel J
COMMONWEALTH EDISON CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
NUDOCS 8102030482
Download: ML20003A317 (2)


Text

. .g .

/ C N Commonwealth Edison I ) One First National Plaza. Chicagnois

( O "J Addrzss R: ply to: Post Ofhes Box 767 (j/ Chicago, Ilknois 60690 January 23, 1981 Mr. Darrell G. Eisenhut, Director Division of Licensing U.S. Nuclear Regulatory Commissioa Washington, DC 20555

Subject:

Quad Cities Unit 2 Cycle 6 Barrier Fuel Demonstration Program NRC Docket No. 50-265 Reference (a): R. L. Tedesco letter to R. E. Engle (General Electric Company) dated November 12, 1980

Dear Mr. Eisenhut:

The NRC review of the General Electric Topical Report NED0-24259 " Generic Information for Barrier Fuel Demonstration Bundle Licensing" was documented by Reference (a). In this review it was concluded that pending the review and approval of a reload application to be submitted by Commonwaalth Edison for Quad Cities Unit 2, the PCI barrier fuel demonstration would be licensable.

Based upon previous discussions with the staff on this s ubj ec t , it is our understanding that a formal reload application would not be required for Quad Cities Unit 2 Cycle 6. Our current plan is to submit in the second quarter-of 1981 the Technical "

Specification changes necessary to enable a 10 CFR 50.59 review to be performed for this cycle. These changes would include the barrier fuel ECCS analysis results (MALPHGR values) and Technical Specification bases relating to use of the ODYN transient model.

Concerning-the end of cycle test program, it is our intention to perform on line monitoring and-post irradiation examinations. The scope of the monitoring and examinations will not be defined until approximately nine (9) months prior to the testing.

We will be pleased to-provide at your request detailed information pertaining to the fuel reload or end.of. cycle testing as-this information becomes available.

One (1) signed original and thirty-nine (39) copies of this transmittal are provided for your use.

y c0 3 +

E-

  • Y 7r , fi-p," -

q.g

~;

c: -

75 81 02630 % S p

Mr. Darrell G. Eisenhut, Director January 23, 1981 Page 2 Please direct any questions you may have in this regard to this office.

Very truly you s,

/

I

. S. Abel Director of Nuclear Licensing cc: RIII Inspector - Quad Ci ies 00208