Advises That Corrective Actions in Response to Violations Noted in IE Insp Repts 50-352/80-12 & 50-353/80-10 Will Be Completed by 810701
ML19350F099
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 06/03/1981
From: Kemper J
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML19350F096 List:
References
NUDOCS 8106240211
Download: ML19350F099 (1)


Text

.

O-PHILADELPHIA ELECTRIC COMPANY 2301 MARKET STREET P.O. BOX 8699 1881 -1981

. PHILADELPHIA. PA.19101 (215)841 45o2 vses#mtalOENT JUN 3 1981 Mr. Boyce Grier, Director United States Nuclear Regulatory Commission Office of Inspection and Enforcement, Region I 631 Park Avenue King of ? russia, PA 19406

Subject:

US NRC Region I Letter dated August 27, 1980 RE: Site ed Office Inspections of June 16-27, 1980 Inspection Report No. 50-352/80-12 & 353/80-10 Limerick Generating Station - Units 1 and 2

Reference:

J. S. Kemper Letter to.B. Grier, dated 9/26/80 File: QUAL 1-2-2 (352/80-12 and 353/80-10)

Dear Mr. Grier:

In our response in the re'ferenced letter, to Infraction C of the subject inspection, we indicated that corrective action would be completed by December 31, 1980. However, we have recently discovered that this task is not complete.

'Ihe corrective action, which consists of placing notes on a certain class of drawings to indicate that they do not reflect the as-built conditions, will be_ completed by July 1,1981.

Sincerely, A iUf FJC/mmk cc:

.J. P. Durr, Resident NRC Inspector Director of Inspection and Enforcement United States Nuclear Regulatory Commission Washington, D. C.