Second Interim Deficiency Rept Re Structural Steel Framing for Control Bldg.Deficiency Considered Reportable Under 10CFR21.Rework of Fillet Weld Has Been Performed by Vendor. Next Rept Will Be Submitted by 801106
ML19344D972
Person / Time
Site: Yellow Creek  Tennessee Valley Authority icon.png
Issue date: 08/15/1980
From: Mills L
TENNESSEE VALLEY AUTHORITY
To:
References
REF-PT21-80-248-001 10CFR-050.55E, 10CFR-50.55E, NCR-YC-069, NUDOCS 8008260452
Download: ML19344D972 (1)


Text

  1. ),Y' U  !

~

$~0 - SM TENNESSEE VALLEY AUTHORITY CH ATTANOOGA, TENNESSEE 374ot 400 Chestnut Street Tower II August 15, 1980 Mr. Jame P. O'Reilly, Director Office of spection and Enforcement U.S. Nuclea egulatory Com:nission Region II - SL te 3100 101 Marietta St et Atlanta, Georgia 0303 l

Dear Mr. O'Reilly:

YELLOW CREEK NUCLEAR PLANT UNITS h AND 2 - STRUCTURAL STEEL FRAMING FOR CONTROL BUILDINO - NCR YC-063 - SECOND INTERIM REPORT The suoject defic'.ency was initially reported to NRCrOIE Inspector R. W.

Wright on June 1*,, 1980, in tocordance with 10 CFR 50(e). An interim report was subattted ora July 9,1980.

Wo expect to sub=it cur next report by November 6,1980. We consider 10 CFR 21 applicable to this deficiency. TVA and vendor representatives have met, and rework of fillet weld has been performed by vendor representatives at the TVA Yellow Creek Nuclear Plant site.

If you have any questions concerning this matter, please get in touch with D. L. Lambert at FIS 857-2581.

Very truly yours, TENNESSEE VALLEY AITTHORITY l

L. M. Mills, Manager Nuclear Regulation and Safety cc: Mr.VictorStello,Jr., Director /

l\ Office of Inspection and Enforcement U.S. Nuclear Regulatory Consnission Washington, DC 20555 l

l psd/1 6io An Equal Opportunity Employer go osc6 0 4 52