Responds to NRC 801208 Ltr Re Violations Noted in IE Insp Repts 50-546/80-28 & 50-547/80-28.Corrective Actions:Calibr Gauges Installed on Equipment & Indicator Gauges Verified Against Calibr Gauge
ML19341B194
Person / Time
Site: Marble Hill
Issue date: 12/30/1980
From: Shields S
PSI ENERGY, INC. A/K/A PUBLIC SERVICE CO. OF INDIANA
To: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19341B190 List:
References
NUDOCS 8101300421
Download: ML19341B194 (3)


Text

-

7 PUBLIC SERVICE INDIANA December 30, 1980 S. W. Shields Sensor Vem Presdent -

Nucler Drwision Mr. Caston Fiorelli United States Nuclear Docket No's: STN50-546 Regulatory Commission Region III STN50-547 799 Roosevelt Road Construction Permit Nos: CPPR-170 Glen Ellyn, Illinois 60137 CPPR-171 SUE.) CT: Marble Hill Nuclear Generating Station Units 1 and 2

REFERENCE:

Letters from PSI to NRC Region III dated September 24, 1980 and November 7, 1980, amended response to Item of Noncompliance 80-28-01

Dear Mr. Fiorelli:

Below is the corrective action taken to resolve Item of Noncompliance 80-28-01.

Corrective Action Taken and Results Achieved Corrective Action Request Number PC-0490 was initiated on July 9, 1980 to document that, contrary to the requirements of ANSI N45.2 Section 13 which l states in part " measures to ensure that tools, gauges, instruments and other inspection, measuring and testing equipment and devices used in activities af fecting quality are of proper range, type and accuracy to verify conformance to established requirements", had not been instituted, in that no program for monitoring of purge pressure gauges on items requiring inert gas blankets existed.

1. Calibrated gauges shall be installed on equipment as required by the Storage and Maintenance Instructions.

l l

Note: Storage and Maintenance Instructions are prepared and/or l

approved by PSI for implementation by site contractors.

2. For Storage and Maintenance Instructions specifying purge limits only, calibrated gauges are not required. The indicator gauges must, however, I

be verified against a calibrated gauge at least every six months.

l DEC 31200 1

i P.O. Box 190, New Washington, Indiana 47162 812. 293.4441 8101300 N 7

s t

\ I PUBUC SERVICE WE>tANA Mr. Fiorelli December 30, 1980

3. If removal of the indicator gauge would result in loss of purge and have possible detrimental ef fect on the equipment, verification against a calibrated gauge is not required, however, written approval is necessary from PSI.

Corrective Action Taken To Prevent Recurrence Project Management Procedure (PMP) 6.03 was revised to require the following:

1. I f the eq uipment arrives with a nitrogen purge, assure pressure gauges are installed and a positive purge pressure is maintained in accordance with the applicable Storage and Maintenance Instruction.

Check daily for the first five working days in accordance with applicable Storage and Maintenance Instructions thereafter.

2. Cauges shall be installed on equipment in accordance with the applicable Storage and Maintenance Instruction. Where calibrated gauges are not required, the gauges shall be verified against a calibrated gauge upon receipt of the equipment and, as a minimum, check every six months thereafter.

If removal of a gauge could result in an immediate loss of purge and/or possible detrimental effect on the equipment, prior written approval and subsequent actions to be taken shall be obtained from the Materials and Project Engineering Sections.

3. If during monitoring, inspection, maintenance or construction activities, it is determined that a purge is lost, a Nonconformance Report shall be initiated for the purpose of Documentation and obtaining Corrective Action.

In addition each Organization responsible for Storage and Maintenance activities was given direction to include these requirements into their respective programs.

Fourteen (14) Storage and Maintenance Instructions (which includes a total of one hundred and twelve (112) pieces of equipment, approximately 222 gauges) were revised to include purge requirements, required pressure ranges, frequency of monitoring and the installation of calibrated gauges where the manufacturers specify the use of calibrated gauges.

't T

.\ .

k PU UC SERVICE

  1. NDIANA Hr. Fiorelli _3 December 30, 1980 The changes as stated should provide a satisfactory resolution to the item of noncompliance.

The above corrective action has been implemented.

Sincer ly, S.W. Shields I

JK/kdt ec: J.G. Keppler E.R. Schweibinz J.J. Harrison

(

! QA Records 02 File l