@ Address Reply to: Post Office Box 767 Comm:nw;cith Edicon One First Na!>onal Plaza. Chicago, Ilknon
(~'}
Chicago, Illinois 60690
\\_/
March 4, 1981 Mr. James G. Keppler, Director Directorate of Inspection and Enforcement - Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137
Subject:
Byror. Station Units 1 and 2 Braidwood Station Units 1 and 2 Supplemental Response to IE Inspection Report Nos.
50-454/80-09, 50-455/80-08, 50-456/80-04, and 50-457/80-04 NRC Docket Nos. 50-454, 50-455, 50-456 and 50-457 References (a):
July 11, 1980 letter from D.
L.
Peoples to James G. Keppler (b):
July 18, 1980 letter from D.
L.
Peoples to James G.
Keppler (c):
October 15, 1980 letter from J.
S. Abel to James G.
Keppler (d):
December 11, 1980 let'3r from J.
S. Abel to James G.
Keppler
Dear Mr. Keppler:
In Reference (d), Commonwealth Edison Company indicated that a technical assessment of the coating requirements for repair of spot weldc on UNISTRUT hangers would be available by February 15, 1981.
The supplier has still not completed his study in sufficient detail for an assessment by Commonwealth Edison.
Completion of the supplier's study and a technical asseJsment by Commonwealth Edison are now expected to be available by March 23, 1981.
Please address any questions that you might have concerning this matter to this office.
Very truly yours, J. S. Abel Director of F 10406 0 RD Nuclear Licensing a33g 90'8 4