|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217K1051999-10-19019 October 1999 Ack Receipt of Ltr Dtd 990707,which Transmitted Rev 29 to Callaway Plant Physical Security Plan,Under Provisions of 10CFR50.54(p).Based on Determination That Changes Do Not Decrease Effectiveness of Plan,No NRC Approval Required ML20217G2071999-10-14014 October 1999 Forwards Insp Rept 50-483/99-10 on 990913-16.No Violations Noted.Insp Was to Review Emergency Plan & Procedures During Biennial Emergency Preparedness Exercise ML20217B5901999-10-0505 October 1999 Informs That Staff Concludes That Licensee Responses to GL 97-06 Provides Reasonable Assurance That Condition of Util SG Internals in Compliance with Current Licensing Bases for Callaway Plant,Unit 1 ML20217B5711999-10-0505 October 1999 Discusses GL 98-01 Issued by NRC on 980511 & Uec Responses for Callaway NPP Unit 1 ,990224 & 990628.Informs That Staff Reviewed Responses & Concluded That All Requested Info for GL 98-01 Provided ML20212G0221999-09-22022 September 1999 Forwards Insp Rept 50-483/99-11 on 990812-20.No Violations Noted.Team Found,Weakness in flow-accelerated Corrosion Monitoring Program Resulted in No Previous Insp of Pipe Segment Which Failed ML20212D9341999-09-16016 September 1999 Informs That on 990818,NRC Completed Midcycle PPR of Callaway Plant.In Area of Ep,C/As Taken in Response to Problems Identified During Previous Exercises Warrant More in-dept Review.Details of Insp Plan Through March 2000 Encl ML20217D5791999-09-15015 September 1999 Provides Formal Documentation of Reviews & Discussions Re Technical Ltr Rept for Proprietary Info.Review of Ltr Was Discussed in Telcon & Via e-mail Messages. Summary of Telcons as Documented on 990708,included ML20212A4921999-09-13013 September 1999 Forwards Insp Rept 50-483/99-08 on 990725-0904.Two Severity Level IV Violations of NRC Requirements Identified & Being Treated as Noncited Violations Consistent with App C of Enforcement Policy ML20212A4701999-09-10010 September 1999 Rssponds to NRC 990709 RAI Re Util Relief Request to Allow Use of 1998 Edition of ASME Section Xi,Subsection Iwe. Acceptance Criteria for Liner Plate Pressure Boundary Thickness Will Be Limited to 10% Nominal Thinning ML20212B1521999-09-10010 September 1999 Forwards Insp Rept 50-483/99-07 on 990809-13.No Violations Noted.Inspectors Used Annual Licensed Operator Requalification Exams to Assess Licensed Operator Performance ML20211N0321999-09-0202 September 1999 Forwards SE Concluding That Util Adequately Addressed Actions Requested in GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20211B0241999-08-18018 August 1999 Ack Receipt of Ltr Dtd 990714,transmitting Scenario for Licensee Upcoming Biennial Exercise.Based on Review,Nrc Determined That Exercise Scenario Sufficient to Meet Emergency Plan Requirements & Exercise Objectives ML20210T9121999-08-13013 August 1999 Forwards Insp Rept 50-483/99-06 on 990613-0724.One Severity Level 4 Violation Occurred & Being Treated as Ncv,Consistent with App C of Enforcement Policy ML20210R7241999-08-12012 August 1999 Forwards semi-annual Fitness for Duty Program Performance Data Rept for Callaway Nuclear Plant for 990101-990630,IAW 10CFR26.71(d) ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ULNRC-04085, Forwards Rev 4 to Callaway Plant Cycle 10 COLR, Per TS 6.9.1.9.COLR Has Been Revised to Update Rod Bank Insertion (Ril) Limits,As Function of Rated Thermal Power1999-08-11011 August 1999 Forwards Rev 4 to Callaway Plant Cycle 10 COLR, Per TS 6.9.1.9.COLR Has Been Revised to Update Rod Bank Insertion (Ril) Limits,As Function of Rated Thermal Power ML20210P0371999-08-10010 August 1999 Forwards SE Granting Licensee 980710 Requests for Relief (ISI-13 - ISI-18) from Requirements of Section XI of 1989 Edition of ASME B&PV Code for Second 10-year Interval ISI at Plant,Unit 1 ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ULNRC-04079, Forwards 180-day Response to NRC GL 99-02, Lab Testing of Nuclear-Grade Activated Charcoal1999-08-0202 August 1999 Forwards 180-day Response to NRC GL 99-02, Lab Testing of Nuclear-Grade Activated Charcoal ML20210H6381999-07-30030 July 1999 Forwards SE Accepting Relief Request for Approval for Use of Alternate Exam Requirement for Plant Inservice Insp Program A93443, Forwards Addl Info as Committed to in Telcon Between Amerenue & NRC Personnel on 990616,re GL 95-07, Pressure Locking & Thermal Binding of MOV Gate Valves1999-07-28028 July 1999 Forwards Addl Info as Committed to in Telcon Between Amerenue & NRC Personnel on 990616,re GL 95-07, Pressure Locking & Thermal Binding of MOV Gate Valves ULNRC-04075, Forwards Response to NRC 990618 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of SR Motor-Operated Valves1999-07-28028 July 1999 Forwards Response to NRC 990618 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of SR Motor-Operated Valves ULNRC-04076, Informs of Implementation of Amend 131 to License NPF-30, Revising OL to Reflect Requirement in TS 3/4.7.1.7 for Four Operable ASD Lines & Associated Revs,Rather than Three Operable ASDs1999-07-28028 July 1999 Informs of Implementation of Amend 131 to License NPF-30, Revising OL to Reflect Requirement in TS 3/4.7.1.7 for Four Operable ASD Lines & Associated Revs,Rather than Three Operable ASDs ULNRC-04070, Forwards Rev 3 to Callaway Plant Cycle 10 COLR, IAW TS 6.9.1.9.COLR Has Been Revised to Update RAOC Axial Flux Difference (Afd) Limits,As Function of Rated Thermal Power1999-07-27027 July 1999 Forwards Rev 3 to Callaway Plant Cycle 10 COLR, IAW TS 6.9.1.9.COLR Has Been Revised to Update RAOC Axial Flux Difference (Afd) Limits,As Function of Rated Thermal Power 05000483/LER-1998-008, Forwards Amended Response to GL 81-07, Control of Heavy Loads, to Address Corrective Action Described in LER 98-008-00.Discrepancy Between Earlier Submittals of Snupps Rept on Control of Heavy Loads & TS Re RHR Sys,Resolved1999-07-27027 July 1999 Forwards Amended Response to GL 81-07, Control of Heavy Loads, to Address Corrective Action Described in LER 98-008-00.Discrepancy Between Earlier Submittals of Snupps Rept on Control of Heavy Loads & TS Re RHR Sys,Resolved ULNRC-04071, Informs That Util Anticipates Approx Ten Licensing Actions That Could Occur During Fys 2000 & 2001,in Response to Administrative Ltr 99-021999-07-27027 July 1999 Informs That Util Anticipates Approx Ten Licensing Actions That Could Occur During Fys 2000 & 2001,in Response to Administrative Ltr 99-02 ML20210B5611999-07-20020 July 1999 Forwards Review of Ltr & Encl Objectives for Plant,Unit 1,1999 Emergency Plan Exercise Scheduled for 990914 ML20210B4021999-07-19019 July 1999 Ack Receipt of Facility Emergency Plan Implementing Procedure EIP-ZZ-00101, Classification of Emergencies, Rev 23,issued on 990513,under Provisions of 10CFR50,App E, Section V ML20210B4401999-07-19019 July 1999 Ack Receipt of Revs to Facility Radiological Emergency Response Plan,Chapters 8.0 & 4.0,issued Respectively on 990512-14,under Provisions of 10CFR50,App E,Section V ML20212A3291999-07-15015 July 1999 Forwards Scenario Manual Containing Description of Callaway Plant 1999 Biennial Emergency Response Plan Exercise to Be Conducted 990914.Correspondence to Satisfy 60-day Submittal Requirement ML20209F3471999-07-0909 July 1999 Forwards Response to NRC 990624 RAI to Complete NRC Review of Relief Request to Allow Use of 1998 Edition of ASME Section Xi,Subsection IWE ML20209E5591999-07-0808 July 1999 Informs That as Result of NRC Review of Util Responses to GL 92-01,rev 1,suppl 1 & Suppl 1 Rai,Staff Revised Info in Reactor Vessel Integrity Database & Releasing Database as