ML19345E834
| ML19345E834 | |
| Person / Time | |
|---|---|
| Site: | Grand Gulf |
| Issue date: | 01/22/1981 |
| From: | Martore J Office of Nuclear Reactor Regulation |
| To: | Office of Nuclear Reactor Regulation |
| References | |
| NUDOCS 8102060233 | |
| Download: ML19345E834 (22) | |
Text
[pa %q[o, UNITED STATES NUCLEAR REGULATORY COMMISSION y
>w g
WASHINGTON, D. C. 20555
%,...../
JAN 2 2 1981 Docket Nos.:
50-416/417 APPLICANTS: Mississippi Power and Light Company Middle South Energy, Inc.
FACILITY:
Grand Gulf Nuclear Station, Units 1 and 2
SUBJECT:
SUMMARY
OF NOVEFBER 19-21, 1980 CASELOAD FORECAST PANEL PEETING AND SITE VISIT the caseload forecast panel met with representatives On November 19-21, 1980, of the applicant (Mississippi Power and Light Company; and Middle South Energy, Inc.), their architect-engineer (Bechtel Power Corporation), and their NSSS supplier (General Electric Company) to review the construction and preoperational testing progress at the Grand Gulf Nuclear Station (GGNS) Unit 1 and to evaluate the most likely fuel load date.
The previous caseload forecast panel visit in August 1979 (report 12, 1979)
The forecast panel's estimate was inficenced by estimate of November 1980.(1) the length of time required for preoperatior.a1 testing, concerns about:
(2) the probable adverse impact on the test schedule resulting from final electrical work, and (3) unforeseen delays which may develop in the construction work that still must be completed.
The panel met at the construction site on November 19, 1980, and was briefed In the on the plant's engineering and construction status during the morning.
af ternoon, the panel toured the plant and inspected the status of construction On the following day the panel continued its tour of l
and turnover activity.
the plant, and met again with the applicant to discuss several issues which I
An exit interview was held on November had been identified the previous day.
The meeting agenda at the applicant's offices in Jackson, Mississippi.
21, 1980 and attendees for the panel's site visit are listed in Enclosures 1 and 2, The handouts provided at the meetings are available from the l
respectively.
l project manager.
By way of introduction, the applicant reiterated the company's financial and 31, 1981, resource comitment to meet their predicted fuel load date of August although their recent preliminary startup testing milestone schedule indicated Mr. James P.
about 2-3 months of negative float in their predicted schedule.
McGaughy, Jr., MPal Assistant Vice President for Nuclear L
l changes recently adopted which should result in considerable progress in l
l controlling the construction and startup effort.
I 810 2 06.0 a.M h
'JAN 2 2 19g3 The status of plant design, procurement, manpower, construction, startup pre-operational test program, resolution of 50.55e items, and the impact of recent licensing requirements are discussed below.
Plant Design Plant design is being performed by Bechtel Power Corporation, at both their Gaithersburg, Maryland offices and at the plant site. Overall design and engineering on Unit I and common facilities required for Unit 1 operation are estimated to be 98% complete, with essentially only electrical work remaining.
However, these estimates do not reflect engineering required for outstanding issues such as ATWS, TMI requirements, the Power Generation Control Complex, or rework. The applicant indicated that engineering is proceeding on these outstanding items, and is not expected to impact their fuel load schedule.
Procurement Procurement of bulk quantities appears to be in good shape and is estimated now to be above 90% overall. Procurement of 273 of 313 major purchase orders is complete, with delivery of the remaining incomplete orders scheduled for the first hal f of 1981.
Manpower MP&L described the construction work force activities and indicated that manpower availability for completion of Uni.t 1 should not be a problem. The current work force of about 1700 represents the full complement needed to complete Unit 1 and is not expected to increase significantly in the future.
In addition, centracts with local unions, many of which expire in mid 1981, contain no-strike agreements.
Construction MP&L described construction progress since the last forecast panel (August 1979).
