[.fN Commonwrith Edison one First National Plaza. Chicago, lihnois i Address Reply to: Post Othee Box 767 Chicaga, Illinois 60690 j
February 11, 1981
%I c>y m
(
Mr. James G. Keppler, Director 9 Q)
Enforcement - Region III
{
y/g /([ [g k
Directorate of Inspection and 44 g
U.S. Nuclear Regulatory Commission 4
/
799 Roosevelt Road Glen Ellyn, IL 60137 4
f N
Subject:
Byron Station Units 1 and 2 Braidwood Station Units 1 and 2 Response to IE Bulletin 80-23
" Failures of Solenoid valves Manufactured by Valcor Engineering Corporation" NRC Docket Nos. 50-454/455 and 50-456/457 References (a):
J. G. Keppler letter'to C. Reed dated November 14, 1980 (b):
T.
J. Rausch letter to J. G. Keppler dated December 29, 1981-
Dear Mr. Keppler:
The Commonwealth Edison Company review conducted in accordance with the subject bulletin disclosed that eight (8) of the i
suspect valcor Engineering Corporation solenoid valves have been supplied as solenoid operators on Anchor / Darling valves at Byron and Braidwood Stations (4 per station).
These solenoid valves are not i
subjected to high temperatures, therefore we do not expect to encounter the problem described in the bulletin.
It is our intent-to replace the coils in these solenoids-with new coils supplied by valcor.
Replacement will be completed
~
l prior to-commencing operation (the current schedule is to have-replacement completed by April 16,-1981).
I Approximately 18 man-hours were e'xpended in conduct of the l
review and preparation of this report.
The manpower required to j
replace the coils is estimated to be a total of 20 man-hours.
i 3108026 i
FEB 12 93I
r
. Please address any questions you may have concerning this matter to this office.
Very truly yours, hhwf
%4 Thomas J. Rausch Nuclear Licensing Administrator Special Projects cc:
Director, Division of Reactor Operations Inspection Washington, DC 20555 0542A