Rvid Version 2.TAC MA0531 Closed ML20209H2471999-07-0707 July 1999 Forwards Rev 29 to Physical Security Plan,Per 10CFR50.54(p). Rev Withheld,Per 10CFR73.21 ML20196J9501999-07-0202 July 1999 Ack Receipt of Plant Ep,Rev 22,received on 981207 & Submitted Under Provision of 10CFR50,App E,Section V.Changes Does Not Decrease Effectiveness of EP & Continues to Meet Stds of 10CFR50.47(b).NRC Approval Not Required ML20209B6851999-06-28028 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness of Computer Systems at Nuclear Power Plants. Disclosure Rept Encl ML20209C0171999-06-28028 June 1999 Forwards Special Rept 99-01 Re Fifteenth Year Inservice Containment Bldg Tendon Surveillance Failure.Observed Voids in Sheathing Filler Grease Do Not Indicate Degradation of post-tensioning Sys,Based on Encl Evaluation ML20196F8101999-06-25025 June 1999 Informs That J Donohew Will Assume Project Manager Responsibilities,Effective 990621 ML20196H2521999-06-25025 June 1999 Forwards Insp Rept 50-483/99-05 on 990502-0612.Two Violations Occurred & Being Treated as Noncited Violations, Consistent with App C of Enforcement Policy ML20196F8181999-06-24024 June 1999 Forwards RAI Re 990111 Request for Relief from Certain ASME Code ISI Requirements for Containment Liners.Response Requested within 30 Days from Date of Agreement ML20196G5621999-06-21021 June 1999 Informs NRC of Implementation of Amend 132 to Callaway License NPF-30 to Allows Installation of Electrosleeves for Steam Generator Tube Repair for Two Cycles Following Installation of First Electrosleeve IR 05000483/19990041999-06-18018 June 1999 Refers to GL 96-05 Issued by NRC on 960918,UE Responses & 970313 & NRC Insp Rept 50-483/99-04,dtd 990427. Forwards Request for Addl Info Re GL 96-05 Program at Callaway Plant,Unit 1 ML20212J2441999-06-18018 June 1999 Submits Request for Alternate Exam Requirements for Plant Re ISI Program Plan.Plant Does Not Torque Bolted Connections to Stress Values Greater than 100 Ksi ML20195H0971999-06-14014 June 1999 Discusses Une 990407 Request That Proprietary Document Entitled, Thermal Stability Assessment - Electrosleeved Tubes, Be Withheld from Public Disclosure.Determined Info to Be Proprietary & Will Be Withheld from Public Disclosure ML20207H3751999-06-14014 June 1999 Discusses 990407 Une Request That Proprietary Version of Document Entitled, Evaluation of Severe Accident Simulation, Dtd April 1999,be Withheld from Public Disclosure.Determined Info Proprietary & Will Be Withheld ML20195H9731999-06-11011 June 1999 Forwards Requested Addl Info Related to Relief Request ISI-16,encountered During Refuel 9 ML20195J9301999-06-0808 June 1999 Informs That Refuel 9 OAR-1 Owners Data Rept for ISI & Summary Rept for Interval 2 Was Submitted with Typographical Error,In That Commercial Service Date Should Be 841219,vice 941219.Please Substitute Encl Corrected Document ML20207G3201999-06-0707 June 1999 Ack Receipt of Change Notice 98-008 Dtd 980918,which Transmitted Changes to Callaway Plant Ep,Rev 21,under Provisions of 10CFR50,App E,Section V.No NRC Approval Required.No Violations Identified ML20207G3151999-06-0707 June 1999 Ack Receipt of Callaway Plant EP Implementing Procedure EIP-ZZ-001001M,Classification of Emergencies,Rev 22,issued on 981222 Under 10CFR50,App E,Section V Provisions.No Violations Identified ML20195C5131999-05-28028 May 1999 Forwards Revs to Sections 3.9 & 5.6 of Its,Based on Resolution Telcons Held Between NRC Staff & Util on 990526 & 27 A98803, Forwards Certified ITS & ITS Bases for Callaway Plant,In Response to NRC 990402 Draft SE for License Amend to Convert TSs to Format & Expanded Bases of ITS1999-05-27027 May 1999 Forwards Certified ITS & ITS Bases for Callaway Plant,In Response to NRC 990402 Draft SE for License Amend to Convert TSs to Format & Expanded Bases of ITS 1999-09-22
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML20217D5791999-09-15015 September 1999 Provides Formal Documentation of Reviews & Discussions Re Technical Ltr Rept for Proprietary Info.Review of Ltr Was Discussed in Telcon & Via e-mail Messages. Summary of Telcons as Documented on 990708,included ML20212A4701999-09-10010 September 1999 Rssponds to NRC 990709 RAI Re Util Relief Request to Allow Use of 1998 Edition of ASME Section Xi,Subsection Iwe. Acceptance Criteria for Liner Plate Pressure Boundary Thickness Will Be Limited to 10% Nominal Thinning ML20210R7241999-08-12012 August 1999 Forwards semi-annual Fitness for Duty Program Performance Data Rept for Callaway Nuclear Plant for 990101-990630,IAW 10CFR26.71(d) ULNRC-04085, Forwards Rev 4 to Callaway Plant Cycle 10 COLR, Per TS 6.9.1.9.COLR Has Been Revised to Update Rod Bank Insertion (Ril) Limits,As Function of Rated Thermal Power1999-08-11011 August 1999 Forwards Rev 4 to Callaway Plant Cycle 10 COLR, Per TS 6.9.1.9.COLR Has Been Revised to Update Rod Bank Insertion (Ril) Limits,As Function of Rated Thermal Power ULNRC-04079, Forwards 180-day Response to NRC GL 99-02, Lab Testing of Nuclear-Grade Activated Charcoal1999-08-0202 August 1999 Forwards 180-day Response to NRC GL 99-02, Lab Testing of Nuclear-Grade Activated Charcoal ULNRC-04075, Forwards Response to NRC 990618 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of SR Motor-Operated Valves1999-07-28028 July 1999 Forwards Response to NRC 990618 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of SR Motor-Operated Valves A93443, Forwards Addl Info as Committed to in Telcon Between Amerenue & NRC Personnel on 990616,re GL 95-07, Pressure Locking & Thermal Binding of MOV Gate Valves1999-07-28028 July 1999 Forwards Addl Info as Committed to in Telcon Between Amerenue & NRC Personnel on 990616,re GL 95-07, Pressure Locking & Thermal Binding of MOV Gate Valves ULNRC-04076, Informs of Implementation of Amend 131 to License NPF-30, Revising OL to Reflect Requirement in TS 3/4.7.1.7 for Four Operable ASD Lines & Associated Revs,Rather than Three Operable ASDs1999-07-28028 July 1999 Informs of Implementation of Amend 131 to License NPF-30, Revising OL to Reflect Requirement in TS 3/4.7.1.7 for Four Operable ASD Lines & Associated Revs,Rather than Three Operable ASDs 05000483/LER-1998-008, Forwards Amended Response to GL 81-07, Control of Heavy Loads, to Address Corrective Action Described in LER 98-008-00.Discrepancy Between Earlier Submittals of Snupps Rept on Control of Heavy Loads & TS Re RHR Sys,Resolved1999-07-27027 July 1999 Forwards Amended Response to GL 81-07, Control of Heavy Loads, to Address Corrective Action Described in LER 98-008-00.Discrepancy Between Earlier Submittals of Snupps Rept on Control of Heavy Loads & TS Re RHR Sys,Resolved ULNRC-04070, Forwards Rev 3 to Callaway Plant Cycle 10 COLR, IAW TS 6.9.1.9.COLR Has Been Revised to Update RAOC Axial Flux Difference (Afd) Limits,As Function of Rated Thermal Power1999-07-27027 July 1999 Forwards Rev 3 to Callaway Plant Cycle 10 COLR, IAW TS 6.9.1.9.COLR Has Been Revised to Update RAOC Axial Flux Difference (Afd) Limits,As Function of Rated Thermal Power ULNRC-04071, Informs That Util Anticipates Approx Ten Licensing Actions That Could Occur During Fys 2000 & 2001,in Response to Administrative Ltr 99-021999-07-27027 July 1999 Informs That Util Anticipates Approx Ten Licensing Actions That Could Occur During Fys 2000 & 2001,in Response to Administrative Ltr 99-02 ML20212A3291999-07-15015 July 1999 Forwards Scenario Manual Containing Description of Callaway Plant 1999 Biennial Emergency Response Plan Exercise to Be Conducted 990914.Correspondence to Satisfy 60-day Submittal Requirement ML20209F3471999-07-0909 July 1999 Forwards Response to NRC 990624 RAI to Complete