Forwards Final Response to IE Bulletin 80-09, Hydramotor Actuator Deficiencies. Review Revealed Possible Problem w/30 Actuators.A/E Discussing Problem W/Vendor.Either Springs or Actuators Will Be Replaced
ML19339A707
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 10/23/1980
From: Rausch T
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
References
IEB-80-09, IEB-80-9, NUDOCS 8011040556
Download: ML19339A707 (2)


Text

{{#Wiki_filter:f ^ ~ e g Commonwe:lth Edison /-{ p one First National Plate. Chic 340. Illinois / / 3 i \\ / Addr:ss itply to: Pop OH 03 Box 767 Chicago, Illinois 60690 October 23, 1980 U.S. Nuclear Regulatory Commission Director of Reactor Construction Inspection, 0.I.E. Washington, DC 20555

Subject:

Supplemental Response to IE Bulletin 80-09, "Hydramotor Actuator Deficiencies" LaSalle County Station Units 1 and 2 NRC Docket Nos. 50-373/374 Reference (a): J. G. Keppler letter to C. Reed dated April 17, 1980 (b): T. J. Rausch letter to J. G. keppler dated August 29, 3980

Dear Sir:

The request for information contained in Reference (a) concerning "Hydramotor Actuator Deficiencies", was last responded to in Reference (b), in which it was indicated that more time was required to complete the review for LaSalle County Units 1 and 2. Subsequently telephone canversations with Mr. L. Spessard of Region III were held on Septer.oer 30, 1980 and October 15, 1980 discussing further extensions of the r; ate on which a final response would be provided. The LaSalle County Station review required b; IE Bulletin 80-09 38 now complete, and is contained in the enclosure to this letter. Please address any questions you may have concerning this matter to this office. Very truly yours, f w g [,t%:<l. Thomas J. Rausch Nuclear Licensing Administrator cc: Mr. James G. Keppler, Director Directorate of Inspection and Enforcement - Region III U.S. Nuclear Regulatory Commission 799 Roo;evelt Road Glen Ellyn, IL 60137 RIII Inspector - LaSalle OCT 2 @@ 7634A 8011040556-k

, t. ' * ~ ENCLOSURE Resoonse to IE Bulletin 80-09 LaSalle Station Units 1 ano 2 1 The Station Nuclear. Engineering Department has reviewed 4 the subject bulletin and has the following comments: MCC Powers had reviewed in accordance with the bulletin all safety related actuators at LaSalle County Station, and has revealed a possible problem with approximately 30 actuators. The problems include No. 1 spring. installations in some cases (bulletin item A.) and/or actuator torque requirements below' design minimum (bulletin item 8.). Sargent and Lundy is presently discussing this problem. with the manufacturer of the actuators, ITT General Controls. 4 Either actuator springs will be replaced,.or entire actuators will be added or replaced for the problem devaces.- This will-be completed prior to fuel load for each unit. Once we have determined which actuators must be modified or replaced, the appropriate preoperational test procedures will be revised to verify the corrective actions. i i j i i f 4 1 "T 1 I l i -i l .l 3, i l . _, _., _ _, _...,,, _}}