Response to IE Bulletin 78-08, Radiation Levels from Fuel Element Transfer Tubes, Providing Requested Information for Surry Units 1 & 2, and North Anna Unit 1
ML19354A145
Person / Time
Site: Surry, North Anna  Dominion icon.png
Issue date: 08/14/1978
From: Stallings C
Virginia Electric & Power Co (VEPCO)
To: O'Reilly J
NRC/IE, NRC/RGN-II
References
IEB-78-008, Serial No. 352 /061278
Download: ML19354A145 (1)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGIN IA 23261

- e August 14, 1978 Mr. James P. O'Reilly, Director Serial No. 352 /061278 Office of Inspection and Enforcement PO&M/DLB~:das U. S. Nuclear Regulatory Commission Docket N . 50-280 Region II 0- .

101 Marietta Street, Suite 3100 50-338 Atlanta, Georgia 30303 License Hos: DPR-32 DPR-37 NPF-4

Dear Mr. O'Reilly:

This is in response to IE Bulletin 78-08, "Radiation Levels From Fuel Ele-ment Transfer Tubes". Following is the information requested for Surry Unit Nos. 1 and 2 and North Anna Unit No. 1.

Surry Power Station Unit Nos. 1 and 2 In accordance with subject IE Bulletin, a study was made of Unit #1 and Unit #2 fuel transfer tube shielding designs. During the Unit #1 refueling shutdown, 5-11-78, a detailed survey was made in all suspect areas in the reac-tor containment and the Spent Fuel building. The survey was documented and is on file. Ali areas of concern in Unit 111 containment, Unit 1/2 containment, and Spent Fuel building are posted in accordance with 10CFR20.203C. The same survey will be performed and documented during the Unit #2 refueling shutdown.

All areas where a whole body dose of 100 mR6II could be received during the move-ment of single fuel element will be locked.

North Anna Power Station Unit No. 1 A review of shielding over the fuel transfer canal at elevation 262'10" has shown a potential for high exposures during refueling. There is an approximately 6" gap between the shielding and the containment wall. This area will be barri-caded and posted prior to refueling and will require a radiation work permit for entry. Surveys will be performed during fuel transfers to establish radia-tion levels and boundaries.

Very truly yours, z!;,);? J1d£/c-~~

C. M. Stallings Vice President - Power Supply and Production Operations