NRC Review of Relief Request to Allow Use of 1998 Edition of ASME Section Xi,Subsection IWE ML20209H2471999-07-0707 July 1999 Forwards Rev 29 to Physical Security Plan,Per 10CFR50.54(p). Rev Withheld,Per 10CFR73.21 ML20209C0171999-06-28028 June 1999 Forwards Special Rept 99-01 Re Fifteenth Year Inservice Containment Bldg Tendon Surveillance Failure.Observed Voids in Sheathing Filler Grease Do Not Indicate Degradation of post-tensioning Sys,Based on Encl Evaluation ML20209B6851999-06-28028 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness of Computer Systems at Nuclear Power Plants. Disclosure Rept Encl ML20196G5621999-06-21021 June 1999 Informs NRC of Implementation of Amend 132 to Callaway License NPF-30 to Allows Installation of Electrosleeves for Steam Generator Tube Repair for Two Cycles Following Installation of First Electrosleeve ML20212J2441999-06-18018 June 1999 Submits Request for Alternate Exam Requirements for Plant Re ISI Program Plan.Plant Does Not Torque Bolted Connections to Stress Values Greater than 100 Ksi ML20195H9731999-06-11011 June 1999 Forwards Requested Addl Info Related to Relief Request ISI-16,encountered During Refuel 9 ML20195J9301999-06-0808 June 1999 Informs That Refuel 9 OAR-1 Owners Data Rept for ISI & Summary Rept for Interval 2 Was Submitted with Typographical Error,In That Commercial Service Date Should Be 841219,vice 941219.Please Substitute Encl Corrected Document ML20195C5131999-05-28028 May 1999 Forwards Revs to Sections 3.9 & 5.6 of Its,Based on Resolution Telcons Held Between NRC Staff & Util on 990526 & 27 A98803, Forwards Certified ITS & ITS Bases for Callaway Plant,In Response to NRC 990402 Draft SE for License Amend to Convert TSs to Format & Expanded Bases of ITS1999-05-27027 May 1999 Forwards Certified ITS & ITS Bases for Callaway Plant,In Response to NRC 990402 Draft SE for License Amend to Convert TSs to Format & Expanded Bases of ITS ML20196L2911999-05-19019 May 1999 Forwards Responses to NRC 990315 RAI Concerning GL 95-07, Pressure Locking & Thermal Binding of MOV Gate Valves A36791, Forwards Response to NRC 990510 RAI Re GL 96-06 with Respect to Analysis of Water Hammer & two-phase Flow Issues. Supporting Calculation Also Encl1999-05-17017 May 1999 Forwards Response to NRC 990510 RAI Re GL 96-06 with Respect to Analysis of Water Hammer & two-phase Flow Issues. Supporting Calculation Also Encl ULNRC-04034, Forwards Amerenues Risk Evaluation Summary & Provides Listing of Other Documents Which Have Been Previously Provided to Support Evaluation of Electrosleeves at High Temp Severe Accident Conditions1999-05-17017 May 1999 Forwards Amerenues Risk Evaluation Summary & Provides Listing of Other Documents Which Have Been Previously Provided to Support Evaluation of Electrosleeves at High Temp Severe Accident Conditions 05000483/LER-1998-003, Forwards LER 98-003-01 Re Inadvertent Actuation of ESFAS Due to 'A' SG High Level During Refuel 9.Rept Is Submitted to Report Change in C/A from That Reported in Original Rept1999-05-12012 May 1999 Forwards LER 98-003-01 Re Inadvertent Actuation of ESFAS Due to 'A' SG High Level During Refuel 9.Rept Is Submitted to Report Change in C/A from That Reported in Original Rept ML20206Q9551999-05-12012 May 1999 Responds to NRC Re Violations Noted in Insp Rept 50-483/99-04.Corrective Actions:Une Commits to Make Available for NRC Review,Action Plan Outlining Scope & Completion Dates of Project ULNRC-04027, Forwards Comments on Draft SE Re Proposed Conversion to Improved Tss.Copy of ITS & ITS Bases Will Be Provided by 990524,to Support Issuance of License Amend on or About 9905281999-05-0404 May 1999 Forwards Comments on Draft SE Re Proposed Conversion to Improved Tss.Copy of ITS & ITS Bases Will Be Provided by 990524,to Support Issuance of License Amend on or About 990528 ML20206E3211999-04-28028 April 1999 Forwards Special Rept 98-03 Re Inservice Insp of CP Sgs,Per Plant TS 4.4.5.5.b.Insp Was Performed in Apr 1998 During Plant Ninth Refueling Outage.Rept Is Being Resubmitted Due to Typos in Original Rept ML20206E5781999-04-23023 April 1999 Informs That R Schukai Is No Longer Employed with Amerenue & Info Sent Is No Longer Required.Name Should Be Removed from Mailing Lists.Mailing Label Used by Company Which May Assist in Matter,Submitted ULNRC-04018, Submits follow-up Items Re Proposed Conversion to ITS Sections 1.0,3.3,3.4,3.6,3.7 & 3.9.Suppl to Ltr Will Be Submitted at Later Date1999-04-21021 April 1999 Submits follow-up Items Re Proposed Conversion to ITS Sections 1.0,3.3,3.4,3.6,3.7 & 3.9.Suppl to Ltr Will Be Submitted at Later Date ML20205Q7751999-04-16016 April 1999 Forwards Special Rept 98-03 Concerning ISI of Callaway SGs Performed in Apr 1998 During Callaway Plants Ninth Ro. Rept Documents Final SG Insp Results ULNRC-04015, Forwards Cash Flow Projection & Certification to Satisfy Guarantee of Payment of Retrospective Premiums,Per 10CFR140.211999-04-15015 April 1999 Forwards Cash Flow Projection & Certification to Satisfy Guarantee of Payment of Retrospective Premiums,Per 10CFR140.21 ULNRC-04005, Forwards Proprietary & non-proprietary White Paper Entitled, Evaluation of Severe Accident Simulation, as Addl Info to Facilitate Approval of Requested Amend to Revise TS to Use Repair SG Tubes.Proprietary Info Withheld,Per 10CFR2.7901999-04-0707 April 1999 Forwards Proprietary & non-proprietary White Paper Entitled, Evaluation of Severe Accident Simulation, as Addl Info to Facilitate Approval of Requested Amend to Revise TS to Use Repair SG Tubes.Proprietary Info Withheld,Per 10CFR2.790 ULNRC-04004, Forwards Proprietary Thermal Stability Background Data Along with Time/Temp Graph Requested in 990402 Telcon with NRC & Contractor,Argonne Natl Lab.Proprietary Info Withheld1999-04-0707 April 1999 Forwards Proprietary Thermal Stability Background Data Along with Time/Temp Graph Requested in 990402 Telcon with NRC & Contractor,Argonne Natl Lab.Proprietary Info Withheld ULNRC-04007, Submits follow-up Items Related to Proposed Conversion to ITSs Sections 3.3,3.4,3.6 & 3.7.Encl Includes mark-ups of ITS Sections 3.5,3.6 & 3.8.Suppl to Ltr Will Be Provided at Later Date1999-04-0707 April 1999 Submits follow-up Items Related to Proposed Conversion to ITSs Sections 3.3,3.4,3.6 & 3.7.Encl Includes mark-ups of ITS Sections 3.5,3.6 & 3.8.Suppl to Ltr Will Be Provided at Later Date ULNRC-04000, Forwards Rept Re Present Level of Insurance & Sources of Insurance Applicable to Callaway Plant,Per 10CFR50.54(w)1999-04-0101 April 1999 Forwards Rept Re Present Level of Insurance & Sources of Insurance Applicable to Callaway Plant,Per 10CFR50.54(w) ULNRC-03998, Forwards Required Financial Info Re Decommissioning Callaway Nuclear Plant,Per 10CFR50.751999-03-30030 March 1999 Forwards Required Financial Info Re Decommissioning Callaway Nuclear Plant,Per 10CFR50.75 ML20205G2211999-03-25025 March 1999 Submits Rev 28A to Callaway Plant Physical Security Plan, Incorporating Addendum Re Security Sys Replacement Transition Plan,Per 10CFR50.54(p).Encl Withheld,Per 10CFR73.21 ML20205R5251999-03-25025 March 1999 Forwards Special Rept 98-03 Re Results of Tenth SG Tube Inservice Insp,Per Requirements of Plant TS 4.4.5.5.b.Insp Was Performed in Apr 1998 During Plant Ninth Refueling Outage ULNRC-03988, Requests Approval of Alternative Exam ISI-12A Per 10CFR50.55a(a)(3)(i) & (II) for 1989 Edition of ASME Section IX,IWA-5242(a) for Class I Bolted Connections Inside Bioshield for RFO 101999-03-19019 March 1999 Requests Approval of Alternative Exam ISI-12A Per 10CFR50.55a(a)(3)(i) & (II) for 1989 Edition of ASME Section IX,IWA-5242(a) for Class I Bolted