i
./
" 'N Commonwealth ? ' son
/
)
'k O ~ One First N'bonal Ptk.. Chicago, ininoir Addr:ss R; ply to: Post Off c3 Box 767
\\
Chicago. Illinois 60690
'pc@tto:T' h)~?N, Apr*,
76 9
\\
N
{
wmno t >:
Mr. Karl R. Goller
'I e.
S
- h g,2
~
A 01 BIS %g 4
p Assistant Director for Operating Reactors g
/J
.w Division of Operating Reacto U.S. Nuclear Regulatory Commi
'v i [ g Washington, D.C.
20555
Subject:
Dresden and Quad-Cities Stations FSAR Modification No. 73-1 NRC Docket Nos. 50-10, 50-237, 50-249, 50-254, and 50-265 Reference (a) :
G. A. Abrell letter to K. R. Goller dated January 30, 1976
Dear Mr. Goller:
Reference (a) estimated a May 1, 1976 completion date
'for reformatting of all the Dresden and Quad-Cities procedures.
At this time, it is anticipated that Dresden Station's surveillance procedures will be approximately 80 percent complete by May 1 and will be 100 percent complete within two weeks.
De-partmental PDcedures are expected to be reformatted by June 1, 1976.
The manpwer demands of the current refueling outage and continued problems of compatibility of the automatic typewriters used for the procedure writing have accounted for the additional delay.
Quad-Cities Station still estimates completion by May 1, 1976.
Very-truly yours,
- G.
A. ::==e u 2cletr id eer.rir- '.i.i.irtrt:cr E0ilir.g U :cr T.ct r:cr Sul0140 202$