ML19340C288

From kanterella
Jump to navigation Jump to search
Requests That NRC Revise Scheduling to Support Facility Current 810304 Fuel Loading Date
ML19340C288
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 11/10/1980
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: Schwencer A
Office of Nuclear Reactor Regulation
References
NUDOCS 8011140439
Download: ML19340C288 (1)


Text

.

TENNESSEE VALLEY AUTHORITY 3- -449% CH ATT ANOOG A. TENNESSEE 37 401 400 Chestnut Street Tower II

[,aS November 10, 1960 g

l5WWS Director of Nuclear Reactor Regulation Attention:

Mr. A. Schwencer, Chier Licensing Branch No. 2 Division of Licensing U.S. Nuclear Regulatory Commission Washington, DC 20555

Dear Mr. Schwencer:

In the Matter of the Application of

)

Docket No. 50-328 Tennessee Valley Authority

)

Reference:

Letter from L. M. Mills to A. Schwencer dated June 26, 1980 In the referenced letter you were informed that the earliest completion date for Sequoyah Nuclear Plant unit 2 was January 1981. TVA stated that the January 1981 completion date should be used for licensing schedules.

The current schedule for Sequoyah unit 2 now has March 4, 1981, as the fuel load date. TVA requests that the NRC revise its scheduling in order to support this fuel load date.

Very truly yours, TENNESSEE VALLEY AUTHORITY l

M C M. Mills, Manager Nuclear Regulation and Safety Sworn to d subscribed before me this /O - day of $ 4 &

1980 ARh1 U

Notary Public My Commission Expires oc: Mr. James P. O'Reilly Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Region II - Suite 3100 101 Marietta Street Atlanta, Georgia 30303 8011140e/37 7

An Equal Opportunity Employer