Ro:On 690220,emergency Diesel Generator Test Operated & Immediately Tripped on Overspeed.Overspeed Mechanism Readjucted to 110% Normal Operating Speed & Tested Addl Two Times.Setpoint Currently Increased to 115%
ML20002D000
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 03/31/1969
From: Haueter R
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: Morris P, Skovholt D
US ATOMIC ENERGY COMMISSION (AEC)
References
NUDOCS 8101150712
Download: ML20002D000 (2)


Text

'

N. l

. ' f (c - 15K'..

..Q ~

q[ Tic,. 2_

w.

~ tunSllh

'h v,-

tx

'[.

3

. C0mpBny r,,

4 5,

General Offices: 212 West Michigan Avenue, Jackson, Michigan 49201. Area Code 617738 0550

' f >j,

F.

ch 31, 1969

/

~

NP-M4,/

f,y

'Y Q}

'b Dr. Peter A. Morris Director Re: Docket 50-155 OY

,..u Division of Reactor Licensing o'

US Atomic Energy Commission t; -

f.c Washin6 ton, DC 205L5 6

[ci.dii..

Dear Dr. Morris:

Att: Mr. D. J. Skovholt 10 /' ?'-

m p

This letter will confim our recent discussion with the USAEC Compliance Office, Chicago, regarding an overspeed trip of the emergency diesel generator at Bi6 Rock Point during test operation.

On February 20, 1969 the emergency diesel generator was test operated and started satisfactorily; however, the unit immediately tripped on overspeed. The overspeed mechanism was readjusted to the 110% of normal operatin6 speed, and the unit was successfully test started an additional two times. The diesel generator was then loaded for its nomal test run and operated successfully.

After the test mn, the diesel generator was unloaded and a fine adjustment made to the overspeed mechanism using a sensitive frequency meter recorder to insure a proper trip setting. Again, the diesel was test started and did not trip. The diesel generator was then placed in the normal standby service.

Subsequent discussions with the manufacturer revealed that a 110% settin6 would be very marginal and that the overspeed mechanism should be adjusted to trip at approximately 115% overspeed and could be safely increased to 122%. At this writing the overspeed mechanism set point has been increased to 115%, and no further overspeed trips have been experienced.

Yours very truly,

[$ &}

~

- n ERC/1v R. L. Haueter Assistant Electric Production CC: GFiorelli Superintendent

~ Nuclear Y

5 (Lzaww% f 5 2I~(Y

~

~ a M... e *m "W mm.esI

~

  • m.

f*

1 2*

s

)

r m.

consumers Power m 31, 1900 Apri.T.1980 11F' 1 Dart M I Mg.

NM OATR OP f

J ekase, Nishigan ur n.

meer, or n (R. L. Eameter)

E TJ Oneo.:

CC:

OrteJis Dr. Peter A. Morris 1

ACTIOs. ktCESS.RY CONCLptPENC=

0 mare ^~s* tare:

NO ACTION NECESSARY O CCD.9AENT O

C L.A 55 e F.:

POST OFFICE F tti, CODE:

%g.. s450-135 o

aco.10:

mtaieric : m.,s. u-w..w mucnRr0 70 oAre arCrivro ev o.re Ltr la ret to the overspeed trip of t

the emergency diesel generator at Zianama 4-1 Sig Rock Point during test w/9 cys for h 7,scu

-~

Cperation................

E NC4.0&uRES:

Dis tribetionis f ' ~ '.'., . 7..j '3 E. Price in Sta Ef I.

skeyholt D. Thompsom pr/Boyd Norris/Sckreed<

Regulatory 6Gr Public Docisment Room Compliam e (2 cys )

nre 1L

.L 4

u.s. ATouic cuenov couuiss' "

MAIL CONTROL FORM rcau.Ar..c,.n.s o.............,........,,in,i..........

l l

]f[( UIUb5Oh

.9&

L

-