b ARKANSAS POWER & LIGHT COMPANY 5.-
POST OFFICE BOX 551 UTTLE ROCK. ARKANSAS 72203 (50*: 371 e.OOO February 19, 1981 l
1R-0281-10 Mr. Thomas H. Novak Assistant Director for Operating Reactors Division of Licensing U. S. Nuclear Regulatory Comm.
Washington, D.C.
20555
SUBJECT:
Arkansas Nuclear One - Unit 1 Docket No. 50-313 License No. DPR-51 Schedules for Submittal of i
EFW Upgrade Information (File: 1510.3).
Gentlemen:
Your letter of January 15, 1981 requested AP6L to submit a schedule for design submittals for NP.C review, a schedule for submittal of Technical Specifications which would be required, and a schedule for fina1 ' implementation of.the emergency feedwater upgrade on ANO-1.
APSL will submit a complete design package by June 1,1982 and the Technical Specifications prior to the Fifth Refueling OutaJe after NRC approval of the final design pockage.
The installation will occur during the ANO-1 Fifth kefueling Outage currently scheduled for the Fall of 1982.
This will allow at Icast 90 days for NRC review of
(
the final design.
Very.truly yours, huna f. &
David C. Trimble Manager, Licensing DCT:LDY:1p 1