YA Thomas J. Martin Public Service Electric and Gas Company 80 Park Plaza Newark, N.J. 07101 201/430-8316 VicD President Engineering and Construction March 9, 1981
,fE
' 7"{T'gb Mr. Doyce H. Grier, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission
$h p(/'/'
6
/
g/
4./j*f Region 1 E1,, p4gOj7 631 Park Avenue
' King of Prussia, Pennsylvania 19406
_g
Dear Mr. Grier:
4%
~NRC.-IE BULLETIN NO. 80-21 s
y VALVE YOKES SUPPLIED BY o
-MALCOLM FOUNDRY COMPANY, INC.
NO. 1-AND 2 UNITS HOPE CREEK GENERATING STATION In reply to IE Bulletin No. 80-21-dated November 6, 1980, we
~
- offer the following at this time:
On~ January 5[1981,wesuppliedan' interim.reporttotheNRC indicating-that the_^ investigation being conducted by Bechtel Power Corporation, our Architect Engineer,.was continuing.
-s_
'Bechtel'is currently surveying its suppliers, and reports to' PSE&G^that all vendor responses received thus far. confirm that
'no valve parts were supplied by Malcolm Foundry.
- However, Bechtel is still waiting for a response from one supplier, Colt. Industries.
It is expected that a final response will be ready for trans-mittal to the'.NRC by April 10, 1981.
~
Very truly-yours,-
- CC NRC OIfice of.-Inspection and Enforcement
~
. Division of Reactor Construction Inspection
--Washington, - DC -
-810.4060 03Y t