Text
\\
%C
@ Consumers Power Company General Offices: 212 West MicP.lgen Avenue, Jackson, M 6chigan 49201 * (517) 788 4550 March 13,1981 Cs j
/d
/gYg[
1 1
Mr Janes G Keppler y'
Office of Inspection and Enforcement Q
/
6
"g 2079
-3 Region III US Nuclear Regulatory Co==ission
%% g 'ota 799 Roosevelt Road 4
d'8 Glen Ellyn, IL 60137 DOCKr 50-155 - LICENSE DPR cd t '
BIG ROCK POINT PLANT - RESFCNSE TO IE BULLETI?i NO 81 SURVEILLANCE OF MECHANICAL SNUBBERS IE Bulletin No 81-01 dated January 27, 1981, requested Consurers Power Company to provide a schedule for an inspection progra: covering mechanical snubbers.
This request resulted ta';.ly frc= several instances of failures of techanical snubbers supplied by International Nuclear Safeguards Corporation (INC).
Big Rock Point (BRP) does not have any snubbers manufactured by INC; therefore, those actions of the bulletin relating to INC snubbers are not considered appli-cable. All (13) mechanical snubbers at BRP.re manufactured by Pacific Scientific Corporation. As noted in the bulletin, LER 79-017 (May 10,1979) identified i=-
proper installation of the snutters in that a spherical washer was omitted fror l
the transition tube. This problem was identified by visual inspection. Subse-quently, all techanical snubbers were visuall" inspected and two were functionally tested satisfactorily in the presence of Mr I T Yin, NRC inspector.
It is also our understanding that the Trojan Plant has functionally tested satisfactorily fifty of their Pacific Scientific snubbers.
Therefore, it is our determination that no immediate action is required to assure continued operability of the ERP snubbers.
In response to the request of this bulletin, ve have scheduled visual inspection ancF functional testing for the ERP snubbers to be performed at the next refueling out age.
The next refueling outage is currently scheduled to occur in the first quarter of 1982.
0 W$4W Gregory C Withrow Senior Licensing Engineer CC Director, Office of Nuclear Reactor Regulation Director, Office of Inspection and Enforcement MAR ] g jggg ERC Re ident Inspector - Big Rock Point 8108231 u%
\\.
CO?;SlWEFS POWEB COMPANY Big Rock Point Plant IE Bulletin No 81-01 Docket No 50-155 License No DPR-6 At the request of the Commission and pursuant to the Atomic Energy Act of 195h, and the Energy Reorganization Act of 197h, as amended and the Cc= mission's Rules and Regulations thereunder, Consumers Power Company submits our response to IE Bulletin No 81-01, dated January 27, 1981, entitled,
" Surveillance of Mechanical Snubbers". Consumers Power Company's response is dated March 13, 1981.
CONSUMERS POWER COMPANY R /a IM'6Y By R B DeWitt, Vice President Nuclear Operations Sworn and subscribed to before me this 13th day of March 1981.
r!
DW mhk
' Helen I Dempski, Notary P6blic Jackson County, Michigan My commission expires December ik,1983 l
@