They indicated that the current work scope has expanded from that previously estimated, and that the current estimate of 86% complete reflects an 18% workoff (1.2% per month) since August 1979. In order to support an August 31, 1981 fuel load with construction at about 96% complete, an average workoff rate of 1% per month would have to be sustained for the remaining 10 months.
22 M As indicated in Enclosure 3, concrete work is 99% complete. Large pipe Cable hangers and small pipe hangers are 90% and 80% complete, respectively.
trays have been completely installed. Wire and cable is 87% complete, conduit The required quantities of conduit 87% complete, and connection 79% complete.
and cable pulling have been increased over previous estimates, thus necessitating a substantial level of effort to complete these items within the current schedule.
A comparison of Grand Gulf cable pulling experience in 1980 with those quantities required in 1981 to meet the scheduled August 1981 fuel load date is provided in Enclosure 3.
Status and Resolution of 50.55(e) Items MP&L discussed the design deficiencies that have been identified and reported to the NRC pursuant to 10 CFR 50.55(e), and stated that these are being resolved and are not expected to impact the construction schedule. They indicated that the number of potentially reportable deficiencies reflects MPAL's cooperation in reporting this information to NRC Region II, rather than excessive deficiencies at Grand Gulf. Potential problem areas identified include:
(1) ventilation ductwork; (2) fillet welds; (3) QA related to reactor controls design; and (4) Hilti anchor bolts.
In view of the length of time a number of these items have been outstanding, the panel expressed a concern regarding their resolution and workoff so as not to impact the fuel load schedule.
Effects of Recent Licensing Requirements MP&L fndicated that they are actively pursuing implementation of recent TMI requirements, and that all items are expected to be implemented in accordance In addition, they expect no fuel load impacts with the required NRC schedules.
with respect to ATWS or environmental qualification requirements.
Startup Preoperational Test Program The startup preoperational test program and milestones were outlined by the applicant. In contrast to their previous estimate of 18 months, they now consider a period of two years, from plant energization in May 1979 until Although this compares favorable May 1981, sufficient to accomplish this program.
with an industry average of about 24 months, this may be misleading due to The app 1tcant indicated that the limited number of system turnovers to date.
the average number of turnovers is projected to increase from about 3.2 per i
The actions taken by the month in 1980, to about 10-15 per month in 1981. (1) combining the component applicant to achieve this improvement include:
turnover and startup groups to improve coordination and flexibility; (2) the formation of a turnover package group to increase administrative efficiency and (3) establishment of daily critical items meetings, held on-site, to id ntify and oversee critical path items.
JAN 2 2 1981 4_
The panel considers the preoperational test schedule to be the major delaying item for plant fuel load. Our reasons are as follows:
- 1) Recent experience with other plants indicates an industry average of about 5-7 system turnovers per month, whereas MP&L projects a turnover rate higher than this. Even a doubling of their past turnover rate would place the applicant's fuel load at about July 1982;
- 2) The applicant stated that a preliminary review of their preoperational critical path schedule indicates a possible delay in fuel load of about 2-3 months; and
- 3) The completion of remaining electrical work is likely to interfere with and delay preoperational testing.
Conclusion The applicant has made significant progress in actual construction since the last caseload forecast panel meeting, and is implementing aggressive managerial techniques to expedite component and system turnovers and reduce the number of punch list items. The applicant stressed the company's comitment to meet its predicted August 1981 fuel load date, but indicated that recent delays in system turnovers could result in a slippage of between 2-3 months. However, the panel feels this prediction is overly optimistic. Based on the panel's experience with plant construction and preoperational testing, using the same techniques that have been used to estimate the fuel load date for all other i
domestic facilities, and considering the general rework currently in progress and the final electrical work remaining, the panel estimates a fuel load date of July 1982.
