ML19347A734

From kanterella
Jump to navigation Jump to search
Submits Response to IE Bulletin 80-20 Re Failures of Westinghouse Type W-2 Switches.Investigation of Subj Bulletin Is Still in Progress.Expects to Submit Final Rept by 801005
ML19347A734
Person / Time
Site: Waterford Entergy icon.png
Issue date: 09/09/1980
From: Maurin L
LOUISIANA POWER & LIGHT CO.
To: Seyfrit K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
IEB-80-20, LPL-15062, NUDOCS 8009300100
Download: ML19347A734 (1)


Text

-

71 G w \

f l

I LOUISIANA 242 ceuacNee sraser  !

P O W E A, & L i G H T[ P O 80X 6008 e New CRLeANS. LOUISIANA 70174 * (504) 366-2345 i

E!asYlO l s,,,,,,,, ,, 1930 l

LPL 15062 Q-3-A20.03.14 Mr. Karl V. Seyfrit, Director Region IV U. S. Nuclear Regulatory Cocnission Office of Inspection & Enforciement 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76012

SUBJECT:

Waterford SES Unit No. 3 Docket No. 50-382 IE Bulletin No. 80-20 Failures of Westinghouse Type W-2 Spring Return to Neutral Control Switches

Dear Mr. Seyfrit:

Our investigation of the subject bulletin is still in progress at this time.

We expect to complete our engineering review and evaluation by October 15, 1980, at which time we will submit our final report.

If you have any questions, please advise.

Yours very truly, i G L. V. Maurin Project Director LVM:WMA:meb cc: U. S. Nuclear Regulatory Commission Division of Reactor Operations Inspection Office of Inspection and Enforcement L'a r.. Ington , D .C .