Text

public senrice company oecdonde November 4, 1980 Fort St. Vrain Unit No. 1 P-80390 b

E.n

? 7l 4

c.

Mr. Darrell G. Eisenhut, Director UE Division of Licensing 3:

U. S. Nuclear Regulatory Commission p,

Washington, DC 20555 G

Subject:

Environmental Qualification Testing

Reference:

Letter Eisenhut to PSC dated October 1, 1980 (G80169)

Dear Mr. Eisenhut:

This letter is in response to the above referenced request for information concerning any environmental qualification testing that PSC has scheduled within the next two years.

PSC is in the process of scheduling equipment environmental qualification testing for Steam Line Rupture Qualification for new equipment to be installed at Fort St. Vrain.

The tests will not address areas such as radiation, chemical sprays, submergence and the other environment concerns addressed by IE-Bulletin 79-018.

With this in mind, it is felt that PSC originated testing (HTGR environmental criteria) will be of little use industry wide (LWR criteria).

PSC test infonnation can be provided after tests have been scheduled.

Please contact us if you have any further questions regarding PSC environmental qualification testing schedules.

i Very truly yours, f

g m f.

',4 r,

L l

Frederic E. Swart l

Nuclear Project Manager g

0 Q

FES/ MEN:pa g

so2n so 3)A

.