/LLINO/S POWER COMPANY t.14.go(to.28) 9 500 SOUTH 27TH STREET. DECATUR. ILLINOIS 62525 October 28, 1980 Mr. James Keppler Director, Region,III Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137
Dear Mr. Keppler:
Reference:
Letter L. J. Koch to James G. Keppler, dated August 19, 1980, regarding an interim report (10CFR50.55(e)) con:erning a thin-walled elbow in RPV drain line; U-0170, Ll4-80(08-19)-9.
Clinton Power Station Unit 1 Docket No. 50-461 Construccion Permit No. CPPR-137 The referenced letter stated that " Illinois Power Company now estina.tes that the final report will be filed about mid to late October. 1980".
General Electric Company is experiencing a delay in a vendor reporting on the thin-walled elbow.
Conse-quently, Illinois Power now anticipates that the final report will be filed in early December, 1980.
If you have any comments regarding this information, please notify me as appropriate.
Very truly yours, W
s
^
L./. Koch J
Vice President JBC/ph Director, Office of I&E, NRC, Washington, D.@i#
cc:
H. H. Livermore, NRC Residant Inspector Director, Quality Assurance
\\
be4 3
8011040 $