Connections Inside Bioshield for RFO 10 ULNRC-03991, Forwards 1998 Annual Rept of Individual Monitoring Results, Per 10CFR20.2206.Rept Provided in Electronic Format on Diskette IAW Gudiance of Reg Guide 8.7.Without Diskette1999-03-19019 March 1999 Forwards 1998 Annual Rept of Individual Monitoring Results, Per 10CFR20.2206.Rept Provided in Electronic Format on Diskette IAW Gudiance of Reg Guide 8.7.Without Diskette ML20204F7211999-03-17017 March 1999 Forwards Amended Fitness for Duty Program Performance Data for Six Month Period Beginning Jul-Dec 1998 ML20204E1331999-03-17017 March 1999 Responds to NRC Re Violations Noted in Insp Rept 50-483/99-02 on 990208-12.Corrective Actions:Will Revise Security Plan to Increase Min Staffing by Three Armed Security Force Response Personnel Per Shift ML20207C3631999-03-12012 March 1999 Forwards Exam Matl & Associated QA Checklist for Written Exam to Support Plant RO Retake Exam Scheduled for 990423. Exam Matls Requested to Be Withheld from Public Disclosure Until After Exam Completion 05000483/LER-1998-001, Forwards LER 98-001-01,being Submitted to Clarify Scope of Original Reviews Performed for Corrective Action Number 3 in LER 98-001-00.Reviews Have Identified Case of Failure to Properly Establish Equipment Operability1999-03-10010 March 1999 Forwards LER 98-001-01,being Submitted to Clarify Scope of Original Reviews Performed for Corrective Action Number 3 in LER 98-001-00.Reviews Have Identified Case of Failure to Properly Establish Equipment Operability ULNRC-03979, Submits follow-up Items Related to Proposed Conversion to ITSs Sections 3.3,3.4,3.6,3.7,3.8,3.9 & 5.0.Suppl to Ltr Dtd 970515,will Be Provided at Later Date1999-03-0909 March 1999 Submits follow-up Items Related to Proposed Conversion to ITSs Sections 3.3,3.4,3.6,3.7,3.8,3.9 & 5.0.Suppl to Ltr Dtd 970515,will Be Provided at Later Date ULNRC-03975, Informs of No Reportable ECCS Evaluation Model Revs for Callaway During Time Period from Mar 1998 to Mar 1999,IAW 10CFR50.46.ECCS Evaluation Model Margin Assessment Encl1999-03-0505 March 1999 Informs of No Reportable ECCS Evaluation Model Revs for Callaway During Time Period from Mar 1998 to Mar 1999,IAW 10CFR50.46.ECCS Evaluation Model Margin Assessment Encl ULNRC-03971, Forwards Annual Personnel Exposure & Monitoring Rept for 1998, Per TS Sections 6.9.1.4 & 6.9.1.5.Rept Includes One Incident of Specific Activity Analysis of RCS in Which Limits of TS 3.4.8 Were Exceeded1999-02-26026 February 1999 Forwards Annual Personnel Exposure & Monitoring Rept for 1998, Per TS Sections 6.9.1.4 & 6.9.1.5.Rept Includes One Incident of Specific Activity Analysis of RCS in Which Limits of TS 3.4.8 Were Exceeded ML20207A4311999-02-17017 February 1999 Forwards semi-annual Fitness for Duty Program Performance Data Rept for Callaway Nuclear Plant for Period of 980701-981231 1999-09-15
[Table view] Category:UTILITY TO NRC
MONTHYEARML20059G2971990-09-0404 September 1990 Notifies of Implementation of Procedure on 900831 to Correct wide-range Gas Monitor Display for Noble Gas Spectrum ML20059G4991990-08-30030 August 1990 Forwards Semiannual Radioactive Effluent Release Rept for Jan-Jun 1990 & Rev 0 to APA-ZZ-01003, Odcm ML20059C3371990-08-23023 August 1990 Advises That Util Plans to Remove Some Thimble Plugging Devices from Plant During Upcoming Refueling Outage.No License Amend Required.Revs to Tech Spec Bases 3/4.2.2 & 3/4.2.3 That Reflect All Removal of Thimble Plugs Encl ML20058N2051990-08-0707 August 1990 Advises of Implementation of Amend 55,rev to Tech Spec 3/4.7.1.2 Re Auxiliary Feedwater Sys,Effective 900807 ML20081E1971990-07-27027 July 1990 Forwards Rev 6 to Indexing Instruction T210.0002/Q101, Qualification/Certification Documentation & Rev 6 to T210.002/R353, Required Reading/Personnel Form 2 ML20044B1821990-07-0909 July 1990 Forwards Westinghouse Revised Proprietary RCS Flow Measurement Uncertainty Calculation Supplementing Setpoint Studies Submitted in Attachment to Util 900412 Ltr.Encl Withheld ML20055E5261990-07-0505 July 1990 Forwards Revised marked-up Tech Spec Pages for 900306 Application for Amend to License to Place cycle-specific Core Operating Parameters in Core Operating Limits Rept ML20055E7861990-07-0505 July 1990 Forwards Callaway Plant 1990 Annual Exercise Scenario on 900530 ML20044A6601990-06-25025 June 1990 Forwards Requested Info Re Seismic Design of safety-related above-ground Vertical Liquid Storage Tanks,Per 900404 Ltr. All Stresses on Tank Roof Angle,Connecting Cylinder to Roof,Remain within Code Allowables Under Postulated Loads ML20043H8371990-06-21021 June 1990 Forwards Response to Generic Ltr 90-04 Re Status of Implementation of Generic Safety Issues at Facility ML20043H2721990-06-12012 June 1990 Forwards 10CFR50.59 Annual Rept Summaries of Written Safety Evaluations of Changes Approved & Implemented for Plant from 890330 to Present ML20043E2161990-06-0505 June 1990 Forwards Endorsements 42-48 for Nelia Policy NF-264 & Endorsements 28-34 for Maelu Policy MF-111 ML20043G9331990-06-0404 June 1990 Forwards Rev 13 to Operating QA Manual. ML20043D7101990-05-31031 May 1990 Forwards NPDES Renewal Application Submitted to State of Mo Dept of Natural Resources on 900518 ML20043B5841990-05-22022 May 1990 Responds to NRC 900423 Ltr Re Violations Noted in Insp Rept 50-483/90-04.Corrective Actions:Security Post Instructions Modified to Require Check of Security Container in QA Area ML20042F2831990-04-30030 April 1990 Forwards Rev 11 to Inservice Testing Program. ML20042F1161990-04-30030 April 1990 Provides Clarification to SALP 9 Rept 50-483/90-01 for Sept 1988 - Jan 1990.Licensee Voluntarily Retested Few Remaining Const Workers Originally Approved for Unescorted Access Using mini-IPAT ML20042F2901990-04-27027 April 1990 Forwards Util 900402 Ltr Documenting Agreement Between State of Mo Historic Preservation Officer & Util Re Cultural Resources ML20042D8491990-04-0202 April 1990 Forwards Listing of Present Level of Nuclear Property Insurance Coverage & Sources of Insurance,Per 10CFR50.54(w) ML20012F1601990-03-29029 March 1990 Submits Supplemental Info Re Util Response to Station Blackout.Callaway Will Comply W/Numarc Station Blackout Initiative 5A Re Emergency Diesel Generator ML20012D1901990-03-19019 March 1990 Forwards Rev 15 to Physical Security Plan.Rev Withheld (Ref 10CFR73.21) ML20012D7441990-03-16016 March 1990 Responds to Generic Ltr 89-19 Re Resolution of USI A-47, Safety Implications of Control Sys in LWR Nuclear Power Plants. No Changes or Implementation Schedule Need Be Provided in Response to Generic Ltr 89-19 ML20012C6791990-03-0808 March 1990 Advises That Installation Date for Regulatory Effectiveness Review Concern 2.6.1 Revised to 900531.Deficiency Will Be Under Continuous Surveillance Until Correction Made ML20012C3111990-03-0606 March 1990 Forwards Addl Info Re Storage of Enriched Fuel in Spent Fuel Pool Area,Per NRC 900216 Request ML20012B3691990-02-28028 February 1990 Forwards Cash Flow Projection & Certification to Satisfy Guarantee of Payment of Retrospective Premiums ML20012A4141990-02-23023 February 1990 Requests NRC Concurrence That Leak Chase Sys Is Integral Part of Containment Boundary & Does Not Need to Be Vented During Containment Integrated Leak Rate Test ML20006E1401990-02-12012 February 1990 Requests Clarification Re Positive Test Results for Controlled Substances,Specifically How Second Confirmed Positive Test Results Are Handled ML20011E7941990-02-0202 February 1990 Requests Emergency Relief from Tech Spec 3.1.3.1.b Due to Electrical Problem W/Rod Control Sys.Action Required to Prevent Plant Shutdown from 100% Power