THE CINCINNATI GAS & ELECTRIC COMPANY rip W:
CINCINN ATI CHIC 45208 December 22, 1980 QA-1375 C. A. GORG M AN N vsC C *ettac t%f
~,
U. S. Nuclear Regu'atory Commission h
Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 a
7 2
Attention:
Mr. James G. Keppler, Director
- j RE
- WM. H. ZIMMER NUCLEAR POWER STATICN - UNIT I m
10CFR50.55(e) REPORT NO. M-24, HVAC ISOLATION DAMPERS, DOCKET N0. 50-358, CONSTRUCTION PERMIT NO. CPPR-88, W.0. 57300-957, JOB E-5590 Gentlemen:
This letter is intended to update our interim report dated November 4,1980, concerning the HVAC damper actuator mounts. We had previously estimated comple-tion by December 31, 1980.
We now find that this date cannot be met because our architect-engineer, Sargent & Lundy, has not authorized the rework. Authorization of this rework is dependent upon submission of a revised seismic report by American Warming
& Ventilating, Inc., and its approval by Sargent & Lundy. Until such approval is received, we cannot provide a revised completion date. We will keep you apprised of significant developments as they occur.
We trust that the above will constitute an acceptable interim status report on this item.
Very truly yours,
THE CINCINNATI GAS & ELECTRIC COMPANY
<pe -_ - -
E. A. BORGMANN SENIOR VICE PRESIDENT JFW:ec j
cc: Director, Office of 30/f Inspection & Enforcement, 3
Washington, D. C. 20555 NRC Resident Inspector IO Attn:
F. T. Daniels 80128103fg
--