In making this estimate, the forecast panel noted that, although not factored into this conclusion, there are several issues which could pottotially result in additional delays to the fuel load date. These include:
1) resolution of suppression pool hydrodynamic loads questions; 2) resolution of TMI requirements and ATWS issues; l
3) resolution of environmental qualification of equipment; and
- 4) impact of the Pilti anchor bolt design deficiency and resolution of other design deficiencies that currently exist or may arise in the future.
i
SAN 2 2 1981 i The panel further concluded that the estimated fuel load date depends on aggressive construction and preoperational testing progress, and high quality work and system turnovers. The panel stressed the commitment of the NRC staff to complete its licensing review in a timely but thorough manner so as not to delay plant operation unnecessarily.
Joseph A. Martore, Project Manager Licensing Branch #3 Division of Licensing Enclosoures:
1.
Meeting Agenda 2.
Meeting Attendees 3.
MP&L Documentation 4
cc:
See next page.
i l
l t
fir. J. P. McGaughy Assistant Vice President - fiuclear Production Mississippi Power & Light Ccr:pany P. O. Box 1640 Jackson, Mississippi 39205 cc:
kobert B. McGehee, Esq.
Wise, Carter, Child, Steen & Caraway P. C. Box 651 Jackson, Mississippi 3920b Troy B. Conner, Jr., Esq.
Conner, hoore & Corber 1747 Pennsylvania Avenue, H. W.
Washington, D. C.
20006 Mr. Adrian Zaccaria, Project Engineer Grand Gulf Nuclear Station Bechtel Power Corp 9 ration Gaithersburg, Marylan6 20700 Mr. Alan G. Wagner, Resident inspector P. O. Bo' 469 Port Gibson, Mississippi 3915L Mr. N. L. Stampley, Sr. Vice President Engineering, Production & Construction P.O. Box 1640 4
Jackson, hississippi 39205 Mr. L. F. Dale Nuclear Project Manager P.O. Box 1640 l
Jackson, Mississippi 39205 Mr. John Richardson P. O. Box 1640 Jackson, Mississippi 35205 E
e P
cc: Robert b. McGehee, tsq.
Wise, Carter, Child, Steen & Coraway P. O. Box 651 Jackson, Mississippi 39205 Troy C. Ccnner, Jr., Esq.
Conner, Moore & Corber 1747 Pennsylvania Avenue, h. W.
Washington, D. C.
20U06 Mr. Adrian Zaccaria, Project Engirieer Grand Gulf NLelear Stati,n Bechtel Power Corporation Gaithersburg, Maryland 20760 Mr. Alan G. Wagner, Resicent Inspector P. O. Box 469
~
Port Gibson, hississippi 39150 Nr. N. L. Stampley, Sr. Vice Presicent Engineering, Production & Construction P.O. Cox 1640 Jackson, Mississippi 39205 br. L. F. Dale Nuclear Project Manager
~
P.O. Box 1640 Jackson, Mississippi 39205 Mr. Jchn Richardson P. O. Box 1640 i
Jackson, Mississippi 39205 l
John B. Mumford Suite 301 1919 Pennsylvania Ave., N.W.
Washington, D.C.
20006
. y.
4 i
MLEilflG !.UR'MRY lilSTRIBU'llut!
Ducket File G. Lear llP." l'UR S.Pawlickie[9 V. floonan
~
4 i
t.ocal PDR TIC /t; SIC / Tera V. llenaroyt
)
NRR Reading Z. Rosztoc.
V LB# 3 Reading W. Itaass % %, - e
- 11. Denton D. Muller 9 g/S
_ r N
g E. Case R. Ballard qA A
D. Eisenhut W. Regan R. Purple D. Ross f 'o
'y s
B. J. Youngblood P. Check t>
s a A. Schwencer R. Satterfield F. Miraglia
- 0. Parr J. Miller F. Rosa-G. Lainas W. Butler R. Vollmer W. Kreger J. P. Knight R. Ilouston R. Bosnak T. Murphy F. Schauer L. Rubenstein R. E. Jackson T. Speis Project Manager J. MARTORE W. Johnston Attorney, OELD J. Stolz J. Lee S. Hanauer 01E (3)
W. Cammill ACRS (16)
T. Murley R. Tedesco F. Schroeder D. Skovholt M. Ernst NRC Partici.nants:
R._liacr W. Lovelace C. Berlinger A. Wagner, Reg. II K. Kniel G. Knighton-A. Thadani D. Tondi i
J. Kramer D. Vassallo i
P._ Collins O. Ziemann bec: Applicant & Service List s*
I.
