(J')
C mmonwecith Edison
~s
- Je )
One hre Na' onal Prta. Chierp til.ncys
% -)
Accress Re:', to Post Offica Box 767 O
4 Chugo. Ithnois 60690 I
September 8, 1980 t.
Mr. James G.
Keppler, Director Directorate of Inspection and Enforcement - Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137
Subject:
Quad Cities Station Units 1 and 2 Response to IE Inspection Report l
Nos. 50-254/80-17 and 50-265/80-17 NRC Docket Nos. 50-254/265 l
Reference (a):
A.
B. Davis letter to C.
Reed dated August 18, 1980 l
Dear Mr. Keppler:
Reference (a) transmitted'the results of an inspection conducted by Mr. P.
C. Lovendale on May 28, 1980, of a shipment of radioactive waste that arrived at Nuclear Engineering Company, Richland, Washington, from the Quad Cities Nuclear Power Station.
Appendix A to Reference (a) identified one item of noncompliance with NRC requirements.
Our response to this item of noncompliance is provided in Attachment A.
Please address any questions concerni'ng this matter to this office.
Very truly yours,
[
[ J. S.
Ab 1
/
Director of Nuclear Licensing cc:
RIII Resident Inspector, Quad Cities Attachment 6521A 8 010 010 7f3 SEP 1 1 85T