Forwards Revised Guard Training Plan & Response to NRC 800826 Comments Re Plan.Plan & Response Withheld (Ref 10CFR2.790)
ML19345B644
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 11/24/1980
From: Crouse R
TOLEDO EDISON CO.
To: Reid R
Office of Nuclear Reactor Regulation
References
666, NUDOCS 8012020270
Download: ML19345B644 (1)


Text

TOLEDO

%mm EDISON Docket No.

50-346 Pc-:.ac p C=c se License No.

NPF-3 CYi'"

v r aa sw Serial No. 666 Novembet 24, 1980 Mr. Robert W.

Reid, Chief Operating Reactors Branch f/4 Division of Licensing U. S. Nuclear Regulatory Commission Washin gton, D.C.

20555

Dear Mr. Reid:

Enclosed is the response to the comments listed in your letter of August 26, 1980, on the Davis-Besse Guard Training Plan for the Davis-Besse Nuclear Power Station Unit No. 1.

The enclosure fully resolves each comment.

Five copies of the revised Davis-Besse Guard Training Plan are also enclosed.

Application is made to withhold the enclosed information from public disclosure pursuant to 10 CFR 2.790(d).

Sincerely, ff,A" RPC:MRP:jms Enclosures (5) cc:

NRC Davis-Besse Resident Inspector w/o s

F 80J2020 MD Enclosure Contains 10 CFR 2.790(d) Information THE TCLECO ECISON CCMPANY ECISCN PLAZA 300 MADISCN AVENUE TCLECO CHIO 43652