.e.
9 L_
ENCLOSURE 1 AGENDA NOVEMBER 19-20, 1980 GRAND GULF NUCLEAR STATION, UNIT 1 AND NEEDED FACILITIES 1.
Overview of project construction schedule including progress and ma;or milestonc, completed, since Caseload Panel visit of August 1979, current problems and any anticipated problem areas that may impact the current projected fuel load date.
2.
Detailed review and current status of design and engineering effort (by major discipline) including any potential problems that may arise from necessary rework.
3.
Detailed review and current status of procurement activities including valves, pipe, instruments, cable, major components, etc.
4.
Actual and proposed craf t work force (by major craft), craft availability, productivity, potential labor negotiations and problems.
5.
Detailed review and current status of all large and small bore pipe hangers, restraints, snabbers, etc., including design, rework, procurement, fabrication, delivery and installation.
6.
Detailed review of project schedule identifying critical path items, near critical items, amount of float for various activities, the current critical path to fuel loading, methods of implementation of corrective action for any activities with negative flest, and provisions for contingencies.
The estimated project percent complete as of October 31, 1980.
7.
Detailed review and current status of bulk quantities including current estimated quantities, quantities installed to date, quantities scheduled to date, current percent complete for each, actual versus forecast installation rates, and Dasis for figures.
(a) Concrete (CY)
(b) Process Pipe (LF)
Large Bore Pipe (21/2" and larger)
Small Bore Pipe (2" and smaller)
(c) Yard Pipe (LF)
(d) Large Bore Pipe Hangers, Restraints, Snubbers (ea)
-. (e) Small Bore Pipe Hangers, Restraints (ea)
(f) Cable Tray (LF)
(g) Total Conduit (LF)
(h) Total Exposed Metal Conduit (LF)
(i) Cable (LF)
- Power Control Security Instrumentation Plant Lighting (j) Terminations (ea)
Power Control Security Instrumentation Plant Lighting (k) Electrical Circuits (ea)
Power Control Security (1) Instrumentation (ea) 8.
Detailed review and current status of preparation of preop test procedures, integration of preep test activities with construction schedule, system turnover schedule, preop test schedule, current and proposed preop test program manpower.
(a) Total number of procedures required for fuel load.
(b) Number of draft procedures not started.
(c) Number of draft procedures being written.
(d) Number of procedures approved.
(e) Number of procedures in review.
(f) Total number of preop tests required for fuel-load.
(
Number of preop tests completed.
(g Number of preop tests currently in progress.
h (i
Number of systems turned over to start-up.
9.
Detailed discussion of potential schedular influence due to changes attributed to NUREG-0660, NUREG-0694 and other recent licensing requirementc.
- 10. Site tour and observation of construction activities.
- 11. Discussion of 50.55e items which raay have an impact on the construction completion schedule.
1 1
i t
ENCLOSURE 2 MEETING ATTENDEES GRAND GULF CASELOAD FORECASE PANEL MEETING NOVEMBER 19, 1980 NAME
_0RGANIZATION J. Martore NRC W. Lovelace NRC A. Wagner, Region II NRC M. Archdeacon Bechtel H. Brooks Bechtel L. Ruhland Bechtel A. Smith GE C. Gibbs MSEI T. Cloninger MP&L L. Dale MP&L C. Stuart MP&L G. Rogers MP&L J. McGaughy MF&L J. Richardson MP&L C. McCoy MP&L T. Reaves MP&L
3 ENCLOSURE 3 fMJOR MILESTC6ES NO 'CCGPLISRE.D
. C00EGSATEh=i'.MTER FLUSH - 4/18/20
, DRWELL SIT - 6/7/80
(. FPV ff/DRO - 11/28/80)
- CCfEB EER CO NECTICNS # 0 HYDRO
- PIPING AND INSTRIPE R CONNECTICNS TO RPV
- NSSS SYST 8 BUILD N O CCffENCED FLDSHING
- COPEiCED TMI MDDIFICATIC S
- PLACED 11)RBINE ON TUP.NING GEAR
- CGPLETED COOLING TOWER ShB.L
- APPROXIMATELY 70% OF TOTAL SYSTD1S SCCPE RELEASED TO TEST GPCUP FO C&P0fENT CHECKOUT -
I i
i I
l
4 i
f C::1 EL'CTICN PRCGESS #0 RRCENT CCiRETE i
s..-..