When Adverse Weather Conditions Exist in Svc Area ML20006D1061990-01-29029 January 1990 Responds to Generic Ltr 89-13, Svc Water Sys Problems Affecting Safety-Related Equipment. Dredge & Visual Shoreline Insps of Missouri River Near Plant Intake Indicated Presence of Small Numbers of Asiatic Clams ML20006C2311990-01-24024 January 1990 Forwards Callaway Plant Annual Exercise,891011, Emergency Exercise Scenario for 1989 Exercise ML20006B1371990-01-19019 January 1990 Forwards ECCS Evaluation Model Revs 10CFR50.46 Annual Rept. Util Will Provide Followup Rept Based on Results of Westinghouse Investigation to Be Completed in Second Quarter 1990 ML20005E8161990-01-0303 January 1990 Responds to NRC Bulletin 89-002 Re Stress Corrosion Cracking of high-hardness Type 410 Stainless Steel Internal Preloaded Bolting in Anchor Darling Model S350W Swing Check Valves or Valves of Similar Design ML20005E5141990-01-0202 January 1990 Certifies That fitness-for-duty Program That Meets Requirements of 10CFR26 Will Be Implemented on 900103 ML20005G3511989-12-28028 December 1989 Forwards Addl Info Supporting NRC Review of Proposed Revs to Tech Spec 3/4.1.3, Movable Control Assemblies. ML20005E5221989-12-28028 December 1989 Responds to Generic Ltr 89-10, Safety-Related Motor-Operated Valve Testing & Surveillance. ML19353B0041989-12-0404 December 1989 Forwards Response to NRC 891016 Ltr Re Results of Regulatory Effectiveness Review on 890918-21.Encl Withheld (Ref 10CFR73.21) ML19332F1861989-11-30030 November 1989 Responds to Generic Ltr 89-15 Re Emergency Response Data Sys.Sys Will Be Implemented by Jul 1991,to Allow Addl Features to Be Developed for Plant Computer Sys & to Be Installed in Conjunction W/New Plant Computer Sys ML19332E9881989-11-30030 November 1989 Discusses Visual Insp of Hafnium Rod Cluster Control Assemblies During Refuel-2 in Fall 1987.Results Indicate Guide Card Fretting Wear Per NRC Info Notice 87-019.All Hafnium Rods Replaced W/Silver/Indium/Cadnium Assemblies ML19332D4441989-11-22022 November 1989 Responds to Generic Ltr 89-21,forwarding Table Providing Implementation Status of Each USI at Facility ML19327C0741989-11-0707 November 1989 Forwards Executed Amend 3 to Indemnity Agreement B-93, Reflecting Changes to 10CFR140, Financial Protection Requirements & Indemnity Agreements. ML19324C4291989-11-0707 November 1989 Responds to NRC Bulletin 88-010,Suppl 1, Nonconforming Molded-Case Circuit Breakers. Bulletin Provisions as Clarified by Suppl Met & Documentation Associated W/Review Being Maintained at Facility ML19332B6121989-10-31031 October 1989 Provides Individual Plant Exam Method & Schedule.Completion of Level 1 PRA Scheduled for Jul 1991.Containment Performance Analysis Will Be Completed in Feb 1992.Results Will Be Provided in Sept 1992 ML20005D6181989-10-23023 October 1989 Submits Response to Suppl 1 to Generic Ltr 89-07 Re Safeguards Contingency Planning for Surface Vehicle Bombs. Short-term Actions Included to Protect Against Attempted Radiological Sabotage Involving Land Vehicle Bomb ML19325C9251989-10-0404 October 1989 Submits Corrected Wording to Encl to 890929 Ltr Supporting 10CFR50,App J Exemption to Allow Leak Chase Plugging During Integrated Leak Rate Test ML20248E4831989-09-29029 September 1989 Forwards Addl Info to Support 10CFR50,App J Exemption to Allow Leaving Leak Chases Plugged During Type a Integrated Leak Rate Test ML20248G0871989-09-28028 September 1989 Responds to NRC Bulletin 88-011 Re Pressurizer Surge Line Thermal Stratification.Action Items 1.a & B Completed & 1.d Actions Re Stress & Fatigue Ongoing Through Westinghouse Owners Group ML20248C1951989-09-21021 September 1989 Forwards Summary of Refueling Water Storage Tank Seismic Design Analysis Which Includes Effects of Tank Wall Flexibility.Issue Not Applicable to Condensate Storage Tank at Facility ML20246J7011989-08-30030 August 1989 Forwards Semiannual Radioactive Effluent Release Rept for First Half 1989.W/o Encl ML20246K9451989-08-29029 August 1989 Forwards Relief Request 0 to Plant Inservice Insp Program Plan,Per Observations During Refuel III ML20246E0521989-08-18018 August 1989 Forwards Info on Operator Licensing Exam Schedule,Per Generic Ltr 89-12 1990-09-04
[Table view] |
Text
y < . - w.r v_ , j u S,.
8 '
'n; 9 44 A f)P C/ :
7gO UNION ELECTRIC COMPANY . / ,
1908 GRATIOT STREET .Q /
sT. Louis MissouR W
. 4 r \/
JOHN s(, GRV AN o, me. ......."'
May 22, 1981 "'*"'**""'**'**
Mr. Harold R. Denton Director of Nuclear Reactor Regulation _.j US Nuclear Regulatory Commission d 1/
Washington, DC 20555 ULNRC '4 47
Dear Mr. Denton:
DOCKET NUMBERS 50-483 AND 50-486 CALLAWAY PLANT UNITS 1 & 2 FINAL SAFETY ANALYSIS REPORT
Reference:
NRC letter dated March 26, 1981 signed by R. L. Tedesco The referenced letter requested additional information concerning the Callaway Plant FSAR. The specific nature of the requested information was in the area of quality assurance. Trans-n'itted herewith are responses to the referenced letter's questions.
These responses reflect the consensus reached during an April 24, 1981 meeting of the NRC (Messrs. W. Haas, J. Spraul, and A. Dromerick) and Union Electric and SNUPPS Staff representatives; and subsequent discussions and reviews with J. Spraul on May 19 and 20, 1981.
We trust these responses are acceptable and therefore plan their formal incorporation into the FSAR in future revisions (Note- A complete incorporation of these responses requires a revision to the SNUPPS Standard Plant FSAR as well as the Callaway Addendum).
The information is hereby incorporated into the Callaway Application.
Should any questions remain regarding the acceptability of these responses please contact S. J. Seiken of the SNUPPS Staff.
Very ,ruly yours, i n,
{
[' 'J(o n K. u 6 t\
Bryan s
JJS/jds 66 66 b
- i. 8106020 3 3'7
STATE OF MISSOURI )
) S S CITY OF ST. LOUIS )
John K. Bryan, of lawful age, being first duly sworn upon oath says that he is Vice President-Nuclear and an officer of Union Electric Company; that he has read the foregoing document and knows the content thereof; that he has executed the same for and on behalf of said company with full power and authority to do so; and that the facts therein stated are true and correct to the best of his knowledge, information and belie f.
4 l
l ,,
y'*b By 1[% c-Aggp C6hn'K. Tryan
! ice President
!]'J Nuclear SUBSCRIBED and sworn to before me thig 22nd day of May, 1981 D~s . ? ' ~
Q . L'a .
l f/. 'OG AHLT S. HEID A fiOT A'If P'JSUC-STML OF MISSCURI ST. LO'JIS COUNTY MY C0'.' MISSION EAPihES JANUARY 2,1982
\
cc: Glenn L. Koester Vice President Operations Kansas Gas & Electric PO Box 208 Wichita, KS 67201 John E. Arthur Chief Engineer Rochester Gas & Electric Company 89 East Avenue Rochester, NY 14649 A. V. Dienhart Vice President Plant Engineering and Construction Northern States Power 414 Nicollet Mall Minneapolis, MN 55401 Donald T. McPhee Vice President Kansas City Power and Light Company 1330 Baltimore Avenue Kansas City, MO 64141 Gerald Charnoff, Esq.
Shaw, Pittman, Potts & Trowbridge 1810 M. Street, N.W.
Washington, DC 20036 Nicholas A. Petrick Executive Director SNUPPS 5 Choke Cherry Rd.
Rockville, MD 20850 W. Hansen Callaway Resident Office US Nuclear Regulatory Commission RR#1 Steedman, MO 65077 S. J. Seiken OA Manager Si;UPPS 5 Choke Cherry Rd.
Rockville, MD 20850
SNUPPS-C Item 260.13 Section 17.2.3 of the Callaway FSAR, on page 17.2-12, s t e.t e s : " Design verification shall be performed by.
personnel other than those who performed the original design and shall be accomplished prior to reliance on t the safety-related component, system, or structure to.
