Responds to 801001 Ltr Re Environ Qualification of safety- Related Equipment.Equipment Description & Sys Where Equipment Installed Included in FSAR Tables 3.10 & 3.11. Tests Will Be Performed in Vendor Shop or by Subcontractor
ML19339A662
Person / Time
Site: Clinton  Constellation icon.png
Issue date: 10/31/1980
From: Wuller G
ILLINOIS POWER CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
U-0196, U-196, NUDOCS 8011040485
Download: ML19339A662 (1)


Text

'

U-0196

., ILLIN0/8 POWER COMPANY ~ } ' L.30.go(tg.31).6

$00 south 27TH STREET, DECATUR, ILLINotS 62525 October 31, 1980 Mr. Darrell G. Eisenhut, Director Division of Licensing Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Dear Mr. Eisenhut:

Clinton Power Station Units 1 & 2 Docket Nos. 50-461 and 50-462 Construction Permits No. CPPR-137 & CPPR-138 In response to your October 1, 1980 letter regarding Environmental Qualification of Safety Related Equipment, we offer the following information regarding Clinton Power Station:

1. The equipment description is partly included in FSAR Tables 3.10-1 and 3.11-9. We are developing further information on this subject and will submit an FSAR amendment.
2. The systems where the equipment is installed are also included in FSAR Tables 3.10-1 and 3.11-9 and are in the same status of FSAR amendment preparation.
3. The tests will be performed either in the vendor shop, or by a subcontractor hired for the qualification.

Most of the equipment has already been tested. A schedule for the tests which have not yet been completed is being prepared and should be available by about January 1, 1981.

4. The cognizant licensee contact for matters related to the tests is-Mr. A. L. Ruwe.

Sincerely,

'/G. E. Wuller

/

Supervisor-Licensing Nuclear Station Engineering Dept.

GEW/ph 300 I cc: B. C. Buckley, NRC Clinton Project Manager H. H. Livermore, NRC Resident Inspector b 8011040/75/