ML19343C332

From kanterella
Jump to navigation Jump to search
Responds to IE Bulletin 78-01, Flammable Contact-Arm Retainers in GE CR120A Relays. Util Found 290 GE CR120A Relays Containing Celcon contact-arm Retainers.Celcon Retainers to Be Replaced at Next Outage
ML19343C332
Person / Time
Site: Millstone Dominion icon.png
Issue date: 02/23/1978
From: Switzer D
NORTHEAST NUCLEAR ENERGY CO.
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
IEB-78-01, IEB-78-1, NUDOCS 8103090515
Download: ML19343C332 (1)


Text

.-----:.

- - ~

~

NNE?CO 2.gfg.,,m,..

NORTHEAST NUCLEAR ENERGY COMPANY 2m&

A NORTMEAST UTILITIES COUDANY February 23, 1978 Docket No. 50-245 Mr. Boyce H. Grier Director, Region I Office of Inspection and Enforcement U. S. Nuclear Regulatory Comission 631 Park Avenue King of Prussia, PA 19406

Dear Mr. Grier:

Subject:

IE Bulletin 78-01 This is in response to IE Bulletin No. 78-01 concerning Flammable Contact-Am Retainers in General Electric CR120A Relays.

There are approximately 290 GE CR120A relays either installed or in spares inventory in Millstone Unit 1, of which approximately 75 are installed in safety-related equipment. The balance are used in non-safety-related equipment for general alam purposes and are located in areas separate from safety-related equipment.

~ In an attempt to detemine the date of manufacture of the relays difficulty was experienced due to the location of the manufacturer's date code, therefore, it will be assumed that all CR120A relays within Millstone Unit 1 contain the Celcon contact-am retainers.

Development cf a procedure and replacement of the Celcon retainers will be completed at the next outage of at least two weeks duration following availability of the replacement retainers from General Electric.

Based on anticipated material delivery dates, it is estimated that replacement will be completed by April 30, 1978.

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY n

l f)

N. t

,J-D. C. Switzer J President DCS:RWW/kwe cc:

Director, Office of. Inspection I

and Enforcement

'f '

Divisi_on of Reactor Operations Inspection Washington, DC 20555 fC().

cea m t <=as bAb bOO ONNEOTIOUT C NORTHEAST NUCLEAR ENERGY COMPANY A NORTHEAST UTILITIES COMPANY February 23, 1978 Docket No. 50-245 Mr. Boyce H. Grier Director, Region I Office of Inspection and Enforcement U. S. Nuclear Regulatory Comission 631 Park Avenue King of Prussia, PA 19406

Dear Mr. Grier:

Subject:

IE Bulletin 78-01 This is in response to IE Bulletin No. 78-01 concerning Flammable Contact-Am Retainers in General Electric CR120A Relays.

There are approximately 290 GE CR120A relays either installed or in spares inventory in Millstone Unit 1, of which approximately 75 are installed in safety-related equipment. The balance are used in non-safety-related equipment for general alam purposes and are located in areas separate from safety-related equipment.

In an attempt to determine the date of manufacture of the relays, difficulty was experienced due to the location of the manufacturer's date code, therefore, it will be assumed that all CR12'A relays within Millstone Unit I contain the Celcon contact-arm retaincrs.

Development of a procedure and replacement of the Celcon retainers will be completed at the next outage of at least two weeks duration following availability of the replacement retainers from General Electric.

Based on anticipated material delivery dates, it is estimated that replacement will be completed by April 30, 1978.

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY lo

-f/p%Cg/[

D. C. Switze President DCS:RWW/kwe cc:

Director, Office of Inspection and Enforcement

/

t I

' Division ~of-Reactor Operations Inspection Washington, DC 20555-

,