Forwards Plans & Schedules for Implementing Fire Protection Requirements in 10CFR50,App R,Sections Iii.G.J & III.0.Plans for Meeting Requirements Accepted in Fire Protection Evaluation Repts Also Encl
ML19350C736
Person / Time
Site: Quad Cities  
Issue date: 03/18/1981
From: Janacek R
COMMONWEALTH EDISON CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 8104060644
Download: ML19350C736 (4)


Text

Commonweilth Edison l,' Q cne F.rst NaSonal P'in Chec3co. DI ncis Access Reply to: Post Office Box 767 Chictgo. Ilknors 60690 March 18, 1981 Mr. Harola R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

Quad Cities Station Units 1 and 2 Fire Protection Features to meet 10 CFR Part 50, Appencix R NRC' Docket Nos. 50-254/265

Dear Mr. Denton:

In accordance with the requirements of 10 CFR 50.48(c)(5),

Commonwealth Edison Co. hereby submits our plans and schedules to meet the provisions of 10 CFR Part 50, Appendix R, Sections III.G, III.J., and III.0 for Quad Cities Units 1 and 2.

Attachment I contains our plans for implementation of the requirements of Appenaix R, Sections III.G, III.J, anc III.0.

In adcition, Attachment 2 contains our plans and schecules for meeting other fire protection reauirements which were previously accepted W

  • ho NRC Staff in Fire Protection Evaluation Reports or supplemer As indicated in these attachments, Commonwealth Edison Co.

believes it will meet the applicable requirements of 10 CFR 50.48 and Appenaix R for Quad Cities Units 1 and 2 in accordance with the schedules provideo therein.

Please address any questions concerning this matter to this office.

Very truly yours, A

L Robert F Janecek Nuclear Licensing Aaministrator Boiling Water-Reactors Attachments

'cc:

RIII-Inspector, Quac Cities 1469B jbli i

il 1

i820.4oeo(gy p

Quad Cities etation Units 1 anc 2 Acce7 dix R Items Item III.G.

In response to item III.G. (safe shutdown) of Appencix R Commonwealtn Edison Company has made the following suomittals:

1.

" Fire Protection Safe Shutcown Analysis" Quad Cities Units 1 ano 2 datec, July 1978.

This document was transmitted to the NRC in a letter to T.A.

Ippolito from M.S.

Turbak dated July 31, 1978.

2.

" Fire Protection Safe Shutoown Analysis" Supplement 1 Quad Cities Units 1 and 2 dated Septemoer 1979.

This document was transmi'.ted to the NRC in a letter to T.A.

Ippolito from R.F.

Janecek datec October 1, 1979.

3.

" Fire Protection Safe Shutcown Analysis" Supplement 2 Cold Shutdown dated January 1980.

This document was transmitted to the NRC in a letter to T.A.

Ippolito from R.F. Janecek cateo Maren 4,

1980.

4.

Response to NRC letter cated October 22, 1979 " Requesting Acoltional Information on Fire Protection Safe Shutcown Analysis".

This information was transmitted to the NRC in letters to T.A.

Ippolito from R.F.

Janecek catec January 23, 1980, February 29, 1980, and June 6, 1980 A fire area has recently been identified where a fire could impede safe shutcown and which has not been included in earlier suomittals on safe shutcown.

The area identified is the DC Distribution Center for each unit.

A fire in this area could result in the loss of 125v OC power to cotn safety civisions for the unit in which a fire is postulated.

Corrective action is Deing taken which will isolate DC power in this fire area for one safety civision from the seconc safety division with a three hour fire barrier.

Details of this analysis and design modifications will be suomittea by May 19, 1981.

The work associated with this modification will be completed in accordance with Paragrapn 50.48(c)(A).

m

7

-2

.]

The preceding list of submittals and i nformation describe a method for safely shutting down the plant in the event of fire in any other fire area which, we believe, meets the intent of item III.G. of Appendix R.

Item III.J.

In response to item III.J. of Appendix R Commonwealth Eoison Company has committed to install emergency lighting units with an 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> battery power supply in areas needed for operation of safe shutdown equipment and access and egrest routes thereto.

This installation will be completed in accorcance-with Paragraph 50.48(c)(2), 9 months after the i

effective cate of Appendix R (November 17, 1981).

3 l~

Item III.O.

i i

Item III.O. i s not applicable to Quad Cities Station since the i

containments are inerted during normal operation.

i i

i i

f f '

+

i i

r 4

4 l

~

m.

m.

.-u.

- ma.m

---. m

. u-m a

.-m a

m.m

.m

.a -.

m-.6

_,_.___________a-mu---l

Quad Cities Station Units 1 anc 2 Safety Evaluation F.ecort Items On February 12, 1981 in a letter to J.S.

Abel from T.A. Ippolito the NRC issued Supplement 2 to the Fire Protection Safety Evaluation Report for Quad Cities Units 1 ano 2.

Two incomplete items are identified in the Safety Evaluation Report Supplement 2.

1.

The placement of.the MG set foam suppression system control panel will be relocated such that it will not be within the influence of an MG set fire.

2.

Smoke detectors will ce bench tested tc verify that the detectors will responc to comoustion prooucts that might ce present in eacn area where detectors are located.

Commonwealth Edison Company is committed to finish these two incomplete i; ems.

They will be completed in accoroance with Paragraph 50.48(d)(2), 12 months after the cate of the NRC staff Fire Protection Safety Evaluation Report accepting such features which is February 12, 1982.

(12 months after the SER Supplement dated Feoruary 12, 1981).

1469B 4