Requests Withdrawal of Revision to License Condition 2.C 3h Re Completion Date for Fire Protection Mods
ML19338E957
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 09/30/1980
From: Crouse R
TOLEDO EDISON CO.
To: Reid R
Office of Nuclear Reactor Regulation
References
654, NUDOCS 8010060359
Download: ML19338E957 (1)


Text

TOLEDO EDISON RcmAso P CAOUSE O.N~

Docket No. 50-346 i4is: ass sra, License No. NPF-3 Serial No. 654 September 30, 1980 Director of Nuclear Reactor Regulation Attention:

Mr. Robert W. Reid, Chief Operating Reactors Lranch No. 4 Division of Licensing United States Nuclear Regulatory Commission Washington, D.C.

20555

Dear Mr. Reid,

In a July 1, 1980 submittal (Serial No. 625), Toledo Edison requested a revision in License Condition 2.C(3)h for the Davis-Besse Nuclea.r Power Station, Unit 1.

This was to extend the completian date for fire protection modifications. Due to the completion of the modifications, the requested res.sion is no longer required and Toledo Edison withdraws its request.

Very truly yours, A*

/t 4y RPC:TJM: sic cc: NRC D-B 1 Resident Inspector

}) col s,

,/'

i/v THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO. OHIO 43652 80100003

{