. s Y
o I
Metropolitan Edison Company
/
kI y
g j Post Office Box 480 Middletown, Pennsylvania 17057 Wnter's Direct Dial Numoer November 25, 1980 TLL 590 TMI Program Office Attn:
Mr. John T. Collins, Deputy Director U. S. Nuclear Regulatory Commission c/o Three Mile Island Nucleat Station Middletown, Pennsylvania 17057
Dear Sir:
Three Mile Island Nuclear Station, Unit 2 (TMI-2)
Operating License No. DPR-73 Docket No. 50-320 NRC Proj ect Approval In accordance with discussions that we have had with members of your staff, we intend to obtain your approval of IMI-2 recovery projects in a two-step process. First, we will submit the design criteria for your comments and approval.
Secondly, we will later submit the Technical Evaluation Report (TER) for your approval.
Design Criteria documents establish the design objectives for the f acility and/or system to be constructed. Among the design objectives are the regulatory criteria that must be met to provide us assurance that the public health and safety will not be compromised. We will request your approval for our Design Criteria. That approval receipt will provide us assurance that the criteria used as the basis for recovery facilities and/or systems design ic acceptable to regulatory authorities. Furthermore, receipt of your approval will enable us to proceed with detailed engineering with reasonable assurance that, if it is withia the bounds of the criteria, it will meet your requirements.
The Technical Evaluation Report serves as the document that provides a com-prehensive public health and safety analysis of the recovery facility and/or system. The TER provides information to serve as the basis for our analysis as well as the results of our analysis to enable NRC review and approval to place the facility and/or system into operation. This document serves as the principle document to provide our safety analysis and environmental assess-ment, as well as the basis for our internal 10 CFR 30.59 evaluation. The TER will conform to the requirements specified in the GPU Licensing Plan for Recovery Operations, soon to be issued.
The procedural interf ace described above is in accordance with the practices that we have followed in the past. We believe that, because the interface O/
method is effective, it should be continued. This letter documents that interface.
S
/0 8 OJ 2 0 5 0 3 6 5 "*"" " '** " ' "*""' ' *" ""* ~ ' " ** """"
s John T. Collins TLL 590 We would be pleased to discuss this matter with you further, if required, at your convenience.
Sincerely, f
.M(
f.
- 3 V
~
G. K. Hovey Vice-President and Director, UtI-2 GKH:LJL: dad cc: Bernard J. Snyder