- perform-its safety function." Concerning the personnel, provide a commitment that the verifier is
. qualified and is not directly responsible for the design or design change (i.e., neither the designer nor his immediate supervisor). Concerning the timing, provide a commitment that design verification is normally completed prior to release for procurement, manufacture, or installation or to another organization for use in other design activities. Where this timing cannot be met, justification for deferral should be -
documented and the unverified portion should be ;
identified and controlled. Include such a commitment.
Response: Section 17.2.3 will be revised to reflect the commitment that design- verification shall oe performed j by " competent" personnel; however, we consider it imperative that we maintain the option whereby an individual's-immediate supervisor may perform design l'
verification. Accordingly we have identified this exception in Appendix 3A of this Addendum. We forsee the necessity of utilizing immediate supervisors in i design review in cases when they are the only available !
technically qualified individuals. In such cases, as well as in all other design reviews, the requirements ,
of Regulatory Guide 1.64, Rev. 2, June 1976, Section
! l C.2(2), (3) and (4) remain applicable. In addition the l need for design verification by the designer's l immediate supervisor will be individually documented ;
I and approved in advance by the supervisor's management l and Quality Assurance Department audits will examine
- l the frequency and effectiveness of use of supervisors
- I as design verifiers. Points 1, 2, and 3 of the staff f l position presented under Regulatory Guide 1.64 in Item ;
I 260.52C will be incorporated in Section 17.2.3. ;
l In regard to the timing of the completion of design j, l Verification our commitment is delineated in response ;
l to Item 260.58C. ;
i e
i i' i i
[
260.13-1
s SNUPPS-C I
Item 260.52C: -Union Electric Company's commitment to meet the '
Regulatory Position of the Regulatory Guides listed in Item 260.1 is unclear in some cases because Appendix ;
3A in the Callaway FSAR Addendum is different from Appendix 3A in the SNUPPS Standard Plant FSAR.
Resolve the differences noted below. ,
Reg. Callaway SNUPPS Guide Addendum Standard Plant r
1.8 Refers to 2/79 version Refers to 5/77 version 1.26 Not listed 1.29 Not listed 1.'58 Refers to 9/80 version Refers to 8/73 version '
l.94 Not listed 1.144 Refers to 9/80 version Refers to 1/79 version :
1.146 Not listed Regarding the commitment to Regulatory Guides concerning quality assurance, the " Discussion" items noted below need clarification or revision.
1.8 The discussion refers to Site Addendum Section 17.1 and does not make it clear that Union
- Electric Company meets the Regulatory Position 1 of the guide with the clarification noted in the second paragraph of the discussion.
i Clarify.
1.30 The extent to which Union Electric Company l conforms to this Regulatory Guide is not clear. i Clarify.
l.33 The discussion states: " ANSI 18.7-1976/ANS-3.2 '
references certain other stande.rds which comprise the regulatory position of Regulatory ;
Guide 1.33." This requires clarification in that the regulatory position includes much more ,
. than the list of other standards. Clarify. (
The extent to which Union Electric Company ;
conforms to this Regulatory Guide also needs c]arification. !
l' 1.38 Clarify the second paragraph of the discussion [
regarding manufacturer's requirements by either i
, (a) eliminating it (The standard only requires >
{ that the manufacturer's requirements "be considered.") or (b) including the statement .
from the response to item 260.38 that: "The !'
relaxation of manufacturers' storage
- requirements involves an engineering evaluation f and is justified when unrealistic storage i
- requirements are recommended and such recommendations are not reasonably necessary to
' r l 260.52C-1
~ . - . = . _ - - . - .
SNUPPS-C preclude equipment degradation." Also clarify the extent to which Union Electric Company conforms to this Regulatory Guide. '
l.58 The discussion states that factors other-than those stated in ANSI N45.2.6 may be considered for portions of the education and-experience r
requirements. Provide examples of what these factors might be.
1.64 Clarify the extent to which Union Electric Company conforms to this Regulatory Guide. l NRC's position regarding design verification by
! the designer's immediate rupervisor is given i below (cf. item 17.1. 3E2.a of the SRP* ) . .
I In exceptional circumstances, the designer's immediate supervisor can perform the verification provided: ,
(1) The supervisor is the only technically qualified individual.
(2) The need is individually documented j 4 and approved in advance by the !
3 supervisor's management.
l ,
(3) OA audits cover frequency and effectiveness of use of supervisors ,
as design verifiers to guard against abuse.
J Commit to meet this position or provide an f alternative for our evaluation.
1.74 It is the staff position that certificates of conformance and certificates of compliance should be signed by a responsible party from ;
the certifier's orgas ization. Commit to meet I this position or submit an alternative for our
- evaluation. Clarify the extent to which Union i
^
Electric Company conforms to this Regulatory
] Guide.
l.88 Clarify the extent to which Union Electric Company conforms to this Regulatory Guide.
1 l 1.144 Clarify the extent to which Union Electric >
j Company conforms to this Regulatory Guide.
j Also, the first sentence of the disc"ssion is i unacceptable. The staff position given in
- SRP refers to revision 1 of the Standard Review Plan, NUREG-75/087. l 4 r j 260.52C-2
7 J
SNUPPS-C Section C.3.b.(2) of Regulatory Guide 1.144 is a minimum requirement. More frequent audits,
- based on status and importance to safety, are acceptable. Commit to meet the staff position ;
or provide an alternative for our evaluation.- i Response: i
, As you have noted the FSAR Standard Plant Appendix 3A refers to-the Addendum Appendix 3A for the specific regulatory commitment for certain regulatory guides; '
however, in the cases where a reference is not made to. .
the Addendum Appendix 3A the Union Electric commitment is as stated in the Standard Plant Appendix 3A and the ;
same regulatory position is not repeated in the ;
Addendum Appendix 3A. This format accounts for the i absence of the listing of regulatory guides 1.26, !
1.29, and 1.94 in the Callaway Addendum Appendix 3A. t 4
i In the cases of regulatory guides 1.8, 1.58, and 1.144 [
the Standard Plant Appendix 3A reference will be s modified to reflect the same version as noted in the !
Addendum Appendix 3A. 7 i r In regard to regulatory guide.l.146 the Standard Plant Appcndix 3A will be revised to include its listing and i a reference to the Addendum Appendix 3A. [
I
" Discussion" Items l
- RG 1.8 It is believed you intended to reference Section 13.1; 7 nevertheless, Appendix 3A of this Addendum will be revised !
to state that UE complies with the recommendations of this
- regulatory guide with the following clarification-
" Personnel responsible . . . not be certified." !
, RG 1.30 Appendix 3A of this Addendum will be revised to state that
, UE complies with the recommendations of this regulatory [
guide with the following exceptions: "UE concurs . . . !
j (ANSI N45.2.4, Section 6.2.1)."
l RG 1.33 Appendix 3A of this Addendum will be revised to state that l UE complies with the recommendations of this regulatory i guide with the following clarification and exception: !
- " ANSI N18.7-1976/ANS 3.2 references certain other standards I
! which comprise a portion of the regulatory position . . .
r
. is not adopted." l 1
! RG 1.38 Appendix 3A of this Addendum will be revised to state that ;
1 UE complies with the recommendations of this regulatory guide with the following exceptions: "UE takes exception .
. . (Section 6.6, ANSI N45.2.2)." In addition the second paragraph of the discussion will be deleted.
i
! l i i 1
l 260.52C-3
4 SNUPPS-C RG 1.58 Appendix 3A of this Addendum will be revised to r, tate that l UE complies with the recommendations of this regulatory
, guide with the following clarification: "The qualification of UE OC . . . Section 3.4.2." In addition the second 4
paragraph of the. discussion will be revised to state, as .
permitted by the regulatory guide, that in instances where the. education ar.4 experience recommendations of ANSI N45.2.6-1978 are not met, UE will demonstrate by. documented results of written examinations and evaluations of actual ,
work proficiency that individuals possess comparable or equivalent competence. 1 I
RG 1.64 Appendix 3A of this Addendum will be revised to state that UE complies with the recommendations of this regulatory guide with the following exception: "UE maintains . . .
and 4 remain applicable." In addition points 1, 2 and 3'of
, the sta f f position will be adopted and incorporated in Section 17.2.3.
PG 1.74 Appendix 3A of this Addendum will be revised to state that
. UE complies with the recommendations of this regulatory ,
guide. It will be Union Electric's policy to require
, signed certificates of conformance and compliance or certificates accompanied by signed letters of transmittal.
! RG 1.88 Appendix 3A of this Addendum will be revised to state that ;
UE complies with the recommendations of this regulatory guide with the following clarification: "Where the duplicate . . . temperature and humidity."
