Initial Approach to Power Tests (B-Series).
ML19347C996
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 03/05/1981
From:
PUBLIC SERVICE CO. OF COLORADO
To:
Shared Package
ML19347C995 List:
References
NUDOCS 8103100483
Download: ML19347C996 (2)


Text

'

(, -- )

% ,/

THE FORT ST. VRAIN INITIAL APPROACH TO POWER TESTS (B-SERIES)

INTERIM REPORT 18 Report for Period Ending February 22, 1981 i

8103100%'S>

Interim Report 8 covering the 90 day period ending August 22, 1978, re-ported the completion of all tests up to 70% of plant load. Since the Nuclear Regulatory Commission did not release the plant for operation at power levels

, in excess of 70%, no further Initial Approach to Power Tests were performed

, during the 90 days ending February 22, 1981.

The Fort.Sc. Vrain Nuclear Generating Station was accepted for commercial operation at 70% power by Public Service Company of' Colorado on July 1,1979.

Future interim reports will report the results of any startup tests at power levels above 70%.