- su:uco uw
- co,.
j
- NOVEEER,1980
- 86%
- 18% IN 15 IC E S
- 1.2% R R BU4TH I
PLANT HRCE4T C0FRETE BY FUEL LOAD - AUGUST 31,1981-
+
- HISTORICALLY: 9 4 - 98%
--TO GO: 86% -4 %%
- 10% IN 10 IETHS-
- 1% PER IUiTH
' N 5
s i
i i
0'
?
?
e b
4 s
b
. ~..
ENGINEERING OVERALL STATUS -
ENGINEERING DISCIPLINE
% ENGINEERING 1.
Civil / STRUCTURAL EST. QUANTITY COMPLETE CONCRETE (YD.3) 235,000 100%
2.
F1ECHANICAL LARGE PIPE (FT.)
288,000 100%
LARGE PIPE HANGERS 12,150 100%
INSTRUMENTS 2,320
-99%
3.
ELECTRICAL CIRCutTS
~
29,840 97%
CABLE TRAY (FT.)
98,400 100%
CONDUIT (FT.)
583,000 98%
WIRE AND CABLE (FT.)
8,538,000 97%
CONNECTIONS 277,800 97%
ABOVE STATUS DOES NOT' INCLUDE ENGINEERING INVOLVED WITH TMI l
I
.e OJANT STMUS CL*RIENT ESTIMNIS DETAT.T m SCIEDULED
% CCNIEIE CDtODITY 235,000 Yd.
233,000 233,000 99%-
288,000 284,800 288,000 99%
Ccncrete 12.150 10,900 11,200 90%
Large Pipe Large Pipe IIangers 184,200 186,250 94%
Small Pipe 15,289 16,270
-80%
195,500 Snall Pipe Hangers 19,000 N/S 87%
2,300
.2,000 Instrunents 98,400 98,400
.100%.
Cablo Tray 520,600 520,000 87%
98,400 600,000 87%:
Ccoduit 7,447,644 7,617,500 Wira and Cable 8,600,000 Ccnnections 280,000 220,000 234,500 79%
=
4----'~-
I
- y.f e aia pus l
-(r b f. '~"'"c4.hd"lr j g i0,..glo O fno ll TO
/99 p oc o Lj to lo ?, obb -
3 80
/& /, oo'n 4 W
//9,coe
$ CO j 9 7, oco C 80 90, o co 7 to 67, co a F Fo 7'/,o..
4 to 9&,000 to t0
/ GSiva D P J A4fpa6 can d
, s a igio ios, u,o Tin O
lO3, 0& &
x 3,...
r aa z,-
5' to o,c o e l
.5l/ft l
y tooiooo l
ll.rf too,,aa 1
,.,oo.
fa0,ow hf Y 0*
p f
[
s s
-,-m-
Aftt. CTS OF ECBE LICENSING EQUIPEENTS E. ACTIVELY FtlRSUING IFFIBMATION CF EQUIPSETTS O 0694, 0696, 0654, AND 0737.
. f%J0R PROCURDER ITB1S F0ECAST COPETIQi 4/81
- POST ACCIDENT SNPE PN4ELS 4/81, HIGH RN4GE 6/81
- EFFLUBE MONITORIl4G 1/81
- RADIATION MONITORS 11/80 BUU( QUANTITIES F0ECAST 7 R
1,000 195,500
- SMALL PI E (E)
Lc0 19,000
- SPAll PIPE HANGEPS (Ea.)
