Responds to IE Bulletin 80-15 Re Loss of Emergency Notification Sys W/Loss of Offsite Power.Emergency Notification Sys Would Be Unaffected by Loss of Offsite Power
ML19347B171
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 09/05/1980
From: Pasternak R
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
IEB-80-15, JAFP-80-706, NUDOCS 8010010740
Download: ML19347B171 (2)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Y%

.y POWER AUTHORITY OF THE STATE OF NEW YORK JAMES A. FITZPATRICK NUCLEAR POWER PLANT S

RAYMOND J. PAsTERNAK P.O. Box 41 Re Went Menage, Lycommg, New York 13093 315-342 3340 September 5,1980 SERIAL: JAFP 80-706 Boyce H. Grier, Director United States Nuclear Regulatory Commission Region I 631 Park Avenue King of Prussia, PA.

19406

SUBJECT:

NRC I&E BULLETIN NO. 80-15 POSSIBLE LOSS OF EMERGENCY NOTIFICATION SYSTEM (ENS) WITH LOSS OF 0FFSITE POWER

Dear Mr. Grier:

The FitzPatrick Plant Staff has completed the actions required by the subject Bulletin. As part of those actions, we have determined the following:

1)

The Emergency Notification System (ENS) installed at the FitzPatrick Plant is powered by the local telephone company.

Tripping of the branch circuits within the plant which service the PBX telephone room, confirms that in the event of a loss of offsite power, the ENS would be unaffected.

2)

The local telephone company conducted a test in which the normal power to that portion of their system which supplies power to the ENS was interrupted and representatives of the telephone company and plant staff verified the operability of each of the ENS extensions installed at the FitzPatrick Plant.

During the time period in which normal power is interrupted, power for the ENS is provided by a battery and inverter system which is owned and operated by the telephone company.

8010010 $d g

op Boyce H. Grier, Director September 5, 1980 United States Nuclear Regulatory Comission JAFP 80-706

SUBJECT:

NRC I&E BULLETIN 80-15 Page 3)

The FitzPatrick Plant has revised administrative controls which require notification of the NRC Operations Center by commercial telephone within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> whenever 1 or more ESN extensions are not operating properly.

In the event that such notification can not be completed by comercial telephone, notification will be attempted by relaying the message via the ENS which is installed at the Nine Mile Point Unit 1 Nuclear Station located nearby.

Very truly yo,urs,

,/

j % !

,s lY

&fsd W(

RJP:VC:brp RAYM0ND J. PASTERNAK Distribution:

RESIDENT MANAGER Director NRC Office of Inspection & Enforcement Subscribed and Sworn to before Washington, D.C.

20555 me this 5th day of September, 1980 George T. Berry, PASNY, NY0 o

Q d

J. P. Bayne, PASNY, NY0 1 S u l,f.

.i n w - m _3. k G. M. Wilverding, PASNY, NY0

}

Nota (y Public M. C. Cosgrove, PASNY, JAF r

M. N. Brosee, PASNY, JAF BEVERLY R. PRUCNAL. f4625499 R. J. Converse, PASNY, JAF Notary Public - State of New York J. W. Austin, PASNY, JAF Appomted in osweso county My Commissa Empires March 30,193 NRC Resident Inspector Document Control Center

,