ML19345F851

From kanterella
Jump to navigation Jump to search
QA Program Insp Rept 99900053/80-02 on 801027-30.No Noncompliance Noted.Major Areas Inspected:Implementation of 10CFR50 App B Criteria & Applicable Codes & Stds,Including Mfg Process Control & Corrective Actions for Deficiencies
ML19345F851
Person / Time
Issue date: 12/11/1980
From: Hunter V, Kiessel R, Whitesell D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV), NRC OFFICE OF INTERNATIONAL PROGRAMS (OIP)
To:
Shared Package
ML19345F835 List:
References
REF-QA-99900053 NUDOCS 8102190422
Download: ML19345F851 (5)


Text

.

O U. S. h0 CLEAR REGULATORY COMMISSION OFFICE OF INSPECTIO,1 AND ENFORCEMENT l

REGION IV j

Report No. 99900053/80-02 Program No. 51300 Anchor / Darling Valve Co.

701 First Street Williamsport, Pennsylvania 17701 Inspection Conducted:

-tober 27-30, 1980 k

V. H. Hunter, Inspector

/

'Yk80 Inspector:

Date ComponentsSection I Vendor Inspection Branch Other:

R. Kiessel, Headquarters Observer h

~

  1. M Approved by:
0. E. Whitesell, Chief Date ComponentsSection I Vendor Inspection Branch I

Summary l

l Inspection on October 27-30, 1980 (99900053/80-02)

Areas Inspected:

Implementation of 10 CFR 50, Appeadix 8 criteria and applicable codes and standards, including manufact' ring process control and reviewing corrective actions for reported deficiencies under 10 CFR 50.

The inspection involved twenty-eight (28) on site by one (1) inspector.

Results:

In the two (2) areas inspected there were no apparent deviations or unresolved items identified.

l l

02190 #

81 1

2 DETAILS SECTION A.

Principal Persons Contacted W. G. Knight, Technical Director

  • J. W. Marlatt, General Manager
  • G. W. Knieser, Quality Assurance Manager R. O. Husted, Manufacturing Superintendent J. D. Cartwright, Inspection Supervisor
  • Persons who attended the exit interview.

B.

Manufacturing Process,ontrol 1.

Inspection Objectives The objectives of this inspection were to verify that measures had been established and implemented to control the manufacturing process by the use of a shop traveler, or equivalent with space provided for reporting results of completion of specified operations and check points.

Also, to ascertain that procedures are established to main-tain identification of meterials during the manufacturing process.

2.

Insoection Objectives Accomplished by:

a.

Review of Section 12.4 of the ASME accepted QA Manual.

b.

Review of the following documents:

(1)

ES-4, standard for control of heat and/or serial numbers (2) MES-3, for distribution and control of engineering documents

~

(3) QAS-10, for gage control (4) ES-10, for shop order instructions (5) QAS-3, for preparation aro use of the inspection record.

c.

Review of fourteen (14) production release tickets (Shop Travelers).

d.

Observed liquid penetrant test of valve bonnets W. J. 870, 868, and 869 per LP Procedure MQCS-110.

e.

Observed seat and leak test of an 8" 150# swing check valve per procedure EPS-87.

1

3 3.

Inspection Findings Within the areas inspected there were no apparent deviations or un-resolved items identified.

C.

Follow-up of Reported Valve Deficiencies 1.

Reported Deficiency Background On June 17, 1980, Pennsylvania Light and Power (PPL) advised the NRC of a potential deficiency in four (4) valve yokes supplied by the Anchor / Darling Valve Co., in Williamsport Pennsylvania (ADV).

Potential deficiencies were described as cracks in the four (4) radii at the yoke mounting flange / yoke vertical section interface on valves in the RHR system of Unit No. 1.

On July 7, 1980, PPL further advised the Commission that after evaluation, it was determined that tne potential for concurrent failure of the referenced yokes in redundant, safety-related trains of the RHR system constitutes a failure mode whereby all RHR functions could be simultaneously lost.

2.

ADV Activity Background PPL, through Bechtel, advised ADV of the yoke cracking problem.

ADV field representative visited the site and returned with a cracked yoke for further evaluation.

As a result of physical and chemical analysis conducted on specimen removed from the cracked yoke, ADV determined that the cracking phenonomen was caused by the failure of the yoke material to meet the physical testing require-ments of A216-WCB material specification.

The referenced material specification required a tensile strength of 70 to 95 ksi while the investigative test results indicated a 45 ksi with corresponding results for elongation and reduction of area.

A review of ADV documentation files disclosed that the failed yoke castings had been purchased from a single source, the Malcolm Company, Inc. of 67 Polk Street, Newark, New Jersey.

The material was supplied to ADV along with " Certificates of Compliance" in accordance with purchase order requirements.

The certificates certified that the furnished material met all the requirements of material specification A216-WCB as specified by the ASME Code fo" non pressure boundry material.

When ADV attempted to centact the Malcolm Company, it was learned that the Malcolm Company had gone out of business and involved personnel could not be located.

ADV then assumed that a possible generic condition existed and further documentation research identified the following:

a.

The Malcolm Company, Inc. had supplied ADV with yoke castings of A216-WCB material for approximately ten (10) months during 1974 and 1975.

1

4 b.

During this ten (10) month time frame, ADV had supplied these yokes on valves assigned as follows:

(1) One hundred and fifty-four (154) to Bechtel for installation in the Susquehanna Units 1 and 2.

(2) One hundred and thirty eight (138) to the Commonwealth Edison Company for installation in LaSalle Units 1 and 2.

(3) Ten (10) to the Carolina Pcwer and Light Company for installation in Shearon-Harris Units 1 and 2.

(4) Eight (8) to Stone and Webster for installation in the Shoreham Unit.

3.

Current Status ADV has notified the affected organizations listed in paragraph 2 abcve of the potential defective material and has agreed to examine all referenced yokes.

The examination wili be performed by ADV field service personnel and will consist of hardness checks on the yokes.

Strength levels will be reviewed against yoke seismic analysis to verify adequate material strength.

Should any yokes be found unacceptable, ADV will replace them at no cost to the customer.

4.

Inspection Findings a.

It was verified that ADV had:

(1)

Identified the cause of the cracked yokes through physical tests.

(2)

Identified the source of the material and isolated it to a single source.

~

(3) Notified all applicable custorners of the potentially defective material.

(4) Negotiated an acceptable fix with the involved customers.

b.

As the Malcolm Company Inc. is no longer in business, the inspector nor ADV could ascertain whether this type of material was furnished to customers Other than ADV.

Consequently, the NRC staff has issued Bulletin No. 80-21 which requires all power reactor licensees or holders of construction permits to notify the commission if they have received any valve parts cast by the Malcolm Company,.Inc.

4 1

=

5 c.

As a result of ADV investigations, notification of affected customers, on going corrective actions, and NRC Bulletin No. 80-21 the inspector has no further questions relative to this matter.

D.

Ex't Interview The inspector met with management representatives at the conclusion of the inspection on October 30, 1980.

The inspector sunaarized the scope and findings identified during the inspection.

Management acknowledged the inspector's contents regarding the scope and findings as presented.

1 I

i o

.