Forwards Facility Estimate of Cost of Replacement Energy & Capital Expense Incurred Due to Licensing Delays,Per 810325 Ltr.Encl Table Reiterates NRC & Util Estimate Based on Projected Cost of Oil in 1983
ML19341D688
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 03/31/1981
From: Novarro J
LONG ISLAND LIGHTING CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
SNRC-552, NUDOCS 8104080424
Download: ML19341D688 (2)


Text

.,

LONG ISLAND LIGHTING COM PANY 7%sassagg FLC'O SHOREHAM NUCLEAR POWER STATION P.O. BOX 618, NORTH COUNTRY RO AD

  • WADING RIVER, N.Y.11791 SNRC-552 March 31, 1981 J

Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555 SHOREHAM NUCLEAR POWER STATION - UNIT 1 Docket No. 50-322

Dear Mr. Denton:

As requested by letter dated March 25, 1981 from Mr. Robert L. Tedesco, Division of Licensing, NRC to Mr. M. S. Pollock, Vice President - Nuclear, Long Island Lighting Company, enclosed herewith is the Shoreham estimate of the cost of replacement energy and capital expense incurred due to Licensing delays. Please note that the table includes a reiteration of the NRC's estimate of the cost of delay as well as LILCO's estimated cost which is based on the projected cost of oil in the year 1983. This information was provided verbally on March 27, 1981.

Very truly yours, J. P. Novarro j

Project Manager shoreham Nuclear Power Station Of CC:mc 5 Enclosure cc: J. Higgins

//

81040 8 0 %M A

~

s n?

COST OF REPLACEMENT ENERGY ' AND CAPITAL EXPENSE INCURRED DUE TO LICENSING DEIAYS (ALL COST ESTIMATES ARE IN CURRENT DOLLARS)

COST OF -REPLACEMENT ENERGY CAPITAL EXPENSE

. Capital Average Esti- Total Replace- Estimated Expense Cost of- Incro- mated Replace- ment Capital Delay Capital Replace- . Nuclear mental Length ment Energy Cost- During Expense REPLACEMENT FUEL ment Fuel Fuel of Energy Cost Per of Unit at Delay Per

' MIX % _ Fuel Cost Cost Delay Cost Month Completion Period Month UNIT MWe COAL OIL GAS Mills /kWh Mills /kWh Mills /kWh Mo:iths $1 x 10 $1 x 10 $1 x 10 $1 x 10 Shoreham 1 820 100 41.3 10.0 31.3 1 11.2 11.2 2210 18.4 18.4

.(NRC)

Shoreham- l' 820 100 74.7 8.7 66.0 1 23.5 23.5 2210 20. 20.

(LILCO) 4

--