100 2,320
- INSTRitENTS (Ea.)
260 30,000
- CIRCUITS (Ea.)
~
17,000~
~'600,000
- ETAU_IC CONDUIT (LF)'
62,000 8,600,000
- WIE AND CABE (W).
2,200 280,000~
- CONNECTIONS (Ea.)
ALL ITD1S EXPECED TO BE IPPlBMED IN A
. NUREG-0737 SCEDUE MJST BE EVALUATED.
4
/"
I s
a w
-r--
AFFECTS CF ECEiT LICBISING E0JIPHOTS AT.C GCiiS AGGRESSIVELY FURSuliE IiPLBETATICN OF ALT. 3A, PER NUEG-0460.
- BEGAN DESIGN JUNE 1980
- CCiPLETION SCHEDUE:
DESIGN
.12/82 If1 pie EITATION - 1/84
- BY FUEL LOAD:
RPT PROCEDUES NO FUEL LOAD IFPACTS.
ATWS RULE IffLBENTATION SCEDULE WILL CAUSE PROBLBi.
k I
e g
-g-res-
-w
-r6
- y y
=
1h, AFFECTS OF ECENT LICENSING EQUIPBUTS EINIR0ffENTAL QUALIFICATION PROGRAM TO CTFLY WITH f0EG-0588.
- EQUIPENT IN HOSTILE ENVIR0tFENT IDENTIFIED REVIEW OF COWLIANCE WITH QUALIFICATION EQUIRBUTS BY,L1/81 QUALIFICATION TO EET G88 IN ACCORDANCE WITH NRC SCHEDULE - 6/82 NO FUEL LOAD IWACT IDENTIFIED TO DATE.
j 1
l 1
7 r
8
*g
, er.
~
y
i 1
4 i -
T STATUS OF COMPONENT IESTING i
l ELECTRICAL CHECK OUT 55%
COMPLETE l
MECHANICAL CHECK OUT 55%
COMPLETE 3
I & C CALIBRATION 507.
COMPLETE i
FLUSHING 70%
COMPLETE 1-TOTAL 60%
-s i
h l
l~
i f
E
't i
{.
h, i.
W,,,_
--*~a+---.
..._......--.,,/.-r.-,...-....
...-..,,....,..,,,,,..,.,......,;,-..,.~.--_e.._,
-__,_..v..-,
, y,,
n
Page 9 IIRENOCAti OP RlUFASIS MU 'IUIUOVERS - 1980
~
,1 -
L Jan Peb
. Mar Apr May Jun Jul Aug Sep ~
Oct
'll.L e l St or t 8; :,
i.
Releases
'3-3 10 9.:
10 12 13 14 6
8 hl
}.
Sdeduled 2
5 10 11 18 13 16 20 12 13 1:to
[
Turnovers.
0-0 4
10 4
3 1
4 0
6 32K 51 Sdeduled 0
-4 5
12 11 7
'12 14 6
15 11 i
+
j%
y9,:.a
,,/
i p
TURNOVERS TO 11P&L S/U 150..
PRESENT FORECAST VERSUS 190 140 _
SCilEDULED 180 -
130 170 -
O ' * ) '
N 120 _
T70 '>
t' 160 -
110 -
150 -
100 -
140 -
90 -
130 -
80 -
120 -
70.
110 -
60 100 -
50 -
90 -
40 _
.30 Short 51 T/v')
20 -
b.. m t e.4 c<. y u t,e Lt-10 -
I79) 0-Total of 42 turnovers (18 NOV 89) ( 74 i.. I to
.a. ws p l < l.
.s 4
18 36 52 -
63 773 80
- 99 109-119j 127 132 CL?tULATIVE
~
[.
14-18 16 11 14 12 '
10 10 10 '
8 5
110NTill.Y
,o I
i i
i i
i i
i s
i i
i
,OCT NOV DEC JAN FEB ttAR APR MAY JUN JUL AUG SEP OCT NOV D
1980 1981