o UNITED STATES
['
NUCLEAR REGULATORY COMMISSION g
- y WASHINGTON, D. O~ 20666
\\*...+/
APR 2 81981 Docket No.:
50-341 MEMORANDUM FOR:
B. J. Youngblood, Chief. Licensing Branch No. 1, DL FROM:
L. L. Kintner, Project Manager, Licensing Branch No.1, DL
SUBJECT:
MEETING WITH DETROIT EDISON REGARDING THE REVIEW 0F THE FERMI 2 APPLICATION FOR AN OPERATING LICENSE DATE AND TIME:
May 4 - May 8, 1981 9:00 AM LOCATION:
Fermi 2 Plant Monroe, Michigan PURPOSE:
To conduct fire protection review (see attached agenda)
PARTICIPANTS:
Detroit Edison Company J. Honkala, L. Schuerman, W. Colbert, W. Fahrner NRC Staff R. Anand, R. Fitzpatrick, A. Saeed, J. Beam (Gage Babcock)
L.
. Kintner, Project Manager Iicensing Branch No. 1 Division of Licensing
Enclosure:
As stated cc:
See next page 810501ol%
F
Mr. Harry Tauber Vice President igineering & Construction Detroit Edison Company 2000 Second Avenue Detroit, Michigan 48226 cc:
Eugene B. Thomas, Jr., Esq.
David E. Howell, Esq.
LeBoeuf, Lamb, Leiby & MacRae 21916 John R 1333 New Hampshire Avenue, N. W.
Hazel Park, Michigan 48030 Washington, D. C.
20036 Mr. Bruce Little Peter A. Marquardt, Esq.
U. S. Nuclear Regulatory Commission Co-Counsel Resident Inspector's Office Thb Detroit Edison Company 6450 W. Dixie Highway 2000 Second Avenue Newport, Michigan 48166 Detroit, Michigan 48226 Dr. Wayne Jens ~
Mr. William J. Fahrner Detroit Edison Company Project Manager - Fermi 2 2000 Second Avenue The Detroit Edison Company Detroit, Michigan 48226 2000 Second Avenue Detroit, Michigan 48226 Mr. Larry E. Schuerman Detroit Edison. Company 3331 West Big Beaver Road Troy, Michigan 48084 1
l
- ?
e
__~ -____
~ h i
AGENDA FOR SITE VISIT - FIRE. PROTECTION (FERMI 2) 1.
- ntroduction by NRC f
a.
Purpose of Visit 5.
Method.of Site Review -(Comparison with 10 CFR 50 Appendix A, GDC 3 and Appendix R) 2.
Comments by Licensee a.
Any restrictions S.
Brief description of plant layout c.
Description of cable design and cable tray identification d.
Special tests of fire retarding materials or construction to verify protection ratings e.
Discussion of initial questions 3.
Plant Review a.
Examine each of the following safety-related areas:
(1)
Control Room / Computer Room (2)
Cable Spreading Room (3) Battery Rooms (4) Diasel Generator Rooms (5) Switchgear Rooms (6)
Relay Rooms (7) Safety-Related Pump Areas (including Residual Heat Removal Conglex)
(8)
Reactor Building (where accessible) i b.
Examine other areas / hazards, including:
(1) Turbine lubrication and control oil storage and use areas (2)
Diesel Fuel / Auxiliary Boiler Fuel Oil Storage Tanks (3)
Radwaste Area 4)
Decontamination Area 5)
Records Storage Area
- 6) Auxiliary Boiler Area (7)
Fire Pump Areas (8). Oil Filled Transfomers (Indoor and Outdoor)
(9) Hydrogen - Storage, use, and processing areas e
~
f c.
As applicable, the above areas will be examined for:
(1) General conditions, congestion, and accessibility (2) Separation between redundant trays and conduits Barriers and fire stops Fire detection and suppression equipment Ventilation Systems and controls Floor drains (7) Communications equipment (8) Lighting (9) Combustible materials (10) Equipment protection from water damage (11) Ability to contain fire, or isolate from external fire (12) Means for containing oil spills (13) Means for detecting hydrogen accumulation or loss of ventilation (battery rooms) 4.
Alternate Shutdown Capability 5.
Administrative Controls Discuss:
a.
Fire Protection Organization b.
Fire Hazard Control c.
Control of Ignition Sources d.
Fire Brigade Organization and Training e.
Plant Personnel Indoctrination
'f.
Fire Fighting Plans g.
Quality Assurance for Fire Protection h.
Controls over Fire Protection Systems
- i. Lighting and Comunication t
t APR 2 81981
__. +b'j;iY_ _n"
-)
- n.. t - + riin J. 5t?l7 s i, ne T
O.
'!.' ?. 5.2110
- f. j e i i 2I.".n C: 1. rich f i l e I. ituteey l4. riu3ha
- ch *'O'J'E F I. C J :,0 h.
Niii *cl
[.
Ei ;. :n C. <'".4'r1t R. Purrl; I.. t r.i ch ton T. Nova!.
f' E r'G t 9 Varga R. faaer
' : ;l i :.
=
F Ma r.mi o
- C;. P 9
4
.m. inadani R. Reid g
f p F [1 ACF.5 (16) g *'
I-Attorney, OELD
\\
R. Tedesco J. Youn61 rad OIE (3)
- a. wk '
8:
APR 2 819815 T2 ocr.(7) r i % -De* L. Kintner u.s, %%
J. i, P, i l h -
minot,
Littn:ing Assistant !1. Rushcrook t'
G. Lainas J
. Recaptiorlis t D. Cru;cniieiC g,
TEIA.
i gp
... F u; n ' '
m ieDeux, I&u J. Olshini 1 V. i4c.n re R. Volhrer I&E Headquarters R. Bosnak I&E Region I F. Schauer I&,E Region II R. E. Jackson I&E Region III
~
G. Lear I&E Region IV V. Noonan I&E Region V S. Pawlicki V. Benaroya NRC
Participants:
Z. Rosztoczy R Anand W. Haass R. Fitzpatrick D. Muller A. Saeed R. Ballard J. Beam (Gage Babcock)
W. Regan J. D. Sal tzman D. Ross P. Check Chief, Power Systems Branch O. Parr bcc: Applicant & Service, List F. Rosa W. Butler W. Kreger R. W. Houston Chief. Radiological Assessment Branch W. Garrlill L. Rubenstein T. Speis W. Johnston B. Grimes S. Schwartz
- =