Notification of 801119 & 20 Meetings W/Util in Port Gibson, Ms to Discuss Overall Project Status & Detailed Project Schedule & to Observe Const Activities in Progress
ML19339A392
Person / Time
Site: Grand Gulf  
Issue date: 10/24/1980
From: Martore J
Office of Nuclear Reactor Regulation
To: Miraglia F
Office of Nuclear Reactor Regulation
References
NUDOCS 8011030741
Download: ML19339A392 (6)


Text

.e cero fg UNITED STATES p

NUCLEAR REGULATORY COMMISSION O

E WASHINGTON, D. C. 20555 g

OCT 2 3 1980 Docket Nos. 50-416 and 50-417 MEM RNADUM FOR:

F. Mi rag' io, Acting Chief Licensir.g Branch No. 3, Division of Licensing FROM:

Joseph A. Martore, Project Manager Licensing Branch No. 3, D 6i:?on of Licensing

SUBJECT:

FORTHCOMING CASELOAD FORECA5 PANEL SITE VISIT (GRAND GULF NUCLEAR STATION, UNITS 1 AND 2)

DATE & TIME:

Wednesday, November 19, 1980 9:00 a.m.

Thursday, November 20, 1980 LOCATION:

Grand Gulf Nuclear Station Port Gibson, Mississippi PURPOSE:

To discuss overall project status and detailed project schedule, and to observe construction activities in progress in order to evaluate Unit 1 fuel load date PARTICIPANTS:

MISSISSIPPI POWER AND LIGHT COMPANY L. Dale, J. Richardson, et. al.

NRC J. Martore, W. Lovelace, A. Wagner (Region II)

MATTERS TO BE DISCUSSED:

See Enclosure m

/.n

. f%.;}b.VlL

(

00 7 seph A. Martore, Project Managar

., Licensing Branch No. 3 Division of Licenisng

Enclosure:

Matters to be Discussed cc: See rext page

.so uos o 79/

i 5

Mr. J. P. McGaughy Assistant Vice President - Nuclear Production Mississippi Power & Light Coq,pany P. O. Box 1640 Jackson, Mississippi 39205 cc: Robert 8. McGehee, Esq.

Wise, Cartc, Child, Steen & Caraway P. O. Box bst Jackson, Mississippi 39205 Troy B. Conner, Jr., Esq.

Conner, Moore 8 Corber 1747 Pennsylvania Avenue, N. W.

Washington, D. C.

20006 Mr. Adriar Zaccaria, Project Engineer Grand Gulf Nuclear Station Bechtel Power Corporation Gaithersburg, Maryland 20760 Mr. Alan G. Wagner, Resident Inspector P. O. Box 469 Port Gibson, Mississippi 39150 Mr. John Richardson P. G. Cox 1640 Jackson, Mississippi 39205 S

9 l

i cc: Robert B. McGehee, Esq.

Wise, Carter, Child, Steen & Caraway P. O. Box 651 Jackson, Mississippi 39205 Troy 8. Conner, Jr., Esq.

Conner, Moore & Corber 1747 Pennsylvania Avenue, N. W.

Washington, D. C.

20006 Mr. Adrian Zaccaria, Project Engineer-Grand Gulf Nuclear Station Bechtel Power Corporstion Gaithersburg, Maryland 20760 Mr. Alan G. Wagner, Resident Inspector

?. O. Box 469 Port Gibson, Mississippi 39150 Mr. John Richardson P. O. Box 1640

-Jackson, Mississippi 39205 i

a t

i o

8 J

--,-g

,~,,,m,--

-,,-w----w,,,,r.---ws--

e----

-rr r

-~

,,,--e

ENCLOSURE MATTERS TO BE CONSIDERED

\\

NOVEMBER 19-20, 1980 GRAND GULF NUCLEAR STATION, UNIT 1

.TND NEEDED FACILITIES 1.

Overview of project construction schedule including progress and major milestones completed, since Caseload Panel visit of August 1979, current problems and any anticipated problem areas that may impact the current projected fuel load date.

2.

Detailed review and current status of design and engineering effort (by major discipline) including any potential problems that may arise from necessary rework.

3.

Detailed review and current status of procurement activities including valves, pipe, instruments, cable, major components.

etc.

4.

Actual and proposed craft work force (by major craft), craft availability, productivity, potential labor negotiations and problems.

5.

Detailed review and current status of all large and small bore pipe hangers, restraints, snubbers, etc., including design, rework, procurement, fabrication, delivery and installation.

6.

Detailed review of project schedule identifying critical path items, near critical items, amount of float for various activities, the current critical path to fuel loading, methods of implementation of corrective action for any tetivities with negative float, and provisions for contingencies.

Tae estimated project percent complete as of October 31, 1980.

7.

Detailed review and current status of bulk quantities including current estimated quantities, quantities installed to date, quantities scheduled to date, current percent complete for each, actual versus forecast installation rates, and basis for figures.

(a) Concrete (CY)

(b) Process Pipe (LF)

Large Bore Pipe (2 1/2" and larger)

Small Bore Pipe (2" and smaller)

(c) Yard Pipe (LF)

(d) Large Bore Pipe Hangers, Restraints, Snubbers (ea) t (e) Small Bore Pipe Hangers, Restraints (ea)

(f) Cable Tray (LF)

(g) Total Conduit (LF)

(h) Total Exposed Metal Conduit (LF)

(i) Cable (LF)

Power Control Security Instrumentation Plant Lighting (j) Terminations (ea)

- Power

- Control Security

- Instrumentation Plant Lighting (k) Electrical Circuits (ea)

Power Control

- Security (1) Instrumentation (ea) 8.

Detailed review and current status of preparation of preop test procedures, integration of preop test activities with construction schedule, system turnover schedule, preop test schedule, current and proposed preop test program manpower.

(a) Total num'ser of procedures required for fuel load.

(b) Number 'sf draft procedures not started.

(c) Number of draft procedures being written.

(d) Number of procedures approved.

(e) Number of procedures in review.

(f)' Total number of preop tests required for fuel load.

(g) Number of preop tests completed.

(h) Number of preop tests currently in progress.

(1) Number of systems turned over to start-up.

b.

t 9.

Detailed discussion of potential schedular influence due to changes attributed to NUREG-0660, NUREG-0694 and ether recent licensing requirements.

10. Site tour ano observation of construction activities.

I

11. Discussion of 50.55e items which may have an impact on the construction completion schedule.