- RG 1.144 Appendix 3A of this Addendum will be revised to state that
. UE complies with the recommendations of this regulatory guide with the following clari fications: It is Union
. Electric's intent to utilize audits performed by others ,
, (C.5) to fulfill triennial audit requirements. In '
addition, the need for a triennial eudit may be precluded upon evaluation and documentation by the OA Department that the results of mini-audits performed during source inspection and source surveillance activities confirm the i adequacy and implementation of the supplier's OA program.
Section 17.2.18 will be revised to reflect the staff I position outlined under Regulatory Guide 1.144 of Item i
! 260.52C.
i i ;
i i
l 4
l i,
l
~ _ _ _ . - _ . _
_.___. ._ _ . _ _,.~260 52C..4_ _ _ . _ . _ _ _ _ _ _ . . _ _ . . _
SNUPPS-C Item 260.53C The response to item 260.5 is unacceptable. It is the staff position that Union Electric Company execute an agreement with an Authorized Inspection Agency to obtain the independent third-party inspection coverage of Code items which is normally supplied by an Authorized Inspector. Commit to meet this position or provide an alternative for our evaluation. We do not accept the determination of insurability by American Nuclear Insurers as a viable alternative.
Response All Callaway Plant operating phase " code" activities will be performed in accordance with the ASME Code.
This compliance will include the independent third-party inspection coverage of " code" items by an Authorized Nuclear Inspector. Section 17.2.2 will be revised to reflect this commitment. ,
/
i i
260.53C-1
SNUPPS-C
+
Item 260.54C Incorporate more of the response to item 260.7 into ,
the FSAR. That is,-include the statement that: !
"Felated consumables utilized in safety-related structures, systems, and components, although not listed in Table 3.2-1, are.also under the control of the OOAP." Also clarify.in the FSAR that the OOAP is ;
the governing quality assurance program during the ;
operations phase for items in Table 3.2-1 which have a "Y" under the " Quality Assurance" heading and that the programs identified under this heading were those used ;
- during the design and construction phase.
- Response: Section 17.2.2 will.ima revised to include the statement that related consumables utilized in safety- :
related structures, systems, and components, although
- 4 not listed in Table 3.2-1, are also under the control '
of the OOAP. The notes to Standard Plant FSAR Table ;
3.2-1 will also be revised to clarify that the utility's operating quality assurance program is the governing quality assurance program during the operating phase for items in Table 3.2-1 which have a
! "Y" under the " Quality Assurance" heading and that tho ;
programs identified under this heading are those used ;
during the design and construction phase. '!
3
)
)
i i
i i
i t
i i
I l t J60 p $4C-3. _
I
SNUPPS-C 260.55C The response to item 260.10, regarding management overview of OA for the Callaway Plant, relies too l heavily on the NSRB which is chaired by the Manager, ;
Nuclear Engineering. The staff is more concerned with
- the involvement of the Vice President Nuclear and his management in the Callaway Plant OA program. Describe- ,
how they maintain frequent contact with the OA program status.
Response: The Vice President, Nuclear's involvement in the i Callaway OA Program is continuous. As the head of the Nuclear Function, he is a dedicated Vice President
] (i.e., his responsibilities are solely nuclear) responsible for the design, construction, and operation of the Callaway Plant. He maintains an i awareness of program activities through weekly ;
meetings with his general managers and department !
managers ar.d monthly reports provided him regarding function activities. A monthly report provided by the Manager, Quality Assurar.ce specifically concerns OA l Department activitjes and specific quality issues, and !
is provided to all staff meeting-participants to keep them apprised of the OA program status. Exclusive of these scheduled meetings and reports, the Vice ,
President, Nuclear maintains frequent contact and [
communications with OA and other key management' l personnel in the course of routine daily interchanges :
and remains directly accessible to OA management.
l In addition to the aforementioned involvement, it .
I should be noted that the NSRB reports its "1 dings and I recommendations to the Vice President, Nuc- ar for his action, as appropriate. Cumulatively, theoe actions i serve to maintain an awareness of the OA program (
status within the function management outside the OA t Department. I
, t E
f I
I 1 i l
4 ,
f l
I T
l
\ '
l l
i l
260.55C-1
/*
SNUPPS-C 260.56C The meaning of the underlined words in item 260.11 is still unclear. Clarify or delete them.
Response: The underlined words noted in Item 260.11 will be deleted from Section 17.2.3.
+
)
I i
260.56C-1
SNUPPS-C 260.57C Make the implicit intent to " document errors and deficiencies identified in approved design documents and to control (i.e., review and approve) the process of correcting any errors or deficiencies" explicit in the FSAR (See the response to item 260.12.)
Response: The response to Item 260.12 will be incorporated in Section 17.2.3.
l i ,
1 260.57C-1 l
i
4 SNUPPS-C 260.58C The response'to item 260.13 is unacceptable. Our position regarding design verification by the designer's immediate supervisor is given under Regulatory Guide 1.64 in item 260.52. The response to ;'
item 260.52 should be reflected in the response to item.260,13. Our position regarding the timeliness of design verification during the operations phase is given below (cf. item 17.1.3E2 of the SRP).
Design verification, if other than by .
! qualification testing of a prototype or Icad 4
production unit, is completed prior co release for procurement, manufacturing, construction or to another organization for use in other design
- activities. In those cases where this timing [
cannot be met, the design verification may be deferred, providing that the justification for this action is documented x1 the unverified portion of the design outime document and all design output documents, based on the unverified '
data, are appropriately identified and controlled.
Site activities associated with a design or design change should not proceed without verification past the point where the installation would become irreversible (i.e., require extensive demolition
, and rework). In all cases, the design verification should be complete, prior to relying upon the component, system, or structure to :
perform its function.
Commit to meet these positions or provide alternatives '
for our evaluation. We do not accept a commitment to [
complete design verification prior to reliance on the i safety-related component, system, or structure to I perform its safety function as a viable alternative i for the position stated above. I 1 r Response: The response to Item 260.52C under Regulatory Guide l.64 addresses the sta f f position regarding design l verification by the designer's immediate supervisor. '
The response to Item 260.52C will be incorporated in a i revision to the previous response to Item 260,13.
- Regarding the timeliness of design verification during :
the operating phase, Union Electric endorses the staff i position identified in Item 260.58C and will l
, incorporate this position in Section 17.2.3.
F l
t t
l 260.58C-1 !
SNUPPS-C 260.59C Incorporate into the FSAR the clarification provided in the response to item 260.14 that an independent third-level review will be employed as an additional verification when uniqueness or special design considerations make such a review appropriate.
Response: The clari fication provided in response to Item 260,14 will be incorporated into Section 17.2.3 as follows:
An independent third-level review will be employed as an additional verification when Union Electric judges that the design involves unique or special design features.
1 l
l 260.59C-1
SNUPPS-C 260.60C Incorporate the response of items 260.17, 260.23, and 260.48 into the FSAR.
Response: The response to Items 260.17, 260.23, and 260.48 will be incorporated in Sections 17.2.3, 17.2.6, and 17.2.16, respectively.
j 260.60C-1
SNUPPS-C P
I 260.61C The response to item 260.19 limits the OA Department's review of procurement documents to a verification that quality requirements as outlined in Section 3.2.3 of ANSI N45.2.13-1976 have been incorporated, and Section 17.2.4 has been revised accordingly. The staff position regarding the review of procurement documents which the PSAR does not address is given below. (cf.
item 17.1.4A1 of the SRP). ;
i' Procedures are established for the review of procurement documents to determine that quality i requirements are correctly stated, inspectable and controllable; there are adequate acceptance and rejection criteria; and procurement documents have l been prepared, reviewed, and approved in ,
accordance with OA program requirements.
Commit to meet this position or provide an alternative for our evaluation. If a commitment is made to meet this staff position, indicate who (by position title) '
or what group performs the review. i Drawings, whether a part of a procurement document or for in-house use only, should also receive the kind of i review noted in the above staff position and should r also be addressed in the response to this item. l t
Response: The Quality Assurance Department and the internal ;
Union Electric organization originating the [
procurement document perform reviews of procurement documents in accordance with written procedures. .
Collectively, their reviews will address all the [
points of the staff position outlined in 260.61C, I above. The OA Department will review procurement [
documents to assure that the quality requirements are :
, correctly stated and that they have been prepared, reviewed and approved in accordance with OA program requirements. Quality requirements are considered to 3 be those outlined in Section 3.2.3 of ANSI N45.2.13- t 1976. The originating organization will independently review procurement documents to assure requirements (
are correctly stated, inspectable and controllable and i that there are adequate acceptance and rejection ;
criteria.
