ML19343B979

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Jan 1981
ML19343B979
Person / Time
Site: Pilgrim
Issue date: 02/11/1981
From: Whitney G
BOSTON EDISON CO.
To:
Shared Package
ML19343B976 List:
References
NUDOCS 8102180415
Download: ML19343B979 (6)


Text

REFUELING INFORMATION The following refueling information is included in the Ebnthly Report as requested in a letter to Mr. G. C. Andognini dated January 18, 1978:

For your convenience, the information supplied has been enumerated so that each number corresponds to equivalent notation utilized in the request.

1. The name of this facility is Pilgrim Nuclear Power Station, Docket Number 50-293.
2. Scheduled date for next Refueling Shutdown: September, 1981
3. Scheduled date for restart following refueling:

4.

5. Due to their similarity, requests 4, 5, & 6 are responded to collectively:
6. The fuel, which had been loaded /.uring the 1980 scheduled refueling outage, is of the new P8x8R der,1gn, consisting of approximately 64 P8DR3282 assemblies and 120 PSDR3265 assemblies.
7. (a) There are 580 fuel assemblies in the core. ,

(b) There are 764 fuel assemblies in the spent fuel pool.

8. (a) The station is presently licensed to store 2320 spent fuel assemblies.

The actual spent fuel storage capacity is 1770 fuel assemblies at present.

- (b) The planned spent fuel storage capacity is 2320 fuel assemblies.

9. With present spent fuel in storage, the spent fuel pool now has the

' capacity to acco=modate an additional 1006 fuel assemblies.

i 8102180$6

, , , . . - - - - , ~ ~ ..w. - ~ ,. , - . . . ,- , ,,,..m., , . , , , - ,--,----,s --

OPERATING DATA REPORT DOCKET NO. 50-29 3 DATE 2/11/81 COMPLETED BY C- G. Whitney TELEPHONE 617-746-7900 OPERATING STATUS Pilgri:n I Notes

1. Unit Name:
2. Reporting Period: Januarv. 1981 1998.
3. Licensed Thermal Power (MWt):
4. Nameplate Rating (Gross MWe): 678.
5. Design Electrical Rating (Net MWef: 655.
6. Maximum Dependable Capacity (Gross MWe): 690.
7. Maximum Dependable Capacity (Net MWe): 670.

S. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:

None

9. Power Level To Which Restricted,if Any (Net MWe): None
10. Reasons For Restrictions.If Any:

N/A This Month Yr. to-Date Cumulative i1. Hours In Reporting Period 744.0 744.0 71424.0

12. Number Of Hours ReactorWas Critical 726.I 726.1 50010.7 0.0 0.0 O.0
13. Reactor Reserve Shutdown Hours
14. Hours Generator On-Line 716 . 3 716.3 49223.2 0.0 0.0 0.0
15. Unit Reserve Shutdown Hours
16. Gross Thermal Energy Generated (MWH) 1296936.0 1296936.0 83586312.0 .
17. Gross Electrical Energy Generated (MWH) 444410.0 _ _ .

444410.0 27773774.0

[

18. Net Electrical Energy Generated (MWH) 427360.0 427360.0 26677967.0 l 68.9
19. Unit Service Factor 96.3 96.3 l 96.3 96.3 68.9 l 20. Unit Availability Factor ,
21. Unit Capacity Factor (Using MDC Net) 85.7 85.7 55.7 87*7 07*7 57'O
22. Unit Capacity Factor (Using DER Net)
23. Unit Forced Outage Rate 3.7 3.7 10.4
24. Shutdowns Scheduled Over Next 6 Months (Type. Date.and Duration of Each):

l l None

25. If Shur Down At End Of Report Period. Estimated Date of Startop: Unit Operatine

! 26. Units in Test Status (Prior to Commercial Operation): Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION (0/77) l t

I.-. . . _ _ _ - , _ , . _ _ . . _ _ , . - - . . _ . _ _ . .

_ , . . _ , . - _ . . . . . , _ , , , , , , _ . . , _ , . _ , _ . - . . _ , ..._,_,_m. , . . , _ _ ,__. , , _ , _ . _

AVERAGE D A!LY UNIT POWER LEVEL DCCKET NO. 50-293 UNIT Pilerim I DATE 2/II/81 COMPLETED BY C' C* M '"*Y TELEPHONE 617-746-7900 January, 1981 MONTH DAY AVERACE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LD'IL (MWe-Net) (MWe-Net) 671 g. 663 g

671 13 421 2

610 19 150 3

'o' 20 191 4

y 654 21 518 646 ,; 587 .

