i QJ PHILADELPHIA ELECTRIC COMPANY 2301 MARKET STREET P.O. DOX 8699 PHILADELPHI A. PA.19101 EDWARD G. BAUE3, JR.
ND G NE L
UNsEL l215) 841 4000 EUGENE J. BRADLEY Assoca Art oENEnAL coWNsEL DONALD BLANKEN ICKIRKdE"'"'
Oc tober 16, 1980
' "^
T. H. M AHER CORNELL AssesTANT GEN RAL COUNSEL EDWARD J. COLLEN. JR.
JOHN F. KENNEDY. JR.
l ass 3sTANT COUNSEL 1
l Mr. Robert W. Reid, Chief Operating Reactor Branch #4 Division of Licensing United States Nuclear Regulatory Commission Washington, D. C.
20555 Re:
Peach Bottom Atomic Power Station Units 2 and 3 l
Docket Nos. 50-277 and 50-278 l
License Amendment Application APRM Rod Block and Scram Curves
Dear Mr. Reid:
f I
L Our Application for Amendment of Facility Operating l
Licenses DPR-44 and DPR-56 filed on June 17, 1975, as l
supplemented by letter dated February 25, 1977, requested l
changes to the Peach Bottom Technical Specifications which would revise the APRM rod block and scram trip setting l
equations.
These changer were requested to permit greater flexibility for withdraw.1 of control rods at reduced core
(
flow conditions and theraby reduce reactor startup time.
l Reactor core design improvements have been implemented l
at each of the most. recent Unit 2 and 3 refueling outages.
l
- These improvements are providing the desired control rod with-drawal flexibility, therefore the referenced license amendment request is not needed at this time.
Therefore, we withdraw l
the referenced license amendment request for revision of the APRM rod block and scram trip setting equations.
Very truly yours, k
-e 80102103R7 Eugene J. Bradley
-EJBimk
.