Drawings will be prepared under a drawing control system which provides for checking methods and review
, and approval requirements. Drawings will be subject to reviews by the originating organization for '
correctness, comoleteness, conformance to design [
criteria, and compliance with applicable codes and !
standards. The OA Department examines drawings, on an t audit basis, for evidence that they have been i
[
r 260.61C-1 , . _ _ .__
L
SNUPPS-C prepared, reviewed, and approved in accordance with OA program requirements.
In addition, as noted in our response to Item 260.65C, the QA Department's review of procurement documents ,
includes concurrence with the need for post award supplier monitoring; i.e., source inspection and/or source surveillance.
The FSAR will be revised to reflect this clarification.
I k
l 260.61C-2
SNUPPS-C 260.62C Incorporate into the FSAR the fact that the approval of a procurement document by an individual with approval authority signifies the technical and quality reviews of the document have been completed. (See the response to item 260.20.)
Response: Section 17.2.4 will be revised to state that the approval of a procurement document by an individual with approval authority signifies the technical and quality reviews of the document have been completed.
i f
260.62C-1
SNUPPS-C ,
i 260.63C The rcsponse to item 260.24 indicates that the OA Department only examines implementing procedures on an ,
audit basis. The staff position regarding the review of maintenance, modification, and inspection ,
procedures is given below (cf. Item 17.2.6.3 of the SRP).
Maintenance, modification, and inspection procedures are reviewed by qualified personnel ,
knowledgeable in OA disciplines (normally the OA .
organization) to determine I,
- a. The need for inspection,' identification of inspection personnel, and documentation of inspection results.
t
, b. That the necessary inspection requirements, l
- methods, and acceptance criteria have been l identified.
Commit to meet this position or provide an alternative for our evaluation. If a commitment is made to meet this staff position, indicate who (by position title) or what group performs the review.
Response: The staff position outlined in Item 260.63C is acceptable and is met in the following manner.
The OA Department reviews administrative procedures;
- the QC Group reviews maintenance and modification procedures; and the OC Group is responsible for_the !
preparation of inspection procedures and/or checklists I j to support maintenance and modification activities. !
Collectively, these reviews by the OA Department and i 4
the QC Group determine:
- a. The need for inspection, identification of i inspection personnel, and documentation of ;
inspections results; and [
L
- b. That the necessary inspection requirements, l methods, and acceptance criteria have been j identified. i t
^
This commitment will be incorporated in Section 17.2.6 of the FSAlt .
Y l
260.63C-1
SNUPPS-C 250.64C On page 17.2-25, Revision 2 states that the extent of 9 acceptance methods and associated verification ,
activities will vary as a function of the relative importance and. complexity of the purchased item or !
, service and the supplier's past performance. Clarify l 1
that the "importance" mentioned is the items or i i service's importance to safety or relative safety importance. l t
Revision 2 then goes on to state that procedures will provide for the acceptance.of simple "off-the-shelf" !
items based exclusively on receiving inspection with no quality verification documentation requirements. <
It is the staff's position that the- involvel design engineering organization ard quality assurance j 1.
organization should jointly determine the extent of
' inspection verification and the quality verification i documentation requirements based on the item's end l use. Revise the submittal to reflect this position.
l Response: Section 17.2.7 will be revised to state that the -
extent of the acceptance methods and associated l-verification activities will vary and be a function of !
the purchased item's or service's complexity and relative safety significance; as well as the ;
supplier's past performanco. j In regard to the concern that the acceptance of "off-the-shelf" items will exclude a requirement for i
- quality verification documentation, it should be noted that in these types of procurements it is our intent that supplier-generated verification documentation, only, will not be required. Documentation will be generated as a result of receiving inspection '
activities. Section 17.2.7 will be revised to reflect ;
4 this clarification. i l l Y
i t
i 260.64C-1 !
I !
A SEUPPS-C 260.65C The response to item 260.25 states that the originating organization (of procurement documents) makes judgements .regarding verificat lon activities and "
that the OA Department-will not review and approve specific supplier monitoring activities prior to implementation. Regarding such review and approval, the staff position is given below (cf. item 17.1.6A2 of the SRP).
The OA organization, or an individual other than the person who generated the document but
- qualified in quality assurance, reviews and ,
concurs with these (procurenent) documents with ;
i' regards to OA-related aspects.
1 Commit to meet this position or provide an alternative i for our evaluation. If a commitment is made to meet this staff position, indicate who (by position title) i or what group performs this review. If not the OA
- -organization, discuss OA qualifications. E i
i
- Response
- The staff position outlined in Item 260.65C is ;
j acceptable and Section 17.2.7 will be revised to state [
i that the OA Department will review procurement [
documents and concur with the originating j organization's determination of need for post award i supplier monitoring; i.e., source inspection and/or t source surveillance. l
. I i !
5 1
A ,.
l !
r i'
{
t I
L l
1 F
i i
r i
i !
r I
r l i 260.65C-1 ;
SNUPPS-C .
c 260.66C The staff -ition regarding quality assurance fer the procuremens ,i spare or replacement parts as reflected in item 260.27 is given below (cf. item 17.1.7A4 of the SRP). l Procurement of spare or replacement parts for structures, systems, and components important to safety is subject to present OA program controls .
Commit to meet this position or provide an alternative
.r our evaluation. j Response: The staff position of Item 260.66C is acceptable with the following clarification:
The procurement of spare or replacement parts for ,
safety-related structures, systems, and components is ;
subject to present QA program controls, to codes and standards, and to technical requirements equal to or better than the original technical requirements, or as l'
- required to preclude repetition of defects. This position will be incorporated in Section 17.2.4.
I d
i i
+
i f i
t i
1 ,
2 60 . 66C--1 _ _ . . _ _ _ , _ _ . , _ _ _ _ _ . _ . _ _ _ _ , _.
t4' SNUPPS-C i
260.67C Concerning the permanently installed instrumentation i i
for the Callaway Plant, it 10 the staff position that this equipment should be under the OA program controls described in 17.2.12 of the FSAR. Commit to meet this position or provide an alternative for our evaluation. F l
Response Permanently installed safety-related process ;
instrumentation will be afforded the control measures 1 described in 17.2.12 consistent with the surveillance i I
testing program and to the e< tent that the method and interval of calibration for rach installed instrument l and control device shall be defined and shall be based l on the type of equipment, stability, reliability l
. characteristics, required accuracies nnd other l
, conditions affecting calibration. As presently stated
! in Section 17.2.12 the calibration and control program l shall provide for "the calibration of M&TE against a ;
i reference standard having an accuracy of at least four ;
i times the specified tolerance of the M&TE. Reference standards of equal tolerance shall be accept'ble when ,
equipment to meet specified requirements is not !
commercially available." In addition a special j calibration shall be performed when the accuracy of an j
- installed process instrument is questionable. The l calibration accuracy ratio of M&TE to permanently ,
installed process instrumentation will be 1.0 or !
better. Section 17.2.12 will be revised to reflect !
this clarification.
1 i !
I 9
e 4
P P
i I
, 260.67C-1 t
___...,.m-- . . _ . - . _ _ _ . _. ._ _ . _ . , _ . __ ., - __ . , _ _ _
_ . _ _ . . _ _ . . - __~ _ _ _ _ _ . _ _ _ . _ . .
SNUFPS-C 260.68C As discussed under Regulatory Guide 1.38 in item 260.52, above, clarify the basis for relaxation of manufacturer's storage requirements in Section.17.2.13 of the Callaway FSAR.
Response: The response to Item 260.36 will be incorporated in Section 17.2.13.
l f
i r
r c
i i
l l
l 260.68C-1
SNUPPS-C 260.69C Item 260.41 requests a commitment that alterations of the sequence of required tests, inspections, and other operations important to safety are subject to the original review and approval controls. The response does not provide such a commitment. Clarify.
Responne: Required safety-related inspections, tests, and operations and their sequencing are performed in accordance with plant level procedurec which are reviewed by the ORC and approved by the Plant Superintendent. Except in the case of temporary changes (non-intent changes), which are allowed by the Technical Specificationc nnd which are adrninistratively controlled, any deviations from procedural requirements will be subject to the original review and approval controls, (i.e., they will be documented, reviewed by the ORC, and apprc ed by the Plant Superintendent). Section 17.2.14 will be revised to reflect this clarification.
260.69C-1
f SNUPPS-C 260.70C Clarify what is meant by the statement in 17.2.14 that procedures shall address methods for " initiating, maintaining, and releasing equipment control for maintenance . . ." (See item 260.42.)
Response. This sentence is intended to address the need for controlling the release of equipment or systems for maintenance and the control of equipment to maintain personnel and reactor safety and thereby avoid the unauthorized operation of equipment. The referenced sentence will be revised to state that procedures shall address measures for the release and control of equipmant during periods of maintenance; thereby maintaining personnel and teactor safety and avoiding the unauthorized operation of equipment.
I I
260.70C-1 .
l