6

- 669 ,3 661 670 24 573 3

669 25 666 9

669 26 664 10

j 670 7 665 671 ,3 316 12 l

666 ,9 10 3 g3 668 361 14 - 30 668 3j 453 15 16 668 INSTAUCTIONS -

On this format.!ist :he average d25y unit power levelin MWe Net for each day in the reperting month. Campute to the nearest whole me;2 wart.

. (o/77)

- *- m, , , , - - , , , - --~y- , - y ,- -- , .. r-, , - , , - , , ,. - , - - , - - , , - , . - . - - , - , , - . . , , , .-,.% - , ,

IH)CK E I NO. 50-293 tlNil SilUIDOWNS ANI) POWFR REDUCIIONS Pilgrim I UNII NAME DAIE 2/11/81 COMPI.E1 Ell fly C- C- Whitney.

RFPOR I MONIII January, 1981 617-746-7900 1 EI.T PIIONE O c g 5g h 1.icensee E*, c-8.g raisse & rotactlive No. Date g 3g @ } q$5h Event g7 1 Attion to H

$6 $ 5MC Report 11 uiU hU U

Present Reciertence O

{

I 1/4/81 S 0.0 B 1 N/A CB CENERA Repair of brushes on A & B reactor recirculation motor-generator sets.

2 1/18/81 S 0.0 B 1 N/a llB llTEXCil Bypass of "B" I,ow pressure heater train and repair of I-2 water box tailpipe.

3 1/28/81 F 27.7 B 4 N/A IIA INSTRU Reactor scram due to inadvertant high water trip during surveillance test.

4 1/29/11 F 0.0 11 1 N/A IIB llTEXCll "B" high and low pressure heater trains have been isolated limiting power to 75%.

I 2 3 4 F: forced Reason: Mettual: Exhibit G Instinctions S: Scheduled A-Ljuipment Failure (Explain) 1 -Manual for Preparation oI Data D-Maintenar,ce of Test 2 Manual Scram. Eintsy Sheets for 1.icensee C. Refueling 3 Aulomatic Scrarn. Event Repor (1.1-'R) File (NilRI G-D-Regulaimy Restriction 4-Other (Enplain) 0161)

E-Operator Training & l.icense I xamination

- F-Administrative 5 G Operational I:rror (Explain) 1:shibit I - Same Source 19/77) ll Other (Explain)

PILGRIM NUCLLAR l'O'.JER STATION thulli JANUARY 1981 EUOR SAFETY RELATED MAIN 1dNANCE CORRECTIVE ACTION MALFUNCTION CAUSE  !!AINTENANCE TO PREVENT RECURRENCE ASSOCIATED L.

iYSTDI COMPONENT 10 "B" RIIR lleat Exch llead Gasket Leak Furmanited Furmanite is Permanent 9 Head Flange 11 SBLC Pump Leak Rgplaced Head Casket

, 27 1-2 Water Box Pipe Leaking Made Temporary Investigate / Planning 4 Repairs 29 "E" SSWP Check Valve Leak- Replaced Disc ing 27 "D" Screen Bearing Worn Replaced Bear- '

ing 18 "B" Cond. Pump High Vibration Replaced Motor Bearings h

O I h

f

-

  • BOSTON EDISON COMPANY PILGRIM NUCLEAR POWER STATION Summary of Operations for Januarv , 1981 The month of January began with the unit operating at 100% reactor power. The unit operated at 100% thru January 4th when a unit reduction to 50% power was conducted to repair brushes on A & B reactor recircula-tion motor-generator sets and other minor maintenance. The unit was returned to 100% power and operated at this level until January 18th.

On January 18th the unit power was reduced to 50% power to back-wash the main condenser and bypass the "B" Low Pressure Heater Train.

During this power reduction, a 3b" crack was identified in the 1-2 waterbox (Main Condenser) outlet piping. Power increase was commenced and unit returned to 80% on January 19th.

Problems with control of level in the "B" Low Pressure Heater Train limited reactor power to 80% until January 22nd. On January 23rd, feedwater heaters were returned to service and unit power reached 100%

on January 23rd. Shortly af ter reaching 100%, increased leakage in the 1-2 outlet piping necessitated a power reduction to 55% to remove the waterbox.

Power was increased to 100% on January 24th and continued to operate at this power until 1125 hours0.013 days <br />0.313 hours <br />0.00186 weeks <br />4.280625e-4 months <br /> on January 28th. At this time, the reactor scrammd due to surveillance testing of Reactor High Water Trip. The unit war; started up and synchronized to the grid @l506 hours on January 29th. Power was increased to 75% and limit'ed to that power for the remainder of the month because "B" Low and High Pressure Heater Trains were isolated.

l l

l

\

i l

l r 7-l l

l r