Provides Revised Fuel Load & Commercial Operation Dates. Unit 1 Fuel Load & Commercial Operation Dates Are Dec 1981 & Aug 1982,respectively.Unit 2 Fuel Load & Commercial Operations Dates Are Aug 1985 & Apr 1986,respectively
ML19341A191
Person / Time
Site: Grand Gulf  Entergy icon.png
Issue date: 01/16/1981
From: Dale L
MISSISSIPPI POWER & LIGHT CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
AECM-81-34, NUDOCS 8101220337
Download: ML19341A191 (1)


Text

]

MISSISSIPPI POWER & LIGHT COMPANY Halping Build Mississippi andaMiddB P. O. B O X 164 0. J A C K S O N. MIS SIS SIP PI 3 9 2 0 5 January 16, 1981 NUCLEAR PAoOUCT1oN oEDARTMENT U.S. Nuclear Reguratory Commission Office of Nuclear Reactor Regulation Washington, D.C.

20555 Attention:

Mr. Harold R. Denton, Director

Dear Sir:

v.

,o

~~

SUBJECT:

Grand Gulf Nuclear Station Units 1 and 2 Docket Nos. 50-416 and 50-417 File 0260/0277/L-860.0/L-952.0 g

Revised Project Schedule AECM-81/34 If Based on a recent re-evaluation of the Grand Gulf project schedule and construction status, MP&L provides the following revised schedule:

Fuel Load Commercial Operation Unit 1 12/81' 8/82 Unit 2 8/85 4/86 This revised schedule information was also provided to the NRC's Office of Management and Program Analysis by MP&L letter AECM-81/29, dated January 16, 1981.

Yours tr_uly, S' L. F. Dale Nuclear Project Manager JGC/JDR:lm cc:

Mr. N. L. Stampley Mr. G. B. Taylor Mr. R. B. McGehee Mr. T. B. Conner Mr. Victor Stello, Jr., Director Division of Inspection & Enforcement i

U.S. Nuclear Regulatory Commission I

Washington, D.C.

20555 fdOf 8101320 @ }

Sf Member Middle South Utilities System