Forwards NRC Masonry Consultant J Colville Rept Re Resolution of Control Bldg Wall Problem.J Colville to BNL Encl
ML19344A405
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 08/14/1980
From: Gray J
NRC OFFICE OF THE EXECUTIVE LEGAL DIRECTOR (OELD)
To: Mccollom K, Mark Miller, Paxton H
Atomic Safety and Licensing Board Panel
Shared Package
ML19344A406 List:
References
NUDOCS 8008200202
Download: ML19344A405 (2)


Text

s ii fa arco f

q'o UNITED STATES y"

NUCLEAR REGULATORY COMMISSION o

{

,g WASHINGTON, D. C. 20555

/

August 14,1980 i

Marshall E. Miller, Esq.. Chairman Dr. Kenneth A. McCollom, Dean Atomic Safety and Licensing Board Division of Engineering U.S. Nuclear Regulatory Commission Architecture & Technology Washington, DC 20555 Oklahoma State University Stillwater, OK 74074 Dr. Hugh C. Paxton 1229 41st Street f

Los Alamos, NM 87544 1

In the Matter of Portland General Electric Company, et al.

(Trojan Nuclear Plant)

Docket No. 50-344 (Control Building)

T Gentlemen:

Enclosed is the final report of Dr. James Colville, the NRC Staff's masonry consultant, with regard to resolution of the " wall problem" at the Trojan Nuclear Plant. The report, in sinmary, indicates Dr. Coleville's agreement with the criteria leading to resolution of the " wall problem" in the areas of review in which he was involved.

Since Dr. Coleville pre-sented evidence on the " wall problem" at the hearings in the referenced proceeding held in April 1980 and since the " wall problem" was the subject of Board findings in the Initial Decision of July 11,1980, this final report is being forwarded to you for your information.

Sincerely, sep R. Gra Counsel for NRC Staff

Enclosure:

Report on Criteria and Methodology for the Evaluation of Out-of-Plane Loading on Masonry Walls at the Trojan Power Plant, July 1980 I

cc w/ enclosure:

Service List 8008200 M 1 g

J

.l UNIVERSITY OF MARYLAND COLLEGE PAnn 20742 EEFARTMENT OF CWIL ENGINEERING COLLEGE OF ENGINEERING 43058 454 3430 July 17,1980 Mr. Anthony Romano Building 13 Brookhaven National Laboratory Upton, N.Y. 11973

Dear Mr. Romano:

Enclosed is my final report on the concrete masonry walls at the Trojan Nuclear Power Plant. Also enclosed is a copy of a letter, dated June 28, 1980 from Mr. Donald J. Broehl of PGE to Mr. Engelken, Regional Director of hPC along with associated relative criteria referred to in Mr. Broehl's letter.

I believe that my involvement in the masonry wall problem at the Trojan Plant is completed and I am, therefore, also enclosing my final statement of fee plus a travel reimbursement request for my recent trip to Portland and San Francisco to assist NRC Staff in their discussions concerning appropriate design criteria.

SinpeY,ely, l