1 SNUPPS Stenderdised Nuclear Unit j
Power Plant Systern 5 Choke Cherry Road Rockvdle, Marytend 20060 (301) 8894010
]
October 9,1980 SLNRC 80- 47 FILE: 0542/0491.3 l
SUBJ:
SNUPPS Ouality Assurance Prograrry, for Design and Construction I
Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 205E5 Dockets: 50-482, 50-483, 50-486 Ref: a) SLNRC 80-18 dtd. 4/14/80: SNUPPS QA Preograms for Design and I
Construction
{
b) SLNRC 80-25 dtd. 5/27/80: QA Programs for Design, Construction and Fire Protection c) SLNRC 80-33 dtd. 7/28/80: QA Programs for Design, Construction l
and Fire Protection 1
Dear Mr. Denton:
By ccpy of this letter, we are forwarding to Mr. W. P. Haass, Chief, Quality Assurance Branch, USNRC, an uncontrolled copy of Revision 1 to the subject QA Program descriptions.
This revision incorporates agree-l ments, commitments and clarifications pertaining to the SNUPPS quality assurance programs as summarized in the Reference a), b) and c) trans-mittals.
With exception of the changes indicated in the reference transmittals, plus daletion of the Sterling Site Addendum, these pro-gram descriptions are unchanged from Revision 0, transmitted to NRC last December; Ref. SLNRC 79-24 r
Controlled copies of the revised QA program descriptions have been dis-i tributed to NRC Offices of Inspectica and Enforcement for Regions I, III, IV. Revisions will similarly be distributed to these Regions.
Very truly yours, r
S. J. Seiken 0 \\
l o
b(O QA Manager SJS:dck:3a16 Encl: See subject
\\)
cc:
W. P. Haass, USNRC w/ Encl.
J. K. Bryan, UE w/o encl.
D. T. McPhee, KCPL w/o encl.
G. L. Koester, KGE w/o encl.